Resolved
(1) That the current contract for Planned and Reactive Term Maintenance be extended for a further 6 months from 1 October 2021 to 31 March 2022. (2) That detailed work is undertaken on other options for a re-tender.
Cabinet - Decommissioned 18.05.2022 decided this item on Wednesday 17 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the current contract for Planned and Reactive Term Maintenance be extended for a further 6 months from 1 October 2021 to 31 March 2022. (2) That detailed work is undertaken on other options for a re-tender.
2.1The current contract for Planned and Reactive Term Maintenance commenced on 1 October 2018 and was awarded to Kirkman & Jourdain. It had an initial period of three years with an option to extend for a further two years.
2.2Kirkman & Jourdain have met all KPIs over the past two and a half years with an average of 94.7% work completed on time.
2.3Kirkman & Jourdain have their own Health & Safety department which ensures all operatives and subcontractors have been vetted. There have been no health & safety issues throughout the contract period.
2.4All paperwork, including relevant material invoices, have been provided. 2.5 Kirkman & Jourdain have completed 91.3% of work at first visit.
2.6Kirkman & Jourdain look to employ local staff as contractors to save travelling, there are 2 local full time operatives who work on our contract. They also hold van stock and regular items of stock at Swale House to avoid the need of travelling to suppliers. They use local suppliers such as CEF and Parker Building Supplies. The majority of the workforce and subcontractors are based locally.
2.7If work needs to be sub contracted due to its specialist nature local firms are used.
2.8Kirkman & Jourdain have demonstrated value for money on numerous work/projects. They have also supported specifications where necessary and provided advice when needed.
2.9As Kirkman & Jourdain are a well established company, they have all the relevant accreditations meaning any due diligence that is the Council’s responsibility is carried out.
2.10There is a good working relationship between the contractors and various tenants at our sites.
2.11There have been a few out of hours emergency issues over the past two and half years and Kirkman & Jourdain have always responded immediately making the area safe and returning to complete when necessary and instructed by Swale Borough Council.
2.12To date spend in each year is:
1st October 2018 – 31st March 2019 £102,027.30 excl VAT 1st April 2019 – 31st March 2020 £234,530.30 excl VAT 1st April - date £156,234.82 excl VAT
3 Proposals
3.1Option 1
The Council continues to use the incumbent contractor for a further two years. The benefits of this option are that by staying with the current contract, we will ensure continuity of service. As set out above, the performance of Kirkman & Jourdain has been satisfactory and there have been no significant performance issues raised. The main disadvantage of this option is that the Council will not be able to test the market, and one contractor does not give the opportunity for smaller, local companies to bid for work. Option 2
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Reactive and Planned Term Maintenance Contract: Extension of contractReport | 87 KB | DownloadRead as text |
Follow Cabinet - Decommissioned 18.05.2022 at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Apr 2022 | Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I... | Noted | Open |
| 13 Apr 2022 | Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro... | Noted | Open |
| 13 Apr 2022 | Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ... | Agreed | Open |
| 13 Apr 2022 | Beam Partnership - Housing and Employment Support(1) That a spend and save pilot in partnership with Beam be entered into. | Decided | Open |
| 13 Apr 2022 | Project Funding(1) That the schemes funded from the Improvement & Resilience Fund, the Special Projects Fund and the High Street Fun... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.