Dolphin Barge Museum - Option agreement for land transfer to Swale Borough Council from Essential Land and a proposed new lease to the Dolphin Barge Museum
AgreedExecutive2 papers
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 2 March 2016. Below is the council's own wording, with the papers it was decided on.
(1) That delegated authority be given to the Head of Property Services in consultation with the Cabinet Member for Finance and the Cabinet Member for Localism, Sport, Culture and Heritage to draw down land on the Wharf site in Sittingbourne under an option agreement with Essential Land to be used for a new Dolphin Barge Museum. (2) That delegated authority be given to the Head of Property Services in consultation with the Cabinet Member for Finance and the Cabinet Member for Localism, Sport, Culture and Heritage to enter into a new 125 year lease with The Dolphin Barge Museum for Land on the Wharf Site in Sittingbourne to be used to construct, maintain and operate a new Dolphin Barge Museum.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Report Title Dolphin Barge Museum - Option agreement for Land transfer to Swale Borough Council from Essential Land and a proposed new lease to the Dolphin Barge Museum Portfolio Holder Councillor Mike Whiting, Cabinet Member for Localism, Sport, Culture and Heritage SMT Lead Kathryn Carr, Director of Regeneration
Head of Service Anne Adams, Head of Property Services
Lead Officer Peter Binnie
Key Decision No
Classification Open
Forward Plan Reference number:
Recommendations 1. That Cabinet delegates authority to the Head of Property in consultation with the Cabinet Member for Finance and the Cabinet Member for Localism, Sport, Culture and Heritage to draw down land on the Wharf site in Sittingbourne under an option agreement with Essential Land to be used for a new Dolphin Barge Museum 2. That Cabinet delegates authority to the Head of Property in consultation with the Cabinet Member for Finance and the Cabinet Member for Localism, Sport, Culture and Heritage to enter into a new 125 year lease with The Dolphin Barge Museum for Land on the Wharf Site in Sittingbourne to be used to construct, maintain and operate a new Dolphin Barge Museum.
1. Purpose of Report and Executive Summary
1.1This purpose of this report is to seek member’s approval to execute an option agreement for the Council to obtain Land to site B as shown in blue at appendix (i) at the Wharf site in Sittingbourne from Essential Land ( the owners) at no cost to the Council. The option agreement also includes a right of access to construct and use a 3m wide access road across the adjacent site as shaded in blue.
1.2The report also seeks member approval to enter into a 125 year lease with the Trustees of the Dolphin Barge Museum for them to construct, manage, maintain and operate a barge museum on the site for the duration of the lease. 2. Background
2.1As part of an original Section 106 agreement for the development of the Wharf and Mill sites in Sittingbourne there was a provision for an area of the Wharf site to be landscaped to provide a waterside park and then transferred to the Council with a commuted sum for maintenance.
2.2Negotiations between Essential Land and the Council’s planning department resulted in the Planning Committee resolving that the original section 106 could be varied due to viability and when in due course the deed of variation is entered into any obligation to make a payment to the Council or provide a landscaped water park will be removed though the applicant remains willing to transfer the land to the Council.
2.3The Dolphin Barge Museum has submitted a planning application that has now been approved and has funding from an insurance claim to construct a new barge museum on the site.
2.4The Dolphin Barge Museum is negotiating with two contractors to fix a price for the construction and subject to agreeing costs and satisfying planning conditions are in a position where it can start construction in the very near future.
2.5The Council’s Legal team have negotiated an option agreement with Essential Land for the draw down of land for the Dolphin Barge Museum including for an access agreement across the remaining land. See appendix (i) for land to be transferred shown as site B edged in blue and the agreed 3m wide access road shown shaded in blue.
2.6It is intended that the land will be drawn down by the Council and then subject to a 125 year lease between the Council and The Dolphin Barge Museum.
2.7The Dolphin Barge Museum will be responsible under the lease for the cost of construction and the ongoing operation and maintenance of the Museum and the associated land including all DDA and Health and Safety requirements.
3. Proposals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Dolphin Barge Museum: Option agreement for land transfer to Swale Borough Council from Essential Land and a proposed new lease to the Dolphin Barge MuseumReport
553Dolphin Barge Museum - Option agreement for land transfer to Swale Borough Council from Essential Land and a proposed new lease to the Dolphin Barge MuseumThis decision
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.