Resolved
Resolved that: 1) The revision to the proposed project and its Financial Implications be approved and added to the capital programme .
Cabinet approved this item on Thursday 19 October 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) The revision to the proposed project and its Financial Implications be approved and added to the capital programme .
2.1The Kingsway Infrastructure and Employment Hub project is a key component within the Swansea Bay City Deal recently agreed with UK and Welsh Government. A transformational public realm scheme will simplify and rebalance the City’s highway network, providing safer spaces for pedestrians set within a new greener environment presenting a high quality environment for living and working.
2.2The March 2017 cabinet report outlined the scale and scope of the scheme and highlighted amendments made to the proposal following public consultation. The recommendation to approve the proposed scheme and its Financial Implications was supported by Cabinet. At that time the estimated total scheme capital cost was £10m, with a Council contribution of between £6m and £10m, subject to the success of an ERDF funding bid to WEFO for £4m.
2.3A Business Plan to propose the Kingsway project was submitted to WEFO earlier this year seeking grant investment of £4m as part of the funding package to deliver the scheme. As part of recent discussions with WEFO an additional £525k of ERDF grant has been made available and earmarked for the creation or refurbishment of office accommodation within the site area. Feedback from WEFO officers has been positive but stressed the need to utilise the additional grant funding and associated match funding to achieve office refurbishments, jobs created and SMEs accommodated output targets. This will further strengthen the business plan will greatly improve the likelihood of project approval by the end of October 2017.
2.4Under Priority 4, Strategic Objective 4 of the ERDF Operational Programme the key outcomes of this funding stream is to achieve a reduction of benefit claimants through the implementation of projects that will create/refurbish office space that will accommodate businesses at key employment sites and create job opportunities. The revised proposal incorporating the creation or refurbishment of office space along with the original proposal to carry out demolition works, highway reconfiguration and public realm works will significantly strengthen the WEFO bid to justify the need for investment as the Council will be taking an additional step of piloting the creation of high quality office space within the city centre, demonstrating the potential to private sector investors.
3.1Updated cost estimates have been sourced for the public realm, demolition, and highways works, which coupled with the additional office refurbishment works bring the total scheme costs to £12.7m, financed by an ERDF grant of £4.5m and CCS Capital match funding of £8.2m. Scheme Budget Headings £000 Project Management and Compliance 316 Project Delivery Staff 758 Administration Other 2 Advertising & promotion 5 Renovation / Office refurbishment 1,025 Site Works 730 Construction Costs 9,696 Evaluation, development & monitoring 30 Flat Rate (FR15Ge) 161 Total Project Cost 12,723 Financed by: ERDF 4,525 CCS Match Funding 8,198 Total Project Cost 12,723
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
16 (2 of 2): Appendix 1 ERDF 4.4 The Kingsway Employment Hub: Draft Delivery ProfileAppendix | 38 KB | Download |
PDF |
FPR7 Report: The Kingsway Infrastructure Project.Report | 126 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.