Update on Motion to Change Shoreline Management Plan Policy - Eastchurch Cliffs
NotedCommittee3 papers
Environmental Services and Climate Change Committee noted this item on Tuesday 18 March 2025. Below is the council's own wording, with the papers it was decided on.
(1) That the contents of the report following the previous motion to change the Shoreline Management Plan Policy for Eastchurch be noted and the work that had been done be acknowledged and that officers focussed on engaging and supporting the affected residents.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Report to Environmental Services and Climate Change Committee
Environment & Climate Change Committee Meeting Date 18th March 2025
Report Title Update on Motion to Change Shoreline Management Plan Policy – Eastchurch Cliffs EMT Lead Emma Wiggins, Director of Regeneration & Neighbourhoods Head of Service Martyn Cassell, Head of Environment & Leisure
Lead Officer Mike Knowles, Seafront & Engineering Manager
Classification Open
Recommendations 1. Members are asked to note the contents of the report following the previous motion to change the Shoreline Management Plan Policy for Eastchurch and acknowledge the work that has been done and that we will now focus on engaging and supporting affected residents .
1 Purpose of Report and Executive Summary
1.1This report provides an update following the motion passed by Members in November 2020 to seek to change the current policy of the Shoreline Management Plan along the unprotected North Sheppey coastline.
2 Background 2.1 Following the motion previously passed by Members, officers have been actively pursuing a change to the current SMP policy through discussions with partners.
2.2The Isle of Sheppey is covered by Shoreline Management Plan SMP10 (Isle of Grain to South Foreland) which was adopted in 2008 following a review of the original SMP for the North Kent Coast (Isle of Grain to Dover Harbour) 1996.
2.3The section of undefended coastline between the eastern end of the defences at Minster Leas and Warden Bay, policy unit number 4a04 in the SMP, has a policy of “No Active Intervention”.
2.4At Full Council in November 2020, Members passed the motion “that in view of the climate change accelerating the rate of the erosion of the Sheppey cliffs, this Council wishes to change Government policy to prevent further unsustainable erosion, thereby protect the existing, expanding, and future population of Sheppey. Swale Borough Council undertakes to seek the removal of the government coastal policy of non-intervention, with its serious social and
1 commercial implications, and replace that policy with a policy of protection of the coastline.”
2.5Following this motion, a letter was drafted on behalf of the Cabinet Member for the Environment, and sent to the Secretary of State for Environment, Food and Rural Affairs, explaining the motion and requesting further discussion on the issue. A copy of this letter can be found in Appendix I.
2.6A response was subsequently received in February 2022, via the Department for Environment, Food and Rural Affairs (DEFRA). The response stated that the policy options in the Shoreline Management Plan were all adopted by the relevant operating authorities in the first half of 2008, and these included Swale Borough Council, which was involved in developing and adopting the SMP policy of No Active Intervention. A full copy of the response can be found in Appendix II.
2.7The response went on to detail the process for pursuing a change to an SMP policy. To summarise, the process is a complex and technically challenging one, with no guarantee of a positive outcome. As well as receiving the response from DEFRA, officers have also undertaken significant research through the South East Coastal Group (made up of key organisations focussed on coastal management), the Environment Agency and Coastal Consultants, to gather information around the change process.
2.8The conclusion is that, despite the best efforts to date, we are unable to deliver the previous motion. The policy was agreed as the most sustainable policy for a number of reasons, including
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environmental Services and Climate Change Committee at Swale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.