Cabinet - Decommissioned 18.05.2022 approved this item on Wednesday 16 March 2022. Below is the council's own wording, with the papers it was decided on.
(1) That the appointment of Company A & Company G for Swale House Windows & Roof Finishes Replacement PSSC048A807 from March 2022 at values of £314,774.00 & £1,271,429.60 respectively be approved. (2) That the recommendations in respect of the revised proposed works and award of tender(s) as set out in the evaluation document be agreed. (3) To delegate the award of contracts to the Director of Resources and Director of Regeneration & Neighbourhoods in consultation with the Portfolio Holder. (4) That any underspend up to the approved sum of £1.9 million to be allocated for future internal refurbishment/ decoration works be agreed.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.0The opportunity was advertised in accordance with current contract standing orders, with interested parties asked to complete an Invitation to Tender. Seven submissions were received, and scores were allocated according to the criteria explained in the tender document. Score information held within Appendix 1
2.1A progress report was presented to Cabinet on 9th December 2020 which provided background to the refurbishment project for Swale House, detailed the appointment of the project team / consultancy team and set out the key objectives of the project, as follows • To contribute to the delivery of the Climate and Ecological Emergency Action Plan by creating a low carbon building. • To create a modern and efficient working environment for the organisation and • To support the Council’s Economic Improvement Plan and Recovery Plan by providing opportunities for businesses to locate to Swale House.
2.2A detailed feasibility study, proposals and costing for this extensive project concluded that the cost circa £6 million could not be afforded partly due to the fact that the anticipated grant funding under the Public Sector Decarbonisation Scheme awarded was substantially less than expected. In addition, the internal refurbishment proposals put forward were considered too expensive and due to the Covid pandemic and uncertainty as to post-Covid office needs it was decided to defer such proposals.
2.3A further report was submitted to the Cabinet meeting on 17th March 2021 to consider a revised refurbishment and repair programme. The report proposed and requested Cabinet to agree and approve to:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Rodmersham Green Conservation Area(1) That the responses received from the public consultation exercise (summarised in the response table at Appendix I...
Tunstall Conservation Area Review(1) That the content of the public consultation draft of the character appraisal and management strategy document pro...
Extension of Staying Put Framework(1) That the extension of the contractor framework for Staying Put started in April 2020 be agreed for an additional ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.