Resolved
1) That Option 2 - removal of roof slab and metal stations only at a cost of £10k be the selected option for Barton’s Point covered walkway.
Sheppey Area Committee decided this item on Tuesday 7 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That Option 2 - removal of roof slab and metal stations only at a cost of £10k be the selected option for Barton’s Point covered walkway.
The former rifle range at Barton’s Point, Sheerness is now a multi-use coastal park facility, with the earliest part dating from the turn of the 20th century. An unusual and, now unused, feature of the former facility, is a protected walkway between the two ranges, road and seashore to the north. The long stretch of protective and dog- legged brick walling, in parts was added to by reinforced concrete roof slabs supported on one side by the wall, and the other by metal posts to provide an open- sided covered walkway.
Whilst the brick walling is largely intact and appears in the main to be structurally sound, many of the concrete roof panels and supporting metal posts and now missing and a number of those still surviving are in poor and potentially dangerous condition.
Swale Borough Council have secured the structure with security fencing and is now considering options.
Any potential intervention will be limited to the protected walkway itself and would not include the surrounding structures that have been historically associated with it, e.g. gun battery bases, surviving bases of the target walls and ammunition stores etc.
It should be noted that whilst the structure is not listed, it is of local heritage interest and as such, the primary aim would be to retain it in some form and bring it back into a safe condition and good standard of appearance, where it can be enjoyed and its historical function properly understood by users of the coastal park. SBC has identified the following 3 Options:
Option Specification
One Demolition with floor slab retained Two Removal of roof slab and metal stations only Three Full restoration works to structure
Estimated prices have been provided by contractors as follows:
Options Cost One £30,000 Two £10,000 Three £200,000 – £250,000
Initial considerations indicate option 2 would seem the most sensible/pragmatic way forward taking into account both heritage preservation and financial constrictions. Existing budgets could cover the cost of implementing this option. It should be noted that option 2 does have the risk of the wall coming down in parts during the roof removal.
Minster Parish Council considered the options at their August 2021 meeting. The clerk confirmed the discussion was centred around retaining as much of the whole structure as possible to benefit a future bigger scheme that could regenerate the area.
Further options that have been suggested, are to retain or replicate just a small section of the roof structure to the walkway and/or to add in history interpretation boards to inform visitors of the previous but given financial constraints this would only be feasible if we can attract some additional funding.
The area committee is asked;
• Which of the options would be your preference? • Would the Committee be prepared to allocate funding (on top the £10k SBC contribution) to support the further options in the last paragraph? • Would the Committee consider seeking third party contributions?
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Barton's Point covered walkwayReport | 298 KB | DownloadRead as text |
Follow Sheppey Area Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Feb 2026 | Matters arising from previous meetingsIt was agreed to refer this matter to the Chair of the Environmental Services and Climate Change Committee for consid... | Agreed | Open |
| 3 Feb 2026 | Matters referred to Service Committee Chairs for considerationIt was agreed to refer the following matters to the relevant Service Committee Chairs for consideration: · The instal... | Agreed | Open |
| 2 Dec 2025 | Matters arising from previous meetingsIt was agreed that representatives from the following organisations be invited to a future Sheppey Area Committee mee... | Agreed | Open |
| 18 Sep 2025 | Public Forum1) That a representative from the National Health Service be invited to a future Sheppey Area Committee meeting to re... | Decided | Open |
| 18 Sep 2025 | Isle of Sheppey Growth Board1) That the Sheppey Area Committee referred the proposal to set up a Sheppey Growth Board to the Economy and Property... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.