1) That officers made contact with Western Area Committee Members to check what priorities they would like costings/proposals for. Proposals to be brought back to the September 2022 meeting for consideration. 2) That Western Area Committee funding would not be made available to external bids until the costings and proposals had been considered at the September 2022 Area Committee meeting and it was established if there was any remaining funding.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.1In June 2021 the AC Review Working Group and Committee Chairs agreed a process for operating ACs and part of that was for each AC to agree a Work Plan at the June meeting each year. This would set out each Committee’s priorities and ambitions for that year and would link in with how the funding should be allocated. Once the priorities/ambitions have been agreed, the Committee will need to set criteria which any bids for funding would need to meet.
2.2The Committee can decide to use the funding exclusively for a proactive theme/ambition or open the scheme up for external organisations to make bids or a combination of the two. 3 Proposals
3.1Priorities/ambitions for 2022/23 - the AC Review Working Group met in April 2022 to reflect on how the AC’s processes worked during the year 2021/22 and to consider what changes would be beneficial going forward.
3.2One of their recommendations was that Heads of Service be consulted to see if there are any existing projects that each AC could use part of their funding to accelerate without requiring much more than minimal officer involvement. This would help to achieve completion of projects earlier as well as benefit the area. Below is a list briefly outlining some potential projects that Committee Members may wish to consider prioritising for 2022/23.
• Active Travel – consultation events (necessary to support the development and adoption of the borough-wide and area-based Local Cycling and Walking Infrastructure Plans);
• Active Travel – infrastructure improvements. This could be for example new or improved cycle storage on SBC land, or following engagement with partners such as Network Rail;
• public toilet refurbishments;
• tree planting above the current plans;
• support for interventions around the Cost of Living Crisis – Food banks and VCS support such as debt advice etc.
3.3Criteria for funding applications - The Chair and Vice-Chair propose that the criteria set by Western Area Committee for the year 2021/22 should be carried forward to 2022/23 as they are still relevant for the area. Therefore, bids for funding submitted to the September 2022 meeting should demonstrate they will have a positive impact on the appearance, environment and facilities in the Western Area and benefit residents across the area.
3.4Bids will also be considered that can demonstrate how the initiative or project will contribute to Swale’s strategic priorities 2 and 3 as set out in the Corporate Plan as listed below:
3.5Priority 2: Investing in our environment and responding positively to global challenges;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.