Resolved
RESOLVED that: 1) The revised budget be committed to the Capital Programme for 2016-2017 and 2017-2018.
Cabinet decided this item on Thursday 19 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that: 1) The revised budget be committed to the Capital Programme for 2016-2017 and 2017-2018.
1.1In March 2015 Cabinet approved terms for property transactions to facilitate the relocation of a residential facility currently forming part of the proposed St David’s development site. The transactions included the Council acquiring Grwp Gwalia’s (Gwalia’s) existing long leasehold interest in the Llys Dewi Sant building on St David’s Place and the disposal of a similar interest on part of the Vetch site for a replacement building, the construction of which was to be funded by Gwalia from the proceeds of the sale of its interest and Social Housing Grant. At the time of the Cabinet report it was envisaged that no other funding would be necessary based upon Gwalia’s projected development costs at the time 1.2 The financial implications as set out in the Cabinet report were also approved and the scheme added to the Council’s Capital programme.
1.3The Council and Gwalia exchanged conditional contracts in March 2016 subject to certain conditions including the grant of a satisfactory planning consent for the Vetch development and the Council approving any changes to the financial implications of the transaction.
1.4The determination of the planning application for Gwalia’s scheme has been delayed over issues regarding a flood consequences assessment for the scheme. After extensive discussions with National Resources Wales (NRW), NRW are satisfied that the flood risk to the above proposed development can be managed effectively and the application was approved by Planning Committee on 6th December 2016.
1.5Gwalia tendered the construction contract for the development in January 2016 on the basis of which Welsh Government scheme approval was received to confirm the level of grant funding. Due to the delays encountered in the scheme receiving planning consent these tendered costs have since increased in line with agreed published construction cost indices. However now that planning consent has been granted Gwalia are in a position to more accurately assess the final costs of the scheme. As a result it is clear that the proceeds from the disposal of its interest in Llys Dewi Sant together with the awarded Social Housing Grant will be insufficient to fund the scheme and therefore the envisaged shortfall will have to be met by the Council if the transaction is to progress. This report seeks approval for the revised financial implications to be included in the Capital Programme allocated for 2016/17 and 2017/18 to allow this scheme, essential to the delivery of the St David’s development, to progress.
2.0Revised Terms for Transactions
2.1The Council will receive a consideration of £220,000 from Gwalia for the disposal of the lease of part of the Vetch site. This sum will however be paid over by the Council to the Sports Council for Wales in accordance with the terms of a historic grant award. The Council will pay to Gwalia £1.5M in consideration for its lease in Llys Dewi Sant plus compensation payable to Gwalia’s residents as a consequence of the relocation (estimated at £200k) to the Vetch. All values quoted have been verified by the District Valuer.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13: (2 of 2) Copy of App 1- Llys Dewi Sant FPR7 Update finalAppendix | 10 KB | Download |
PDF |
FPR7 Update: Acquisition of Llys Dewi Sant and Disposal of Land at the Vetch Field to Accommodate a Replacement Facility.Report | 85 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.