Resolved
(1) That the Corporate Level risks for Swale Borough Council be noted.
Audit Committee noted this item on Wednesday 14 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the Corporate Level risks for Swale Borough Council be noted.
Appendix I
MID KENT AUDIT
Risk Management Update
Audit Committee
March 2018 Introduction Effective risk management is a vital part of the Council’s governance, and contributes greatly to the successful delivery of services and the key priorities. The Council has always recognised and supported the need to have effective risk management processes, and so, in early 2015 sought to update and refresh procedures and guidance.
As part of this work, we (Mid Kent Audit) took lead responsibility to co-ordinate the update across the council to embed revised risk management processes. Our role includes reporting regular updates to Officers and Members, through the Strategic Management Team (SMT), Informal Cabinet and the Audit Committee, providing workshops and training, and helping to ensure risks are being effectively managed.
Having valuable and up to date risk information enables both Executive and oversight functions to happen effectively. Executive management has the role to review the substance of individual risks to ensure that risk issues are appropriately monitored and addressed. As those charged with governance, the Audit Committee seeks assurance that the Council operates effective risk management.
Purpose In March last year we reported our first risk report to the Audit Committee. This report builds on our previous update and seeks to provide Members with an overview of the Council’s risk management arrangements, thus enabling the committee to fulfil the responsibilities as set out in the Terms of Reference:
“To monitor the effective development and operation of risk management and corporate governance in the Council”
This report should be used to provide assurance to Members that the Council has effective risk management, and that risks identified through that process are managed, and monitored appropriately.
1 Risk Management Process The risk management framework is a guide that sets out how the Council identifies, manages and monitors risks.
In summary, the risk management process for the Council can be broken down into the following key components (see also Appendix II):
Objectives
Monitoring Risk & Identification Reporting Risk Management Guidance
Risk Risk Treatment Evaluation
All risks are recoded on the comprehensive risk register, and it is this register that is used to generate risk information across the Council.
We generally identify risks at two levels, at an operational level and at a corporate level:
Corporate level risks are more strategic in nature; the management of these risks is co-ordinated and overseen by SMT quarterly, Informal Cabinet twice a year, and annually by the Audit Committee. By definition, these risks inherently carry a higher impact level as they affect multiple services. They are the risks that could prevent the Council from achieving its ambitions and objectives.
The corporate level risks were last updated and reviewed in November 2017 and will be reviewed and updated again in March/April 2018.
Operational risks are principally identified as part of the service planning cycle each year. Throughout the year these risks are reviewed, updated and reported to SMT quarterly. Operational level risks are more directly linked with our day to day operation of services. However, operational risks can nonetheless have potential for significant impact.
Operational risks were updated in February 2018, and will continue to be updated between March and April 2018 as service plans are created.
2 Operational Risk Profile All Council services maintain a risk register. These individual risk registers collectively form the comprehensive risk register, and it is this complete register that is used to compile the risk update reports on a regular basis.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ITEM 6 Appendix I: FINAL Risk Management Update 17-18Appendix | 879 KB | DownloadRead as text |
PDF |
Strategic Risk Register and Action PlansPlan | 64 KB | Download |
Follow Audit Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Internal Audit Annual Report and Audit Opinion 2025/26(1) That the Head of Audit Partnership’s Annual Audit Opinion for 2025/26 be noted. (2) That the work underlying the ... | Noted | Open |
| 15 Jul 2026 | Annual Treasury Management Report 2025/26(1) That the Treasury Management outturn report for 2025/26 be noted. | Noted | Open |
| 13 May 2026 | Election of Chair(1) That Councillor Charles Gibson be elected as Chair for the municipal year 2026/27. | Decided | Open |
| 13 May 2026 | Election of Vice-Chair(1) That Councillor Simon Clark be elected as Vice-Chair for the municipal year 2026/27. | Decided | Open |
| 22 Apr 2026 | Internal Audit and Assurance Plan 2026/27(1) That the Internal Audit & Assurance Plan for 2026/27 be approved and that the Head of Audit Partnership be given ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.