Financial Management Report April to September 2020
NotedExecutive1 paper
Cabinet - Decommissioned 18.05.2022 noted this item on Wednesday 16 December 2020. Below is the council's own wording, with the papers it was decided on.
(1) That the total projected revenue overspend of £3,319,000 (£2,555,000 as at end of June 2020) be noted. (2) That the settlement on litigation as set out in paragraph 3.16 be agreed. (3) That the use of reserve funds as set out in paragraph 3.15 be agreed. (4) That the payments with regard to the loss of income claims for the leisure contract as set out in paragraph 3.18 be approved. (5) That the projected capital overspend of £2,279,256 and expenditure of £5,676,723 as detailed in paragraph 3.23 and Table 10 Appendix I be noted. (6) That the additional Government funding received by the Council in response to the Covid-19 pandemic be noted. (7) That the ... view the full minutes text for item 350.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Cabinet Agenda Item: 5 Meeting Date 16 December 2020 Report Title Financial Management Report – Second Quarter 2020/21 Cabinet Member Cllr Roger Truelove, Leader and Cabinet Member for Finance SMT Lead Nick Vickers, Chief Financial Officer Head of Service Nick Vickers, Chief Financial Officer Lead Officer Phil Wilson, Financial Services Manager and Caroline Frampton, Principal Accountant Key Decision Yes Classification Open Forward Plan Reference number: 8 Recommendations 1. To note the total projected revenue overspend of £3,319,000 (£2,555,000 as at end of June 2020). 2. To agree to the settlement on litigation as set out in paragraph 3.16. 3. To agree to the use of reserve funds as set out in paragraph 3.15. 4. To approve the payments with regard to the loss of income claims for the leisure contract as set out in paragraph 3.18. 5. To note the projected capital overspend of £2,279,256 and expenditure of £5,676,723 as detailed in paragraph 3.23 and Table 10 Appendix I. 6. To note the additional Government funding received by the Council in response to the coronavirus. 7. To approve the capital variances and their funding as detailed in paragraph 3.21 and Table 10 Appendix I refers.
1. Purpose of Report and Executive Summary 1.1 This report sets out the revenue and capital projected outturn position for 2020/21 as at the end of September 2020. The report is based on service activity up to the end of September 2020 and is collated from monitoring returns from budget managers.
1.2The headline figures are:
projected total revenue overspend of £3,319,000 (£2,555,000 as at end of June 2020) - Table 2; the projected impact of the Coronavirus pandemic is £3.5m (£2,832,000 as at end of June 2020); projected capital overspend of £2,279,256 – Table 10 appendix I.
1 2. Background 2.1 The Council operates a budget monitoring process at Head of Service level, with regular reports to the Leader and Cabinet Member for Finance and the Strategic Management Team.
2.2Financial monitoring reports are presented to Cabinet on a quarterly basis, as well as to Scrutiny Committee.
3. Proposals Revenue Outturn
3.1The last monitoring report to Cabinet was on 23 September covering April to June and the net revenue service expenditure was a forecast overspend of £2,555,000 and the equivalent outturn figure shown in Table 2 is a forecast overspend of £3,319,000, which represents a movement of £764,000 on a budget of £19.381 million. Table 1 below details the significant movements.
Table 1 – Net Revenue Service Expenditure - Movement from April to June Forecast to April to September Forecast
Movement from 1st Quarter to 2nd Quarter £’000 Notes
1st Quarter Monitoring Report to Cabinet 2,555 Homelessness – increase in numbers / 192 Includes £133k Rough Sleeper Rough Sleeper Initiative costs re Covid – may be possible to claim some of this back Leisure Centre 170 Total estimated cost £570k re loss of income claim from Swale Community Leisure (SCL) Trust Car Park Pay & Display – increased loss of 156 income Faversham Pool Grant 75 One off grant Interest Earnings & Cost of Borrowing – 70 Fall in interest rates and lower reduced income cash balances Recovery of Council Tax costs 67 Community Leisure Trust Grant 50 One off grant Shared Service Costs 41 (HR, ICT and Planning) Maidstone Council Parking Partnership – 38 Reflected in 21/22 budget increased costs proposals Waste Contract Savings – reduced savings 35 Car Park increased loss of income 30 Bourne Place loss of income 18 Mid Kent Services (MKS) Debt Recovery – (65) Courts opening has been delayed based on further advice from Maidstone and MBC anticipate to break- Borough Council (MBC) even. Property Services – underspends (41) Vacant post (£20k) and reduced expenditure offset by reduced printing income (£6k)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.