Resolved
(1) That the Head of Economy and Community Services be authorised, in consultation with the Cabinet Member for Finance and Performance, to approve the appointment of the Groundworks Contractor for the Great Easthall Community Centre.
Cabinet - Decommissioned 18.05.2022 approved this item on Wednesday 15 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the Head of Economy and Community Services be authorised, in consultation with the Cabinet Member for Finance and Performance, to approve the appointment of the Groundworks Contractor for the Great Easthall Community Centre.
Cabinet Meeting Agenda Item: 5 Meeting Date 15 June 2016
Report Title Award of Groundworks Contract for Great Easthall Community Centre. Cabinet Member Cllr Duncan Dewar-Whalley, Cabinet Member for Finance. SMT Lead Kathryn Carr, Director of Regeneration
Head of Service Emma Wiggins, Head of Economy and Community Services Lead Officer Charlotte Hudson, Economy and Community Services Manager Key Decision No
Classification Open
Forward Plan Reference number:
Recommendations 1. To delegate authority to the Head of Economy and Community Services, in consultation with the Cabinet Member for Finance and Performance, to approve the appointment of the Groundworks Contractor for the Great Easthall Community Centre.
1 Purpose of Report and Executive Summary 1.1 This report provides Cabinet with an update on progress of the Great Easthall Community Centre project, and requests delegated authority to award the Groundworks contract to the preferred supplier.
2 Background 2.1 Great Easthall is a new build development within Sittingbourne. The development was subject to a S.106 agreement that provided £1.2 million and land for the construction of a community centre.
2.2The S.106 was varied in 2014 to allow for the funding to be provided up front at a reduced amount of £1.02 million, on the proviso that the scheme was completed by March 2017.
2.3Land has been allocated for the Community Centre, and its freehold transfer (from owners Medical Centre Developments) is currently being finalised by Legal Services under the terms of the S.106. 2.4 A professional team has been appointed and consists of a Project Manager, Architect (Principal Designer), Cost Consultant, Mechanical and Electrical Engineer, and Civil, Structural and Public Health Engineer. The team has progressed with the design of the community centre based on an overall construction budget of £810k. The current programme aims for completion in February 2017.
2.5Due to construction price inflation and in order to maximise value for money, the project team agreed a construction management route for the procurement of the project. The Construction Manager was appointed by Cabinet in February 2016, and he has overall management of the site and preliminaries. The various sub- packages that constitute the build were planned to be procured separately, thus reducing the overhead and profits that a main contractor would achieve, so mitigating any construction price inflation to maintain the project within the budget parameters.
2.6The procurement of the build was developed into 18 lots, and their procurement was conducted as an open tender, advertised through the Kent Business Portal and SBC Website. The tender was issued to all those organisations who had expressed an interest.
2.7This report specifically relates to the Groundworks package. The remaining 17 lots are being evaluated, and all those under the threshold for Cabinet decisions will be appointed under delegated authority of the Head of Service in consultation with the Cabinet Member for Finance and Performance, with the remainder due to be brought forward to award at Cabinet in July.
Groundworks Tender
2.8The procurement of the Groundworks package did not attract any compliant tenders. Following this unsuccessful tender process, legal advice was sought, as a result of which open negotiations were entered into with the non-compliant tenderer and the Construction Manager to obtain these services directly from their supply chain as an alternative procurement route.
2.9The Construction Manager has obtained three quotes from their supply chain and agreed to work under an open book management recharge system with a transparent overheads and profit uplift for the total sum.
3 Proposals
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Great Easthall Construction Packages TenderReport | 89 KB | DownloadRead as text |
Follow Cabinet - Decommissioned 18.05.2022 at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Apr 2022 | Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I... | Noted | Open |
| 13 Apr 2022 | Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro... | Noted | Open |
| 13 Apr 2022 | Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ... | Agreed | Open |
| 13 Apr 2022 | Beam Partnership - Housing and Employment Support(1) That a spend and save pilot in partnership with Beam be entered into. | Decided | Open |
| 13 Apr 2022 | Project Funding(1) That the schemes funded from the Improvement & Resilience Fund, the Special Projects Fund and the High Street Fun... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.