Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure

Noted Committee 1 paper

AI summarySwale Joint Transportation Board noted an update on Kent's electric vehicle charging rollout, with contractor Urban Fox set to deliver up to 10,000 on-street sockets across the county.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted
MoneyNot stated
What happens next150 sites in year oneUp to 13 sites within each Borough or District
Who it affectsResidents and businessesEspecially those without off-street parking

What was decided

The Board noted the report on the Local Electric Vehicle Infrastructure project and other electric vehicle charging infrastructure.

Why

Kent County Council is rolling out public on-street EV charging to support residents and businesses switching to electric vehicles and to capture carbon and air quality benefits. Report 1.1, 2.2

Demand is being driven by the Zero Emission Vehicle mandate requiring 80 per cent of cars sold in 2030 to be electric. Report 2.1

What happens next

Contractor Urban Fox will install, own and operate the charger network, with the LEVI project aiming to deliver up to 10,000 EV sockets across Kent, mainly on the highway. Report P6, 2.3, 2.4

Up to 150 locations are planned in the first year, with up to 13 in each Borough or District, subject to site feasibility, each starting with two sockets and extra cabling for later expansion. Report 2.10, 2.11

Kent County Council is expected to decide later in 2026 whether to proceed with a limited cable gully trial once safety guidance is updated. Report 3.2, 3.3

Implications

  • Climate: The network is designed to support the switch to electric vehicles and improve local air quality. Report 2.2
  • Other: Charger locations will be supported by Traffic Regulation Orders, with the chance for residents to support or object on traffic management grounds. Report 2.14
  • Other: Site selection is data-led and aims to stay slightly ahead of demand while avoiding property frontages where possible. Report 2.8
  • Risk: Cable gullies are under safety review by a new technical working group because of concerns about simultaneous touch electrocution risk. Report 3.1, 3.2

Who and where

  • Residents without easy access to off-street parking
  • Businesses switching to electric vehicles Report 1.1
  • District and Borough Councillors asked to support rollout Report 1.1
  • Members of the public invited to suggest charger locations Report 2.13

Timeline

  • February 2026: Contracts signed with Urban Fox, a joint venture between Balfour Beatty and Urban Electric Networks. Report 2.3
  • First year: Up to 150 locations installed county-wide, with up to 13 in each Borough or District, subject to site feasibility. Report 2.10
  • Later in 2026: Kent County Council expected to decide on a limited cable gully trial. Report 3.3
  • 2030: Zero Emission Vehicle mandate requires 80 per cent of cars sold to be electric. Report 2.1

Plain English for the jargon

  • LEVI: Local Electric Vehicle Infrastructure, the project name for KCC's on-street EV charging rollout.
  • EV: Electric Vehicle.
  • KCC: Kent County Council, the upper-tier authority leading the project.
  • Urban Fox: Joint venture between Balfour Beatty and Urban Electric Networks that will install, own and operate the charger network.
  • ZEV mandate: Zero Emission Vehicle mandate, requiring 80 per cent of cars sold in 2030 to be electric.
  • Traffic Regulation Order: Legal order needed to manage parking and traffic at charger locations, open to public support or objection.
  • Cable gully: Cross-pavement gully that lets EV charging cables run under the pavement; currently under safety review.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item147

Resolved

(1) That the report be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Swale Joint Transportation Board

Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure.

To: Joint Transportation Board – June 2026

Portfolio Area: Growth, Environment & Transport

By: Tim Middleton, Network Innovations Manager, KCC

Classification: For Information

Summary: This report provides an update on the Local Electric Vehicle Infrastructure (LEVI) project delivering up to 10,000 Electric Vehicle (EV) charging sockets across Kent. It also provides updates on other EV charging options available to residents and businesses.

1. Introduction

1.1This report gives a broad overview of the Local Electric Vehicle Infrastructure project (LEVI) project. It provides a look at Kent County Council’s (KCC) role in ensuring residents and businesses are able to switch to electric vehicles (EVs) through providing public on-street electric vehicle charging infrastructure. It also outlines how District/Borough Councillors and the public can help to support the rollout.

