(1) That the updated 2020/21 Internal Audit and Assurance Plan be approved. (2) That the approach for keeping the plan current through the year be noted. (3) That the Head of Audit Partnership’s conclusion that he had updated the plan with independence and objectivity, free from undue influence be noted.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Changed Internal Audit & Assurance Plan 2020/21 About the Plan and Planning
1. The Public Sector Internal Audit Standards (the “Standards”) set out how we must approach audit planning. Specifically, the Standards say that we “must establish risk- based plans to determine the priorities of internal audit, consistent with the organisation’s goals”. The Standards note this must support the annual opinion but there is no direction for an annual plan. On the contrary, the Standards expect Heads of Audit should adapt plans to reflect developing risks.
2. There can be little doubt the Covid-19 emergency has significantly altered the authority’s risks and priorities for 20/21. We summarised in our Annual Report a few of the ways that this impacted the audit team specifically, most obviously in diverting audit time towards the emergency response.
3. Given the scale of change, we wanted to bring the plan back to Members so they could see changes since the Spring. Our aim is providing visibility on the changes and reassuring Members that we have (and will continue to) keep the plan flexible.
4. Risk Sources and Information
5. In preparing this plan we consulted widely within the audit profession. This included leveraging our sector groups for information, including the newly formed Institute of Internal Audit Local Government Forum and the Local Authority Chief Auditors’ Network. We also conducted research on published audit plans across various authorities, paying attention to changes that would be relevant in Mid Kent.
6. We also consulted senior managers across the Council on changes to their risks and priorities. This plan reflects the result of these risks, which we will keep under review.
7. Audit Resources
8. Within Mid Kent Audit, Covid-19 has had various impacts on the 1,810 available days across the partnership for the audit year 2020/21. The most significant impacts, at partnership level:
- 190 days of 2019/20 work displaced into 2020/21 by early redeployment.
- 70 days of redeployment in the 2020/21 audit year.
- 175 days resulting from holding a vacancy while councils consider their longer term resource positions, and seeking to bring forward 2020/21 year end to avoid risk of overspill into 2021/22. 9. The table below shows how this impacts audit time at Swale Borough Council
ORIGINAL: LESS: LESS: LESS: FINAL: DAYS IN 20/21 IN-YEAR PRIOR YEAR VACANCY & REMAINING PLAN REDEPLOYMENT WORK BFWD YEAR-END DAYS 450 (16) (44) (40) 350 270 Risk Based Audit 218 120 Governance 84 60 Consultancy 48
10. Although this represents a loss of time, we have tried to concentrate this on consultancy and governance roles. This may mean that some desirable tasks such as introducing software to track risk will experience delay.
Substantive Plan Changes
11. The table below shows planned changes to audit engagements.
Engagement Title Priority & Change Comments Change CCTV High Fall in activity lowers audit risk Removed Leisure Contract Management High Significant fall in operating hours of Removed facilities lowers audit risk Equalities Medium Removed to focus audit time on higher Removed priority areas Planning Administration Medium Significant fall in application numbers Removed lowers audit risk Traffic Regulation Orders Medium Significant fall in traffic in early part of the Removed year lowers audit risk. Community Hub Support High New high profile and spend service Added delivered at start of the year. Audit will aim to provide assurance on controls within the Hub. Remote IT Access High Significant increase in remote access Added demands with homeworking. Audit will examine arrangements for managing access and keeping systems accessed remotely secure. 12. We list below the unchanged engagements on the plan. We are not currently expecting headline changes to these engagements. However we will enquire at planning stage on specific Covid-19 impact, adapting our approach in response. This may result in further changes as the year progresses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.