Resolved
(1) That the use of funds to progress the construction tender be approved.
Swale Rainbow Homes Shareholder Sub-Committee approved this item on Monday 9 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the use of funds to progress the construction tender be approved.
2.1At the SRH Shareholder Sub Committee on 14th February 2024 a detailed update was provided from SRH in terms of progress made and detailed the current viability gap that existed to progress the scheme. The SRH Shareholder Sub Committee resolved to pause the scheme. However, SRH was asked to continue to review grant funding opportunities that could enable the scheme to be viable.
2.2Since the meeting in February SRH have secured planning consent for the Cockleshell Walk on 23rd May 2024. With planning permission secured this enabled SRH Board and Consultants from Counties and Capital Consulting (C&CC) to engage with Homes England regarding the level of grants available for the scheme.
2.3The scheme appraisal with updated parameters (interest rate, new LHA rates and revised QS build costs) was reviewed in April to inform Homes England (HE) grant discussions, there have been fluctuations in the figures since, but no material changes have occurred since April. SRH wrote to Homes England on the 8th April 2024 seeking a level of grant funding far higher than the usual allocation. A meeting took place with representatives from Homes England who have reviewed our scheme financial appraisal information and confirmed that we can assume grant for all 51 homes and that whilst an enhanced grant level is possible (for Social Rented homes) there would not be funding available to entirely remove the entire development funding deficit 2.4 To fully review our scheme and grant requirement Homes England have asked us to undertake our construction tender work to understand our build costs as this is the final variable in confirming our exact funding need. C&CC have estimated that the cost to tender the works contract will be in the region of £65,000, made up of 6-8 months of work from our Employers Agent, some architectural assessments and c£35,000 of surveys.
2.5Due to the decision by SRH Shareholder Sub Committee to pause the scheme, before any further work is commissioned on the scheme, SRH is seeking authority to progress.
3 Proposals
3.1For the Shareholder Panel to approve use of funds to progress the construction tender.
4.1To not approve the progressing of the construction tender.
5 Consultation Undertaken or Proposed
5.1A meeting has taken place with Homes England as discussed in the main body of the report.
6 Implications
Issue Implications Corporate Plan Health & Housing - To aspire to be a borough where everyone has access to a decent home and improved health and wellbeing. Financial, Resource and The costs of the construction tender are estimated to Property be circa. £65k. This can be funded from the earmarked reserve allocated to fund the initial costs of SRH capital project Legal, Statutory and None at this stage. If approved the tender would be Procurement undertaking in line with Public Procurement legislation. Crime and Disorder None identified at this stage. Environment and None identified at this stage. Climate/Ecological Emergency Health and Wellbeing None identified at this stage. Safeguarding of Children, Young None identified at this stage. People and Vulnerable Adults Risk Management and Health None identified at this stage. and Safety Equality and Diversity None identified at this stage Privacy and Data Protection None identified at this stage
7.1None
8.1None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Swale Rainbow Homes Shareholder UpdateReport | 43 KB | DownloadRead as text |
Follow Swale Rainbow Homes Shareholder Sub-Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Feb 2024 | Exclusion of the Press and Public(1) That under Section 100A(4) of the Local Government Act 1972, the press and public be excluded from the meeting fo... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.