Risk Management framework 2022

Approved Finance 2 papers

Audit Committee approved this item on Monday 25 July 2022. Below is the council's own wording, with the papers it was decided on.

Item213

Resolved

(1) That the revised Risk Management Framework be approved.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Audit Committee

Background

2.1Since the Frameworks introduction in 2015 it has been routinely reviewed and updated, with the last update taking place in 2019.

2.2During October / November 2021 SMT were consulted on changes that could be made to the Council’s risk management processes to enhance and update them and to reflect the new management team structure. This feedback and the operation of the process over the past few years was used to develop the revised Risk Management Framework, which SMT agreed in January 2022 – subject to confirmation of how risk information would be reported and overseen within the new Committee Structure.

2.3Feedback on the key changes was sought from Audit Committee in March 2022, including changes to the impact and likelihood scales and changes to the Council’s risk appetite statement.

2.4Now the Committee Structure has been agreed and the role of Policy & Resources Committee established, the revised Risk Management Framework can be bought for agreement. 2.5 The key changes made to the Risk Management Framework were included in the March 2022 report and are summarised as:

• Adding a foreword from the Chief Executive promoting the value of the Council’s risk management processes. • Likelihood scales updated to refine the probability thresholds, reducing the maximum probability down from 90% and re-distributing the other levels. Descriptions were also updated to incorporate a timeframe over which the risk may occur. • Impact scales have been updated, including amending the financial scales, changing the definitions of the service and strategic objective scales, adding in a wellbeing scale, and incorporating the health & safety scale within legal/compliance. • The risk appetite statement was updated to remove the blue priority (incorporating it into the green scale) and to increase the threshold for the red priority to better reflect the Council’s approach to managing those risks. • Adjusting the reporting of risk information to report key risk information to Policy & Resources Committee rather than Informal Cabinet. • Framework updated to remove reference to capturing risks within a spreadsheet and replace with reference and links to the Council’s risk management software JCAD. • Incorporating other suggested amendments from the Council’s insurer’s (Zurich) review of the Framework.

2.6Once the new Framework is agreed existing risks can be fully reviewed, updated and re-scored. This provides an opportunity to fully refresh corporate and operational risk registers, including removing risks and identifying new risks as needed.

3 Proposals

3.1That the Risk Management Framework 2022 be adopted and used to assess and monitor existing and new corporate and operational risks.

Alternative options

4.1Effective risk management processes need to be underpinned by clear guidelines on how risks should be identified, managed, monitored and reported on. Effective risk management is a key principle of corporate governance and its importance is recognised in the Accounts and Audit Regulations 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Swale Risk Management Framework: 2022 DraftAppendix I 649 KB Download
PDF
Risk Management framework 2022Report 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 21 attended
BA
Billy AttawayOfficer, in attendance, virtual
CB
Cameron BeartCommittee Member, present as substitute
AB
Alison BlakeOfficer, in attendance
DC
Derek CarnellChair, present
SC
Simon ClarkCommittee Member, present
LF
Lisa FilleryOfficer, in attendance
AH
Ann HampshireCommittee Member, apologies, sent representative
AH
Angela HarrisonCommittee Member, absent
MH
Mike HendersonVice-Chair, apologies
JH
Julie HetheringtonOfficer, in attendance, virtual
DK
Denise KnightsCommittee Member, present, as expected, virtual
PM
Peter MacDonaldCommittee Member, present

All 21 on the meeting page

On this subject at Swale

Search all
  1. Risk Management framework 2022This decision
  2. Risk Management UpdateNoted
  3. Risk Management UpdateNoted
  4. Updated Risk Management Policy Statement, Strategy & FrameworkApproved
  5. Annual Risk Management ReportNoted
  6. Risk Management UpdateNoted

More from Swale Audit Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Internal Audit Annual Report and Audit Opinion 2025/26(1) That the Head of Audit Partnership’s Annual Audit Opinion for 2025/26 be noted. (2) That the work underlying the ... Noted Open
15 Jul 2026 Annual Treasury Management Report 2025/26(1) That the Treasury Management outturn report for 2025/26 be noted. Noted Open
13 May 2026 Election of Chair(1) That Councillor Charles Gibson be elected as Chair for the municipal year 2026/27. Decided Open
13 May 2026 Election of Vice-Chair(1) That Councillor Simon Clark be elected as Vice-Chair for the municipal year 2026/27. Decided Open
22 Apr 2026 Internal Audit and Assurance Plan 2026/27(1) That the Internal Audit & Assurance Plan for 2026/27 be approved and that the Head of Audit Partnership be given ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies