Queenborough and Rushenden Regeneration scheme funding agreement and consultant appointments
AgreedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 12 December 2018. Below is the council's own wording, with the papers it was decided on.
(1) That the Director of Regeneration and the Chief Financial Officer, in consultation with the Cabinet Member for Regeneration and the Cabinet Member for Finance and Performance, be given delegated authority to enter into the Homes England Grant Determination Agreement to provide £3.5 million HIF funding to support the Queenborough and Rushenden regeneration scheme, and staff resources allocated to administer the funds in-line with requirements. (2) That the Director of Regeneration and the Chief Financial Officer, in consultation with the Cabinet Member for Regeneration and the Cabinet Member for Finance and Performance, be given delegated authority to make a direct award to a consultation on the Homes England framework to produce the tender specification documents and manage the procurement of the contractors required to deliver the works included within the HIF spend profile, plus the subsequent contract delivery project management.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Cabinet Member Cllr Mike Cosgrove, Cabinet Member for Regeneration
SMT Lead Emma Wiggins, Director of Regeneration
Head of Service Charlotte Hudson, Head of Housing & Economy Services
Lead Officer Debbie Townrow, Economic Development Officer
Key Decision Yes
Classification Open
Recommendations 1. To provide delegated authority to the Director for Regeneration and the Chief Financial Officer in consultation with the Cabinet Member for Regeneration and the Cabinet Member for Finance & Performance to enter into the Homes England Grant Determination Agreement to provide £3.5million HIF funding to support the Queenborough & Rushenden regeneration scheme and staff resources allocated to administer the funds in line with requirements. 2. To provide delegated authority to the Director for Regeneration and the Chief Financial Officer, in consultation with the Cabinet Member for Regeneration and the Cabinet Member for Finance & Performance to make a direct award to a consultant on the Homes England framework to produce the tender specification documents and manage the procurement of the contractors required to deliver the works included within the HIF spend profile plus the subsequent contract delivery project management.
1 Purpose of Report and Executive Summary 1.1 Housing Infrastructure Funding of £3.5 million has been secured from Homes England to assist the delivery of the infrastructure improvements required to enable Phase 4 of the Queenborough and Rushenden regeneration scheme to be developed.
1.2This report seeks to gain approval for entering into the Grant Determination Agreement (GDA) with Homes England to enable Swale to receive the funds and allocate staff resources to administer the funds in line with the GDA’s requirements. 1.3 This report also seeks to gain delegated authority to enable a consultant to be appointed from Homes England’s multi-disciplinary framework to produce the tender specification documentation and manage the procurement process to appoint the contractors required to deliver the works detailed in the HIF spend profile, plus the subsequent contract delivery project management.
2 Background 2.1 In 2017, Swale Borough Council made a bid of £3.5 million to the Housing Infrastructure Fund (HIF) Marginal Viability funding for the Queenborough and Rushenden Regeneration scheme. The HIF scheme was designed to provide grant funding for new infrastructure that unlocks the ability to provide new homes in the areas of greatest housing demand. For the Queenborough & Rushenden scheme, this money will pay for:
land raising works to bring the development area for phase 4 out of the flood zone; site clearance and land remediation works required to enable development to commence.
2.2On 26th September 2018, we received a formal offer letter and the associated Assurance Framework from Homes England for this funding, which details the key terms which forms the basis of the GDA to be signed between ourselves and Homes England.
2.3Officers have carried out due diligence on the information received to date and will do so with the GDA once received. Mid-Kent Legal Services have indicated that the contents of the document appear to be acceptable, at this stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.