(1) That the Council retained and maintained the building in its current condition, to be reviewed after a period of no more than 18 months. (2) That officers explored opportunities to bring the building back to a useable standard during this period.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
2.144 Trinity Road, Sheerness (known as the Old Library, see attached plan at appendix I) was historically used for a range of community uses but has now remained vacant for several years. More recently the building has been subject to vandalism, including significant internal fire damage, with an adverse visual impact in a prominent town centre location. 2.2 The property was advertised inviting Expressions of Interest alongside Masters House in 2022. There were no substantive offers at that stage. There has been some interest in the building since for community/learning use but its condition means that it is currently unable to be occupied and would require investment, that to date has not been forthcoming.
2.3The property has been secured and asbestos removed, to permit access to undertake cost surveys. These indicate that there are substantial costs involved to bring forward a refurbishment of the building.
2.4If a suitable source of external funding were available to support the refurbishment this would positively impact on the Councils ability to undertake such works. This possibility has been promoted to external partners as a potential ‘quick win’ project, in the event that resources become available.
2.4There are options available to the Council in terms of this property asset including:
• Dispose of the building as it is. A third party may have an interest based on the site’s value, involving demolition of the building, with this cost likely to reduce the achievable receipt.
• Demolition. This may render the site more saleable or create a future development opportunity.
• Fund the refurbishment, although this would be a capital cost to the Council’s limited resources.
• Retain and maintain the building, in its current condition for a period to see whether external funding opportunities come forward to support refurbishment for occupation. Retention also provides the Council with a greater stake and potential influence in relation to the future of surrounding land holdings, including the Water Tower site, which is not owned by the Council, but is currently understood to be for sale. The land to the rear of the property is also vacant and undeveloped.
3 Proposals
3.1It is recommended that the Council retains and maintains the building in its current condition, to be reviewed after a period of no more than 18 months.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Granting of a New Commercial Lease(1) That the grant of a new commercial lease of the property detailed in the exempt Appendix I be approved. (2) That ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.