Planning Application 2014/0977 - Parc Ceirw, Cwmrhydyceirw Quarry - Proposed cessation of landfill and other operations enabled by residential development circa 300 dwellings, public open space, associated highway and ancillary work (outline).
RefusedPlanning3 papers
Planning Committee refused this item on Tuesday 7 June 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the application BE REFUSED for the reasons outlined below: Highway Issues The applicant has failed to prove that the additional traffic movements generated by the proposal will not have an adverse effect on local congestion to the detriment of the safe and free flow of vehicles and pedestrians, contrary to the provisions of policies EV1, AS2 and HC2 of the City and County of Swansea Unitary Development Plan (2008). Affordable Housing The proposal fails to provide sufficient affordable housing to contribute towards the demonstrable need within the area, to the detriment of community regeneration and social inclusion. The proposal is therefore contrary the aims of Planning Policy Wales (edition 8) and the Well-being of Future Generations Act 2015.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
1.1This application was reported to Planning Committee on 10th May 2016 with the recommendation that planning permission be approved subject to conditions. Members did not accept the recommendation but resolved that the application be deferred under the two stage voting process so that further advice could be provided on reasons for refusal. The application will not be deemed to be refused unless and until reasons for refusal have been recorded and approved by members.
1.2In reaching a decision Members will need to consider advice on the award of costs in planning appeals in Welsh Office Circular 23/93 : ‘Award of Costs incurred in Planning and other (including Compulsory Purchase Order) Proceedings’. The circular states that Planning Authorities are not bound to adopt, or include as part of their case, the professional or technical advice given by their own officers, or received from statutory bodies or consultees. However, they will be expected to show they had reasonable planning grounds for taking a decision contrary to such advice, and be able to produce relevant evidence to support the decision. If they fail to do so, costs may be awarded against the Authority.
1.2A copy of the report to Planning Committee on 10th May 2016 is attached as Appendix A. The corrections reported on the committee update sheet have been incorporated into the report.
2.0Main Issues
2.1Members identified the following areas as grounds for refusal of the application: highway safety, no affordable homes, loss of amenity for school pupils due to the reduction in play space, the provision of three classrooms is not sufficient and concerns over the long term pumping arrangements.
2.2The applicant’s agent has submitted further information for Committee to consider in response to the discussion at the Planning Committee. The agent has indicated that the issues raised do not provide anything new – with all items having been previously tabled as part of the application and discussed with officers. The response therefore reiterates / repackages the offer, in order to meet the concerns raised by Members. Furthermore, the additional offer in terms of affordable housing provision aims to channel the monies which would otherwise be spent on any appeal (should the application be refused) into the development, and accordingly to the wider benefit of the locality. Should an appeal need to be pursued, then this offer would not be able to be maintained, due to the significant costs that would be associated with progressing an appeal, and the viability positon of the proposal – which has been previously established. It is also reiterated that the Council defined the S106 package and improvement works deemed necessary as proposed at the recent Committee meeting – with reference of course to the established viability position. Affordable housing had initially been part of the applicant S106 offer, but the Council confirmed that their preference was for these monies to go towards education. These current proposals therefore reinstate a contribution towards affordable housing, without diminishing the education contribution (i.e. it will be over and above and not in lieu).
2.3More detailed comment is provided in each of the sub-headings below.
2.4Highway Issues
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Planning Application 2014/0977: Parc Ceirw, Cwmrhydyceirw Quarry: Proposed cessation of landfill and other operations enabled by residential development circa 300 dwellings, public open space, associated highway and ancillary work (outline).Report
10Planning Application 2014/0977 - Parc Ceirw, Cwmrhydyceirw Quarry - Proposed cessation of landfill and other operations enabled by residential development circa 300 dwellings, public open space, associated highway and ancillary work (outline).This decision
Planning Application 2014/0977 - Parc Ceirw, Cwmrhydyceirw Quarry - Proposed cessation of landfill and other operations enabled by residential development circa 300 dwellings, public open space, associated highway and ancillary work (outline).This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.