Approval of New Play Area, trim trail and play area improvements
DecidedExecutive4 papers
Cabinet - Decommissioned 18.05.2022 decided this item on Wednesday 7 December 2016. Below is the council's own wording, with the papers it was decided on.
(1) That the contract for the Thistle Hill Play areas be awarded to HAGS-SMP, for the sum of £169,976.98 (2) That the contract for the Thistle Hill Trim Trail be awarded to Wicksteed Playgrounds, for the sum of £33,385.00 (3) That the contract for the ‘all-inclusive’ play equipment at King George’s Playing Field, Sittingbourne be awarded to Proludic Ltd, for the sum of £5,300.00. (4) That the Head of Commissioning and Customer Contact and Head of Legal, in consultation with the Cabinet Member for Environmental and Rural Affairs, be delegated to complete the contract awards.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Cabinet Meeting Agenda Item: 9 Meeting Date 7 December 2016
Report Title Awarding of Contract - New play areas, new trim trail and play area improvements. Cabinet Member Cllr David Simmons, Cabinet Member for Environment and Rural Affairs SMT Lead Dave Thomas
Head of Service Dave Thomas
Lead Officer Daniel Gooch
Key Decision Yes
Classification Open
Forward Plan Reference number:
Recommendations 1. That the contract for the Thistle Hill Play areas be awarded to HAGS-SMP, for the sum of £169,976.98. 2. That the contract for the Thistle Hill Trim Trail be awarded to Wicksteed Playgrounds, for the sum of £33,385.00. 3. That the contract for the ‘all-inclusive’ play equipment at King George’s Playing Field, Sittingbourne be awarded to Proludic Ltd, for the sum of £5,300.00. 4. To delegate authority to the Head of Commissioning and Customer Contact and Head of Legal, in consultation with the Cabinet Member for Environmental and Rural Affairs, to complete the contract awards.
1 Purpose of Report and Executive Summary
1.1This report provides an explanation of the tender process to appoint contractors to undertake the following: design and installation of new Toddler and Junior Play areas at Thistle Hill; design and installation of new exercise trim trail at Thistle Hill Community Woodland; and design and installation of additional ‘all-inclusive play’ equipment at King George’s Playing Field, Sittingbourne.
1.2Following the tendering process and evaluation by an assessment panel, this report requests authority to award the three contracts to the winning tenders. 2 Background
2.1The Council has invested significantly in the refurbishment of priority play equipment across the Borough. The major projects completed to date include repainting and replacement of parts at Leysdown Coastal Park, Minster Leas outdoor gym equipment, Rushenden Hill play area embankment steps, Reedland Crescent play area (Faversham), and Sittingbourne Recreation Ground play area.
2.2On top of this, SBC is in receipt of S106 funding for the development of new play areas and trim trail at Thistle Hill, as well as a small external fund for ‘all inclusive’ play at King George’s Playing Field play area. Commuted sums assist with the ongoing maintenance of these additional play facilities.
ESPO Framework
2.3Swale Borough Council has used the ESPO Framework 115 to obtain designs and quotes from leading play companies for these works. The ESPO Framework is a national framework agreement which uses standardised criteria to help public bodies make decisions on suitability, and replaces the need for Council officers to ask play companies to complete a pre-qualification questionnaire. All play companies on the Framework are pre-approved, thus reducing Council staff time in the procurement process. It is a requirement under the Framework to invite all relevant companies on each corresponding lot to submit a bid.
Thistle Hill Toddler and Junior Play Areas
2.4The play areas, suitable for toddlers (0-6 years) and juniors (6-12 years), were set out as part of the planning permission for the new Thistle Hill housing development, along with a number of other ‘satellite’ play areas already installed in the last few years.
2.5They will be situated in the already landscaped and fenced area next to the Thistle Hill Community Centre in Laurel Road, and are intended to be the destination play areas of the development.
2.6Nine play companies were contacted (as per the ESPO Framework) to submit designs. The specification included providing themed play areas taking inspiration from the history of the Isle of Sheppey. Eight different designs were received.
Thistle Hill Community Woodland Trim Trail
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.