Resolved
(i) That the appointment of Company A (Kingdom Security Ltd) to deliver the supplementary environmental enforcement service from 1 April 2016 until 31 March 2019 (with an option to extend for a two further years) be agreed.
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 3 February 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) That the appointment of Company A (Kingdom Security Ltd) to deliver the supplementary environmental enforcement service from 1 April 2016 until 31 March 2019 (with an option to extend for a two further years) be agreed.
1.2A six month pilot project to tackle littering and dog fouling commenced on 24th March 2015. The pilot was later extended until 31st March 2016. The pilot utilises the services of an external contractor called ‘Kingdom Security Ltd’ to issue Fixed Penalty Notices (FPNs) to persons caught dropping litter within the borough. The pilot project has been funded through the FPN payments.
2.2The officers on the street are highly visible and the scheme has received strong support from residents and the media. Over 1400 FPNs have been issued since March 2015.
2.3Approximately 70% of the FPNs are paid, with the remainder potentially facing court action. Recently ten cases were taken to court by Swale BC, all of which were successful. It is anticipated that between ten and twenty cases will be taken to court on a monthly basis from January 2016.
2.4Based upon the following factors, the pilot has been a success: Litter levels remaining low and within target. A highly visible presence on the streets to tackle environmental crime. Improved Local Area Perception Survey figures for cleanliness. Positive media interest.
2.5It was agreed at SMT on 11th August 2015 and by the Cabinet Member for Environment and Rural Affairs, to carry out a procurement exercise to appoint an external contractor to continue to provide this supplementary service when the pilot project ends on 31st March 2016.
Procurement of New Contract
2.6An OJEU open procurement was undertaken in October 2015 resulting in two companies submitting tenders for the work. These were evaluated and scored according to the procurement process i.e. 40% on price and 60% on quality. The tenders were evaluated on 26th October 2015 by the Head of Economy and Community Services, the Environment Response Manager, and the Principal Environment Warden. The tender price and quality scores are shown in table 1 below.
Table 1: Scores at assessment panel stage
2.7As two companies applied (whereas three submissions are usually required), a procurement waiver has been agreed on the basis that the opportunity was correctly advertised and it was open to reasonable competition and that nothing more could have been done to secure better value for Swale BC.
2 Proposal
3.1To approve the appointment of Company A to deliver the supplementary environmental enforcement service from 1st April 2016 until 31st March 2019 (with an option to extend for two further years).
4.1To stop the project. This is not recommended as the pilot has proved to be successful and it shows that Swale BC takes resident feedback seriously. Engagement surveys and the Local Area Perception Surveys show that cleaner streets are a priority for residents, and this project tackles the source of the problem. The withdrawal of the service may have a detrimental effect on street cleanliness and thus perceptions of the area as well as the reputation of Swale BC in tackling customer priorities. 5 Consultation Undertaken or Proposed
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tackling Litter: a new approach to Fixed Penalty NoticesReport | 76 KB | DownloadRead as text |
Follow Cabinet - Decommissioned 18.05.2022 at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Apr 2022 | Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I... | Noted | Open |
| 13 Apr 2022 | Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro... | Noted | Open |
| 13 Apr 2022 | Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ... | Agreed | Open |
| 13 Apr 2022 | Beam Partnership - Housing and Employment Support(1) That a spend and save pilot in partnership with Beam be entered into. | Decided | Open |
| 13 Apr 2022 | Project Funding(1) That the schemes funded from the Improvement & Resilience Fund, the Special Projects Fund and the High Street Fun... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.