2. On-Street Electric Vehicles Charging Infrastructure

2.1Electric Vehicle (EV) sales are growing in the UK and the demand for charging infrastructure is rising. Demand will be driven by the Zero Emission Vehicle mandate requiring 80% of cars sold in 2030 to be EV.

2.2In order to help the transition to electrification, with all the carbon and local air quality benefits this would bring, KCC have developed an EV infrastructure programme to install EV charging points across the county.

2.3In February 2026, contracts were signed with Urban Fox. Urban Fox are a joint venture between Balfour Beatty and Urban Electric Networks, combining Balfour Beatty’s expertise in large-scale infrastructure delivery with Urban Electric’s innovation in smart street-level charging technology.

2.4Urban Fox will install, own and operate the network of chargers.

2.5The focus of the LEVI project is to help deliver a step change in the deployment of on-street charging infrastructure to accelerate the commercialisation of, and investment in, the local charging infrastructure sector. 2.6. The first 6 months allow for a mobilisation period, followed by up to 10 years in which chargers will be installed across a phased delivery programme. The contract aims to deliver around 10,000 EV charger sockets across Kent, primarily on the highway, catering for those without easy access to off-street parking.

2.7Elected Councillor and resident suggested locations are used, alongside multiple data sources considering propensity for off-street parking, future growth, the existing network, location details of existing EV’s registered in Kent, to name a few.

2.8The network is designed to be equitable and data led, aiming to stay slightly ahead of demand. Locations have been selected to avoid property frontages where possible to minimise disruption to residents.

2.9KCC have been engaging with District/Borough officers to ensure the proposed planning is suitable for each area and any initial challenges can be avoided.

2.10The first year will see 150 locations installed county wide with up to 13 of those located within each Borough/District, subject to site feasibility.

2.11It is intended that each location will have an initial 2 sockets available (2 x bays) so as to minimise parking disruption in the early phases. To reduce disruption later, extra cabling and ducts will be installed so that additional chargers can be easily added in the future when demand grows.

2.12The vast majority of the chargers installed will be dual 7kw units with some 11kw and 22kw included where appropriate. While the chargers selected will evolve with technological advances over time, a few images of the chargers to be installed this year have been included in the Appendix.

2.13Urban Fox have provided a webpage to provide updates and information on the rollout. Additionally, the public and Councillors are invited to suggest suitable charger locations via the online portal www.urbanfox.network/networks/kent

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructureReport 171 KB DownloadRead as text

At this meeting

Whole meeting
144Presentation from Network RailDecided 146Petition for Residents' Parking Scheme - College Road, SittingbourneOn the agenda
147Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructureThis decision

Who was there

12 of 23 attended
MB
Monique BonneyCommittee Member, in attendance, virtual
DC
Daniel Cannon-SkeetOfficer, in attendance, virtual
SC
Shelley CheesmanVisiting Councillor, in attendance
SC
Simon ClarkVice-Chair, present
AG
Alastair GouldCommittee Member, present
MH
Maxwell Harrison (Kent County Councillor)Kent County Councillor, present
AH
Antony Hook (Kent County Councillor)Kent County Councillor, apologies
IK
Isabella Kemp (Kent County Councillor)Kent County Councillor, absent
MK
Mike KnowlesOfficer, in attendance, virtual
RL
Rich Lehmann (Kent County Councillor)Kent County Councillor, absent
PM
Peter MacDonaldCommittee Member, present
JM
James MorrisonParish Councillor, present

All 23 on the meeting page

More from Swale Swale Joint Transportation Board

All decisions
MeetingDecisionOutcome
29 Jun 2026 Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... Decided Open
6 Oct 2025 Highways Work Programme(1) That the report be noted. Noted Open
6 Oct 2025 Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. Noted Open
30 Jun 2025 Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. Noted Open
30 Jun 2025 Highways Work Programme(1) That the report be noted. Noted Open