RESOLVED that the External Funding Panel notes the implications contained in the report and approves the submission of a business case to attract up to £400,000 of funding. The Development & Outreach Manager then raised an urgent issue in relation to assistance that Bishopston School / Leisure Centre required in relation to funding for a 3G facility on the existing Tennis Courts. A Trust had been set up in order to pay for the project; however there was a shortfall of £15,000. He confirmed that the maintenance of the facility would be via the Bishopston Leisure Centre staff and the facility would be utilised by both the school and the Leisure Centre patrons. It was hoped that the work would be undertaken during the School Summer Holidays in order to avoid disruption. The External Funding Panel agreed the funding in principle, subject to a formal report being submitted to the next meeting.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
The City & County of Swansea EFP1 PRE-SUBMISSION - Notification of Funding Bid to Ref: a External Funding Panel THE EFP1 APPLIES TO HARD COPY AND ELECTRONIC SUBMISSIONS 1. Scheme background and details - this is to inform the External Funding Panel of the intention to apply for a new grant proposal – a. Awarding Body Collaborative Sports Facilities Group (representing Sport Wales and the Governing Bodies of Rugby, Football and Hockey in Wales). b. Name and purpose of Collaboration Fund: Potential 3G sites in Scheme/Programme (attach Swansea proposal brief) The ‘All Wales Artificial Turf Pitch Vision and Guidance’ findings indicate that Swansea is the least resourced county in Wales for 3G facilities. The county has the 3rd highest population in Wales and has a vast sports club infrastructure but has no full sized 3G facilities.
The proposed scheme is for; The creation of two full sized floodlit 3G facilities at Cefn Hengoed Comprehensive School/Community Leisure Centre and Bryntawe Comprehensive School/ Penlan Community Leisure Centre . c. Grant value in Total £ £400,000
d. Grant period / timescale 1st December 2106 – 31st August 2017 for delivery e. CCS acting as Lead Body CCS acting as Lead Body or Joint Sponsor? Name other Partners. f. Detail links to existing This project is proposed as a result of a schemes at Local, Regional national study on artificial pitch provision in or National level Wales. Swansea is the least resourced Authority in terms of provision and has the highest number of residents with no access to suitable facilities. The study has identified Swansea as a priority area. g. Detail direct links to Healthy City, Creating an Active and Healthy Council Policy, including, Swansea and where appropriate, target City of Sport areas h. List key target and Work is completed on time and within budget. proposed performance Completed scheme will result in improved measures playing surface and conditions, less cancelled EFP 1
matches and an increase in targeted provision as well as overall increase in participation levels i. For WEFO schemes (attach email confirmation from the European confirm that the scheme has Unit) been developed in conjunction with the European Unit – Yes /No (delete)
j. Does this grant require a NO continuation of funding by the Council after the grant period has expired? This includes current or additional staff costs. Yes / No
k. Does the application Existing capital budget and contribution from require match-funding? Swansea Yes/No if it does where is this coming from? l. Will the project entail the NO employment of additional staff and on what basis? M. Have you completed an yes EIA (Equality Impact Assessment) Screening Form (please attach)?
N. Is a full EIA report no required?
2. Please complete the following financial information: Current Year Year 2 Year 4 Year 5 Total Ongoing financial 3 year £ £ £ £ £ £ £ Total project cost: 100,000 1,000,000 Capital 100,000 1,000,000 Revenue Grant applied for: Capital 100,000 300,000 Revenue Match Funding 300,000 Internal Match Funding 400,000 External
3. Please complete the following: EFP 1
a. Does the funding meet the Yes. Council’s priorities? Healthy City, Creating an Active and Healthy Swansea and City of Sport
(Evidence to be attached) b. What are the expected outcomes The expected outcome is that the project is and are they clear and achievable? completed on time and within budget. The (link to 1h) completed scheme will result in improved playing surface and conditions, less cancelled matches and an increase in targeted provision as well as overall increase in participation levels (Evidence to be attached) c. Is there an exit plan? (link to 1j/l) Yes. Income generated from pitch hire will offset running costs and a sinking fund will be put aside from income generated at both sites for replacing the carpet and shock pad as well as either repair or replacement of fencing and floodlighting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.