Resolved
RESOLVED that (1) the contents of the report be noted (2) a copy of the final Wavehill evaluation report be reported to the Audit Committee when available.
Governance & Audit Committee noted this item on Thursday 7 August 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that (1) the contents of the report be noted (2) a copy of the final Wavehill evaluation report be reported to the Audit Committee when available.
Report of the Chief Auditor
Audit Committee – 7 August 2014
COASTAL PROJECT – UPDATE REPORT
Purpose: This report provides further information on the Coastal Project in particular the evaluation of the Project by Wavehill.
Policy Framework: None.
Reason for Decision: To allow the Audit Committee to discuss and raise any questions regarding the Coastal Project.
Consultation: Legal, Finance, Access to Services.
Recommendation: It is recommended that: the Committee notes the report.
Report Author: Paul Beynon
Finance Officer: Paul Beynon
Legal Officer: Sharon Heys
Access to Services Sherill Hopkins Officer:
1. Introduction
1.1The Head of Finance and Delivery presented a report to the Audit Committee on 24/04/14 which provided details of an investigation undertaken by the Internal Audit Section into the Coastal Project.
1.2The investigation followed a change in the terms and conditions of the grant by WEFO which represented a significant financial risk to the Project as a whole and to the City and County of Swansea in particular.
1.3The report included the full version of the Internal Audit Report and also outlined the management action which had been taken in response to the change in terms of conditions of the grant by WEFO
1.4Discussion of the report was deferred at the meeting on 24/04/14 and the report was subsequently discussed on 12/06/14. 1.5 At the meeting in June, a member of the Audit Committee provided a copy of an evaluation report of the Coastal Project produced by Wavehill dated October 2011.
1.6This report provides the background to the Wavehill report and the implications for the original audit findings as the Wavehill report had not previously been identified during the review of Coastal.
1.7A list of the senior staff in post throughout the Coastal Project is included in Appendix 1
1.8The Chief Social Services Officer and Coastal Regional Project Director will be attending the Audit Committee on 7th August 2014.
2. Wavehill Evaluation Report
2.1All European funded projects with a value in excess of £2m are required by the terms and conditions of the grant to engage an independent, external evaluation of the Project.
2.2The Regional Management Team undertook a procurement exercise in June 2009 using Sell2Wales to appoint a company to provide the evaluation. There were 63 expressions of interest with 5 organisations being shortlisted and Wavehill being commissioned to provide the evaluation in September 2009.
2.3The remit for Wavehill was to provide a ‘formative’ evaluation with a series of progress reports over the course of the Project and a final summary report at Project closure.
2.4To date, Wavehill have produced 4 reports in October 2010, October 2011, February 2012 and January 2013.
2.5The report produced at the last Audit Committee was the second report dated October 2011 and the issue raised at the last Audit Committee was that the Wavehill report identified the same issues as those raised by WEFO when they imposed the 20% retention in August 2013.
2.6An extract of the Wavehill report summary is provided in Appendix 2 showing relevant comments and recommendations. The extract does not show the complete summary of the report as other issues and recommendations which are not relevant to the investigation have been excluded.
2.7The extract in Appendix 2 shows that the issues relating to the slow achievement of targets in particular the employment target and the consequent risk to funding was clearly made by Wavehill in October 2011. 2.8 The final version of the Wavehill report was discussed at the Regional Project Board meeting held on 26/04/12.
2.9Copies of all Wavehill reports were sent to WEFO and at a meeting held with WEFO representatives in February 2012 it was noted that they had no comments to make regarding the 2nd Wavehill report other than it was an honest evaluation with a need to work on the recommendations.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Coastal Project: Update Report.Report | 59 KB | DownloadRead as text |
Follow Governance & Audit Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. | Decided | Open |
| 2 Sep 2026 | Minutes.Approved. | Approved | Open |
| 2 Sep 2026 | Internal Audit Monitoring Report – Q1 2026/27.Noted. | Noted | Open |
| 2 Sep 2026 | Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. | Decided | Open |
| 2 Sep 2026 | Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.