Fourth Deed of Variation to the Development Agreement between the Council and Spirit of Sittingbourne
AgreedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 agreed this item on Wednesday 25 September 2019. Below is the council's own wording, with the papers it was decided on.
(1) That authority be delegated to the Director of Regeneration to agree a fourth Deed of Variation to the Development Agreement between the Council and Spirit of Sittingbourne to extend the long stop date for the drawdown of land to the residential elements of Phase 1 of the Development Agreement.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1The Development Agreement between the Council and Spirit of Sittingbourne allows for the construction of 212 residential units on Cockleshell Walk, Spring Street and Fountain street.
2.2The Development Agreement contains several conditions and longstop dates for the Development Agreement between the Council and Spirit of Sittingbourne that is to be delivered in two distinct phases, Phase 1 and Phase 2. Phase 1 comprised significant roadworks and infrastructure that are substantially complete, a retail park that is complete and open to business, a Multi Storey Car Park that is complete, a Cinema, Hotel and public open space that will be completed by the end of the year and the three residential site that have not yet started.
2.3Considering the Coalition’s priorities, particularly in relation to affordable housing Officers engaged with Spirit of Sittingbourne to consider ways in which the residential phase could be substantially revised. These discussions are ongoing and as a result Spirit could not meet the timescale for the satisfaction of the Viability Condition and the Council’s Funding Condition. In order continue discussions Spirit of Sittingbourne has requested a 3-month extension to the Longstop Date for drawdown of the Building Leases to the three residential sites. In undertaking discussions intended to achieve better outcomes the Council has to act “reasonably” which is why the request for the extension of the long stop date is made.
3 Proposals
3.1It is proposed to extend the Longstop Date for draw down of the Building Leases to sites 1,2 and 3 in the Development Agreement between the Council and Spirit of Sittingbourne under a fourth Deed of Variation by three months that will extend the due date to the 29 October 2019.
3.2The extension of the long stop date will allow the Council and Spirit to continue their discussions.
Alternative options
4.1The revised Longstop Date is not agreed, and the Council will have to consider approval on the original submission and whether the conditions have been met, this is not recommended as we are seeking a better solution and Legal advice has indicated that we need to act reasonably.
5 Consultation Undertaken or Proposed
5.1Advice has also been taken with Legal and Commercial advisors.
6 Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.