CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Scrutiny Committee - Decommissioned 18.05.2022, Wednesday 15 January 2020 at 7.00pm

Other Review Progress Reports

Noted Scrutiny 1 paper

Scrutiny Committee - Decommissioned 18.05.2022 noted this item on Wednesday 15 January 2020. Below is the council's own wording, with the papers it was decided on.

Item453

Resolved

(1) That the tabled update report be noted. (2) That the progress letter sent to residents and business on 10 January 2020 be circulated to all Members.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Scrutiny Committee - Decommissioned 18.05.2022

Tabled

Sittingbourne Town Centre Regeneration Update to Scrutiny Committee 15th January 2020

Progress Update SPIRIT OF SITTINGBOURNE Highway Works Erith continue with the drainage works associated with Section 2 S278 and S104/S185 works in Fountain Street, Dover Street and Spring Street car park and the turning head retaining wall and capping beam in Fountain Street. Spirit/Erith continue to implement the additional items in the bus stop area that were agreed with KCC and the bus operators. Southern Gas Networks have now completed their repair works adjacent to one of the shelters however the shelter has not yet been re-installed by Erith’s sub- contractor. The bus stop area should be fully open to the public in February when the outstanding items are complete. The Principal designer (highways) and KCC Highways Development Team have now agreed an extensive specific and non-specific (generalised) snagging/defects list for all areas of Erith’s work previously carried out. This includes civils work as well as carriageway resurfacing that will need to be re-done before KCC issue the initial completion certificate. Spirit await to receive Erith’s own list of snagging/defect items along with a completion programme. The resurfacing work that needs to be re-done in the one- way, in Park Road, in Station Street, in the bus stop area and in front of the station is now planned to be done in the Spring when overnight temperatures are warmer. Spirit also expect the snagging/defects items to be complete by the end of April.

Leisure Development PDR has now removed the leisure site hoarding adjacent to (Bourne Place) the Forum car park and access road and has now installing the precast concrete retaining wall along the Western boundary. PDR has also relocated their site offices onto the Western edge of the Forum car park with Praxis’ agreement to enable them to commence with the hard landscaping (paving) throughout the site.

The power to the integral substation has now been energised and the electricity meter was installed/commissioned within the hotel on 3rd January. Due to the stringent earthing levels required by the Travelodge PDR have had to order additional equipment to ensure they obtain the correct readings. This equipment should be delivered and fitted by the end of January.

The commissioning of all remaining M&E plant/equipment within the hotel is now underway and well as final carpet laying and snagging throughout.

Due to issues BT have encountered off site to enable them to get BT lines to the hotel Spirit has now provided an instruction to PDR to install additional ducting for BT lines across the site from Station Street to the hotel.

An article was recently released in ‘kentonline’ on 2nd January stating that the hotel would hopefully open on 17 th February however PDR have yet to provide the required notice to Spirit (4 weeks) and Spirit have yet to provide the required notice to the Travelodge (10 days) so this date has not yet been confirmed. This information came from an unknown source and therefore Spirit are following this up with their Comms team and Travelodge’s construction team to ensure that the correct information is provided when it is known.

UKPN are due on site again on 13th & 14th January to connect the power supply to units 3a, 4 & 5 (the units currently with agreements for lease). Once UKPN has completed their works in this location the gas and BT connections can be installed into these units.

Nando’s contractor are coming to site towards the end of January to fit their electricity meter within their unit.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Other Review Progress ReportsReport 120 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 24 attended
MB
Monique BonneyVisiting Councillor, in attendance
LB
Councillor Lloyd BowenChair, present
RC
Roger ClarkVisiting Councillor, in attendance
RD
Councillor Richard DarbyCommittee Member, present
SD
Councillor Steve DaveyCommittee Member, present
MD
Councillor Mike DendorVice-Chair, present
TG
Councillor Tim GibsonCommittee Member, present
AG
Councillor Alastair GouldCommittee Member, present
JH
Councillor James HallCommittee Member, present
AH
Alan HortonVisiting Councillor, in attendance
KJ
Kenneth John IngletonVisiting Councillor, in attendance
CJ
Councillor Carole JacksonCommittee Member, present

All 24 on the meeting page

On this subject at Swale

Search all
  1. Other Review Progress ReportsThis decision
  2. Other Review Progress ReportsNoted
  3. Other Review Progress ReportsDecided
  4. Other Review Progress ReportsDeferred
  5. Other Review Progress ReportsNoted
  6. Other Review Progress ReportsNoted

More from Swale Scrutiny Committee - Decommissioned 18.05.2022

All decisions
MeetingDecisionOutcome
23 Mar 2022 Performance Monitoring Report(1) That the report be noted. Noted Open
23 Mar 2022 Cabinet Forward Plan(1) That the Forward Plan be noted. Noted Open
19 Jan 2022 Cabinet Forward Plan(1) That the report be noted. Noted Open
17 Nov 2021 Cabinet Forward PlanThat the report be noted. Noted Open
17 Jun 2021 Sittingbourne Town Centre Update(1) That the Sittingbourne Town Centre update be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies