(1) That the explanation for the delayed completion of the Planning Services audit action, as detailed in the report be noted.
Audit Committee noted this item on Monday 19 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the explanation for the delayed completion of the Planning Services audit action, as detailed in the report be noted.
2.1On 24th January 2024, members of the Audit Committee considered a report on Internal Audit and Assurance Progress.
2.2The report highlighted an outstanding action from 2021 in relation to the audit on Developer Income within the Planning Service.
2.3Members resolved that to determine why the action was yet to be completed, the Head of Planning Services be brought before the Audit Committee at the nearest convenient date.
2.4The audit report in question was issued on 10th August 2021. The report was issued with a sound level of assurance with eight priority findings raised for action (two high, two medium and four low).
2.5The outstanding action is Finding R05: Non-Financial Contributions which identified ‘inadequate monitoring of whether non-financial contributions are being met by the developer’. The recommendation was twofold, that • ‘responsibility for non-financial contributions be appropriately assigned’, and • A post-development review should be undertaken at the end of a S106 agreement to determine if all obligations were met.
1 2.6 Non-financial contributions include assets such as affordable housing, or open space provision, and non-tangible contributions such as employment and apprenticeship opportunities which planning consent obliges a developer to provide.
2.7The actions were mutually agreed, with commentary from the Planning Service that routine monitoring of non-financial obligations would involve significant resource to complete systematically, and that a procedure would need to be agreed to determine at what point a development scheme is considered complete.
2.8It was noted that open space and affordable housing contributions – the two most significant components of non-financial contributions - were both monitored effectively within their respective services. Thus this action was around wider non-financial contributions, and the creation of a centralised system within Planning.
2.9The target date for implementation was agreed as 31st October 2021.
2.10The audit findings have been a point of regular discussion between the Audit Team and Planning Services, with the last discussion in November 2023, and an agreed further review date of April 2024. A summary of the reviews is below:
Date Action / Outcome January Officers had met with counterparts from Maidstone Borough Council to 2022 understand their approach. A mismatch of resources and difference in developer income system (S106 vs CIL) had led officers to request a deferral of this action until June 2022 to allow for • a wider best practice review to be undertaken, • internal resources to be allocated, and • the forthcoming White Paper to be published (to clarify whether Swale would adopt CIL). July 2022 This action was now the responsibility of a new (Interim) Head of Service. The lead officer advised that it had not proved possible to allocate existing resource to the task, and that the addition of a new post to the Planning Services structure was to be considered by the new Head of Service.
The lead officer set out that external support for the Planning Service had been commissioned and that this agency was tasked with making recommendations for monitoring. This work was due to end in October 2022.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning: Outstanding Audit ActionReport | 99 KB | DownloadRead as text |
Follow Audit Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Internal Audit Annual Report and Audit Opinion 2025/26(1) That the Head of Audit Partnership’s Annual Audit Opinion for 2025/26 be noted. (2) That the work underlying the ... | Noted | Open |
| 15 Jul 2026 | Annual Treasury Management Report 2025/26(1) That the Treasury Management outturn report for 2025/26 be noted. | Noted | Open |
| 13 May 2026 | Election of Chair(1) That Councillor Charles Gibson be elected as Chair for the municipal year 2026/27. | Decided | Open |
| 13 May 2026 | Election of Vice-Chair(1) That Councillor Simon Clark be elected as Vice-Chair for the municipal year 2026/27. | Decided | Open |
| 22 Apr 2026 | Internal Audit and Assurance Plan 2026/27(1) That the Internal Audit & Assurance Plan for 2026/27 be approved and that the Head of Audit Partnership be given ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.