CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Cabinet - Decommissioned 18.05.2022, Wednesday 14 July 2021 at 7.00pm

Future Delivery of Property Maintenance

Decided Executive 1 paper

Cabinet - Decommissioned 18.05.2022 decided this item on Wednesday 14 July 2021. Below is the council's own wording, with the papers it was decided on.

Item156

Resolved

(1) That Council proceed with Option 3 in the report for the delivery of property maintenance from 1 April 2022.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Cabinet - Decommissioned 18.05.2022

Cabinet Meeting Meeting Date 14 July 2021

Report Title Options for the delivery of property maintenance

Cabinet Member Cllr Monique Bonney, Cabinet Member for Property and Economy SMT Lead Nick Vickers, Chief Financial Officer

Head of Service Nick Vickers, Chief Financial Officer

Lead Officer Debbie Hardy, Buildings Manager

Key Decision Yes

Classification Open

Recommendation Cabinet is recommended to proceed with Option 3 as set out in the report which is a modified term contract for the delivery of property maintenance from 1 April 2022.

1 Purpose of Report and Executive Summary 1.1 The purpose of this report is to present members with a detailed appraisal of the options for the delivery of reactive and planned property maintenance and to recommend the most favourable option.

2 Background 2.1 In March of this year, Cabinet took the decision to extend the existing three-year contract for planned and reactive term maintenance by six months rather than the full two years permitted under the contract.

2.2This was on the basis that officers would present a more detailed options appraisal of the alternative options to a term maintenance contract.

2.3The current contract runs until 31 March 2022 and its annual value is approximately £150,000 - £200,000.

3 Proposals

3.1The following options have been explored in detail and the findings are reported here:

Option 1: Retain the status quo, ie. a single term contract,

Option 2: Create a framework contract along the lines of the Staying Put framework, Option 3: Modify the current term contract to encourage all labour and materials to be locally based/procured.

Option 1 (Retain the status quo)

3.2The current arrangement of a three or five year term contract has been in place since 2009 when a joint procurement was carried out with Ashford Borough Council as part of the Swale Ashford Property Partnership. Since the partnership ended, SBC has continued to procure a new contract every three or five years with the current contractor being the fourth company to carry out this work.

3.3The contract operates on a “time and materials” basis. This means that tenders are evaluated based on the hourly rates submitted for each trade and the percentage uplift on the price of materials, plant and specialist subcontractors. Cost control is achieved through the use of signed job sheets verifying the time spent on site and the submission of invoices for materials, plant and specialist subcontractors. Quality is achieved through the use of key performance indicators (KPIs) and post completion inspections.

3.4Jobs are categorised as either emergency, urgent, routine or planned and the required response times are fixed based on the category. One of the KPIs measures the contractor’s ability to meet the response times.

3.5As part of the contract, the contractor is also required to provide diagnostic advice in the event that the cause of a defect and the remedial works required is complex or requires access equipment to investigate. This is provided at no extra cost on the contract.

3.6Payments are made monthly following submission and agreement of a monthly valuation detailing the works carried out in the previous month. A meeting is held between the Buildings Manager and the contractor to discuss any queries.

3.7The term contract is not necessarily used for all planned maintenance projects. It may be more appropriate to carry out a separate procurement exercise for larger projects to ensure that value for money is verified. The term contractor would be eligible to tender for the project.

Option 2 (Framework contract similar to Staying Put)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Future Delivery of Property MaintenanceReport 114 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
BA
Billy AttawayClerk, in attendance
MB
Mike BaldockVice-Chair, apologies
CB
Cameron BeartVisiting Councillor, in attendance
JB
Jayne BolasOfficer, in attendance
MB
Monique BonneyCommittee Member, present
DC
David CliffordOfficer, in attendance
SD
Steve DaveyVisiting Councillor, in attendance
PD
Philippa DaviesOfficer, in attendance
AG
Alastair GouldVisiting Councillor, in attendance
AH
Angela HarrisonCommittee Member, present
BJ
Ben J MartinCommittee Member, present
RP
Richard PalmerCommittee Member, present

All 21 on the meeting page

On this subject at Swale

Search all
  1. Future Delivery of Property MaintenanceThis decision
  2. Community Housing Fund: Options for future delivery models in SwaleDecided
  3. CCTV Future Service Delivery OptionsApproved
  4. CCTV Future Service Delivery OptionsAgreed

More from Swale Cabinet - Decommissioned 18.05.2022

All decisions
MeetingDecisionOutcome
13 Apr 2022 Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I... Noted Open
13 Apr 2022 Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro... Noted Open
13 Apr 2022 Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ... Agreed Open
13 Apr 2022 Beam Partnership - Housing and Employment Support(1) That a spend and save pilot in partnership with Beam be entered into. Decided Open
13 Apr 2022 Project Funding(1) That the schemes funded from the Improvement & Resilience Fund, the Special Projects Fund and the High Street Fun... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies