CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swansea Council
Governance & Audit Committee, Tuesday 12 December 2017 at 2.00pm

Internal Audit Monitoring Report Quarter 2 2017/18.

Noted Finance 3 papers

Governance & Audit Committee noted this item on Tuesday 12 December 2017. Below is the council's own wording, with the papers it was decided on.

Item56

Resolved

Resolved that: - 1) The contents of the report be noted; 2) The appropriate Head(s) of Service are requested to attend the next scheduled meeting in order to update the Committee regarding progress in respect of their moderate audit ratings.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Chief Auditor

Audit Committee – 12 December 2017

Internal Audit Annual Monitoring Report Quarter 2 2017/18

Purpose: This report shows the audits finalised and any other work undertaken by the Internal Audit Section during the period 1 July 2017 to 30 September 2017.

Policy Framework: None.

Consultation: Legal, Finance, Access to Services.

Recommendation(s): It is recommended that Committee review and discuss the work of the Internal Audit Section and note the contents of the report.

Report Author: Simon Cockings

Finance Officer: Simon Cockings

Legal Officer: Sandie Richards

Access to Services Sherill Hopkins Officer:

1. Introduction

1.1The Internal Audit Annual Plan 2017/18 was approved by the Audit Committee on 28th March 2017 and quarterly monitoring reports will be presented throughout the year to allow Committee to review and comment upon the progress of the Internal Audit Section in achieving the Annual Plan.

1.2This report shows the audits which were finalised in the period 1st July 2017 to 30th September 2017. 2. Audits Finalised 1 July 2017 to 30 September 2017

2.1Due to the Chief Auditor’s retirement at the end of March, plans were put in place to allow the implementation of the Audit Section’s restructure from April 2017. Competitive interviews took place resulting in the appointment of one of the Senior Auditors as the new Principal Auditor. This has resulted in the loss of one full time equivalent post from 2017/18 onwards.

2.2The Internal Audit Section has continued to experience high levels of sickness in the 2nd Quarter of 2017/18 with a total of 63 days absence. Cumulative sickness absence to date stands at 109 days against a projected annual budget of 80 days. As previously reported, most of the sickness in the second quarter has been caused by two members of staff being off for extended periods of time.

2.3A total of 21 audits were finalised during Quarter 2. The audits finalised are listed in Appendix 1 which also shows the level of assurance given at the end of the audit and the number of recommendations made and agreed.

2.4An analysis of the audits finalised during the 2nd Quarter is shown in the following table.

Assurance High Substantial Moderate Limited Level Number 7 12 2 0

2.5A total of 249 audit recommendations were made and management agreed to implement 248 recommendations i.e. 99% against a target of 95%. The one recommendation that was not agreed, for practical operational reasons, was classed as low risk, and is agreed with the S151 Officer.

2.6All recommendations made are classified as high risk, medium risk, low risk or good practice. An analysis of the recommendations agreed during Quarter 2 is shown in the following table

High Medium Low Good Total Risk Risk Risk Practice 0 24 158 66 248

2.7In addition, the Internal Audit Section also certified the following grants in the quarter as required by the terms and conditions of the grant issued by the Welsh Government.

Grant Amount £ Education Improvement Grant 2016/17 9,937,118 Live Kilometre Grant 2016/17 n/a Supporting People Programme Grant 2016/17 – n/a Outcomes Supporting People Programme Grant 2016/17 – 42,374 Regional Development Coordinator School Uniform Grant 2014/15, 2015/16, 2016/17 51,392 45,976 61,037

2.8It was found that in all cases, the grant had been spent in accordance with the agreed purpose and that only eligible expenditure was included.

2.9The Audit Plan is a ‘living’ document which is likely to change during the course of the year due to e.g. emerging risks or new priorities. However it is important that the Audit Committee can monitor progress against the Plan approved at the start of the year. To achieve this, Appendix 2 shows each audit included in the Plan approved by Committee in March and identifies the position of each audit as at 30 September 2017.

2.10The following table shows brief details of the significant issues which led to the two moderate ratings issued in the quarter.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09 (2 of 3): Audit Committee Q2 2017&18 Monitoring Report Appendix 1 meeting 12.12.17Appendix 10 KB Download
PDF
09 (3 of 3): Quarterly Progress Report Q2 2017&18 Appendix 2 Meeting 12.12.17Appendix 24 KB Download
PDF
Internal Audit Monitoring Report Quarter 2 2017/18.Report 128 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
AM
Alan M ThomasChair, apologies
CA
Cyril AndersonCommittee Member, present
TH
Terry HenneganCommittee Member, absent
PH
Paxton Hood-WilliamsCommittee Member, present
BH
Beverley HopkinsCommittee Member, apologies
LJ
Lynda JamesVice-Chair, in the Chair, present
OJ
Oliver JamesCommittee Member, present
JJ
Jeff JonesCommittee Member, apologies
PJ
Peter JonesCommittee Member, present
ML
Mike LewisCommittee Member, present
SP
Sam PritchardCommittee Member, present
WT
Will ThomasCommittee Member, present

All 21 on the meeting page

On this subject at Swansea

Search all
  1. Internal Audit Monitoring Report Quarter 2 2017/18.This decision
  2. Internal Audit Monitoring Report – Q1 2026/27.Noted
  3. Internal Audit Annual Report 2025/26Decided
  4. Swansea Bay City Deal Internal Audit Recommendation Report 2025-26.Decided
  5. Internal Audit Strategy & Draft Annual Plan 2026/27.Agreed
  6. Internal Audit Monitoring Report - Q3 2025/26.Decided

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies