CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swale Borough Council
Economy and Property Committee, Wednesday 8 October 2025 at 7.00pm

Levelling-Up Fund Programme Update

Noted Committee 2 papers

AI summarySwale Borough Council Economy and Property Committee noted an update on the £20m Levelling-Up Fund programme of three Sheerness Revival projects, with completion due by July 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo decision beyond noting the report
Money£20m LUF plus over £2m matchPlus £400k from EKC Group
What happens nextBeachfields handover July 2026Masters House November 2025, Sheppey College December 2025
Who it affectsSheerness and Isle of Sheppey residentsThree regeneration projects: Beachfields, Masters House, Sheppey College

What was decided

The Committee noted the Levelling-Up Fund programme update and provided comment as appropriate. Report 3.1

Officers were asked to progress planned next steps including engagement activities, design of TAG Active and soft play, outdoor gym procurement, landscaping, ASB work, potential renaming of the Healthy Living Centre, and concluding new leases for returning Beachfields occupiers. Report P63, P64, P65, P66, P67, P68, P69, P70, 2.35

Why

The report is a 'to note' item, so no alternative options were considered and no consultation was undertaken or proposed. Report 4.1, 5.1

Effective governance and oversight are needed to deliver the LUF programme, support Council Corporate Plan priorities on running the council and the economy, and secure maximum impact from the government investment. Report P76, P77

What happens next

Construction work continues to completion milestones: Masters House November 2025, Sheppey College December 2025, Beachfields July 2026, with government spending allowed up to March 2027. Report P27, 2.19, 2.34

Officers will run engagement activities, design TAG Active and soft play, procure an outdoor gym contractor, begin landscaping at Beachfields, pursue a multi-agency ASB response, consider renaming the Healthy Living Centre, and conclude new leases for returning occupiers. Report 2.35, P63, P64, P65, P66, P67, P68, P69, P70

Programme delivery is supported by two full-time staff, with the team to reduce from April 2026. Report P77

The money

  • £20m UK Levelling-Up Fund investment in the Sheerness Revival programme Report P77
  • over £2m Match funding (in kind and cash) from Swale Borough Council Report P77
  • £400k Funding from EKC Group Report P77

Options considered

  • Chosen: Note the update. Presented as a 'to note' report with no alternative options Report 3.1, 4.1

Implications

  • Financial: Effective management and oversight are key to securing maximum impact from the £20m LUF investment plus match funding. Report P77
  • Risk: A Sheerness Revival risk register is maintained and regularly reviewed and reported to government; each project has its own risk register. Report P77
  • Risk: Anti-social behaviour has been persistent at Beachfields and Masters House, with incidents escalating in frequency and nature over summer 2025; security patrols, CCTV, fencing and design features are in place. Report 2.27, 2.28, 2.29, 2.30, P47
  • Staffing: Two full-time staff support delivery, with the team to reduce from April 2026; specialist support from other departments covered from existing resource. Report P77
  • Legal: Governance arrangements form part of the project business case and the Memorandum of Understanding with government. Report P77
  • Climate: The LUF business case demonstrates how the programme aligns to and supports net zero ambitions, for example a 'blue roof' on Sheppey College for rainwater collection. Report P77, 2.9
  • Other: Social value contributions from contractors include use of local supply chain, school engagement, work experience, charitable donations and student bricklaying participation. Report P38, P40

Who and where

  • Occupants of the Healthy Living Centre at Beachfields (the charity Sheppey Matters, Minster Medical Practice GP surgery, and leisure operators) who have temporarily relocated during works Report 2.11, 2.12, 2.13, 2.14
  • Students and learners at Sheppey College, with additional educational space expected to open in January 2026 Report 2.4, 2.20
  • Visitors and residents of the Isle of Sheppey using the new Beachfields facilities including the Adventure Golf course Report 2.17, P51, P52
  • Local school children, supply chain contractors, and charities including Launch It Report 2.15, P38, P40

Timeline

  • 8th March 2023: Regeneration and Property Committee agreed to use the UK Leisure Framework to identify a delivery contractor for Beachfields and public realm projects Report 2.1
  • September 2024: Planning permission granted for Sheppey College and Masters House Report 2.18
  • 17th December 2024: Committee approved appointment of Etec for Beachfields and Building Associates Limited for Masters House, subject to conditions Report 2.2, 2.3
  • January 2025: Planning consent granted for Beachfields and Public Realm; Healthy Living Centre occupiers decanted to temporary locations Report 2.7, 2.11
  • February 2025: Spade-in-the-ground event held to mark the start of main works at Sheppey College Report 2.8
  • May 2025: Council signed Delivery Management Agreement with Alliance Leisure to instruct Etec; JCT contract for Masters House garages signed Report 2.5, 2.6
  • July 2025: Masters House works commenced on site; Adventure Golf course formally opened Report 2.6, 2.17
  • September 2025: Window and internal fitout works began at Sheppey College Report 2.9
  • November 2025: Masters House completion and handover expected Report P27, 2.21
  • December 2025: Sheppey College completion and handover expected Report P27, 2.20
  • January 2026: Sheppey College expected to open to students Report 2.20
  • April 2026: Programme delivery team size to reduce from two full-time staff Report P77
  • July 2026: Beachfields completion and handover expected Report P27, 2.19
  • March 2027: Latest date by which government LUF investment can be spent Report 2.19

Plain English for the jargon

  • Levelling-Up Fund (LUF): A UK government capital funding programme for local regeneration projects, here providing £20m for the Sheerness Revival programme
  • Sheerness Revival: The collective name for the three LUF-funded projects on the Isle of Sheppey: Beachfields and Public Realm, Masters House, and Sheppey College expansion
  • TAG Active: An indoor active play and trampoline leisure concept planned for Beachfields
  • MUGA: Multi-Use Games Area, an outdoor surfaced area marked for multiple sports, planned alongside the outdoor gym
  • ASB: Anti-social behaviour, identified as a recurring issue at the Beachfields and Masters House sites
  • JCT contract: A standard form of building contract issued by the Joint Contracts Tribunal, used here for the Masters House garage refurbishment
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item390

Resolved

(1) That the update be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Economy and Property Committee

Background

2.1On 8th March 2023, Regeneration and Property Committee (as was) agreed “to utilise the UK Leisure Framework to identify and recommend a delivery contractor for the [Sheerness Revival] Beachfields and public realm projects, to be appointed following Committee approval”.

2.2This was followed by Committee approval on 17th December 2024 to appoint Etec to deliver the Beachfields and Public Realm project, subject to the final contract value being within the available budget and with financial due diligence being undertaken to the satisfaction of Committee Chair and Director of Resources prior to contract award.

2.3Additionally on 17th December Committee approved the appointment of Building Associates Limited for the alteration and refurbishment of obsolete garages at Masters House.

Contractual undertaking

2.4At the end of 2024, East Kent College (EKC) appointed Jenner Group to undertake the expansion works at Sheppey College, which will offer an additional 900 square metres of educational space for learners to explore a wider range of courses that have been informed by local skills needs. This is principally related to further education provision, but will also enable the creation of junior college facilities and the introduction of adult education opportunities.

2.5In May 2025 the council entered into a Delivery Management Agreement with Alliance Leisure to instruct Etec Group to progress the stage 5-7 construction works at Beachfields, following receipt and approval of the final stage 4 costs report.

2.6The JCT contract to undertake refurbishment works on the garages at Masters House was also signed in May 2025 between the council and Building Associates Ltd, with agreed start on site in July to complete the workshops at the end of November.

Progress to date

2.7Planning consent was granted for Beachfields and the Public Realm in January 2025 which enabled the start of early works to prepare the site for stage 5-7 construction.

2.8Similarly main works began at Sheppey College following the legal progression of the land transfer from the Council and a value engineering exercise to ensure the project remained within budget and to scope. A spade in the ground event was held in February 2025 to mark this milestone moment.

2.9Progress on site has seen the full steel structure and brickwork installed. A ‘blue roof’ will support with rainwater drainage by collecting excess water which is then utilised to water vegetation. Works to install the windows and internal fitout began in September, while further works continue at pace.

2.10Full refurbishment is underway at Masters House where the old roof has been removed in preparation for the new roof to be installed and the garages will start to take form, with the impressive steel and glass frontage showcasing the full industrial and modern design.

Temporary Relocation of Beachfield Occupants

2.11The occupiers of the Healthy Living Centre which includes the charity, Sheppey Matters, the GP surgery, Minster Medical Practice and the leisure provision decanted the building and relocated to alternative temporary locations in January to continue their services and operations whilst the works are ongoing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LUF Programme Images Appendix IAppendix 660 KB Download
PDF
Levelling-Up Fund Programme UpdateReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 21 attended
BA
Billy AttawayOfficer, in attendance
MB
Monique BonneyChair, present
HB
Hayden BrawnCommittee Member, present
MC
Martyn CassellOfficer, in attendance, virtual
AC
Ann CavanaghCommittee Member, present
SC
Shelley CheesmanCommittee Member, present
SC
Simon ClarkCommittee Member, present
AE
Alex EyreCommittee Member, present
JJ
Joanne JohnsonOfficer, in attendance
IL
Inger LorraineOfficer, in attendance
KM
Kieren MansfieldOfficer, in attendance
PM
Peter MarchingtonCommittee Member, apologies

All 21 on the meeting page

On this subject at Swale

Search all
  1. Levelling-Up Fund Programme UpdateThis decision
  2. Extended Membership of the Levelling Up Fund Member Working GroupAgreed
  3. Levelling-Up FundAgreed
  4. Levelling-up Fund Application and AppendixApproved

More from Swale Economy and Property Committee

All decisions
MeetingDecisionOutcome
7 Jul 2026 Forward Decisions Plan(1) That the be noted. Noted Open
7 Jul 2026 Disposal of Queenborough Guildhall, associated land and 44 High Street, Queenborough(1) That the decision of the Economy and Property Committee made on 9 April 2025, regarding the disposal of the parce... Agreed Open
7 Jul 2026 Swale House Increased Security – Costed Options(1) That the options to secure the footprint of Swale House, and in particular the undercroft, be noted. (2) That the... Noted Open
7 Jul 2026 Closed Public Conveniences - Property Next Steps(1) That the Council retained the Eastchurch Public Conveniences, to be reviewed after a period of no more than 18 mo... Agreed Open
7 Jul 2026 Granting of a New Commercial Lease(1) That the grant of a new commercial lease of the property detailed in the exempt Appendix I be approved. (2) That ... Approved Open