CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swansea Council
Cabinet, Thursday 14 December 2017 at 2.00pm

Quarter 2 2017/18 Performance Monitoring Report.

Noted Executive 2 papers

Cabinet noted this item on Thursday 14 December 2017. Below is the council's own wording, with the papers it was decided on.

Item100

Resolved

Resolved that: 1) The performance results be noted and reviewed to help inform executive decisions on resource allocation and, where relevant, corrective actions to manage and improve performance and efficiency in delivering national and local priorities.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Performance Report - Qtr 2 2017/18

Corporate Performance against Target Corporate Performance compared to Same Period of Previous Year

Overall Council Summary Overall Council Summary

Green Improving 30 18 Static 2

No RAG , 1 New PI, 4 Red Declining 7 21 Amber 8 Performance Report - Qtr 2 2017/18

Priority Performance against Target Priority Performance compared to same period of previous year

Safeguarding Education Safeguarding Education

Improving Green Declining 9 11 2 Green Static, 1 No RAG , 1 4 New PI, 1

Amber, 2 New PI Red Declining 2 6 8

Transformation Economy Transformation Economy

Green Static Improving 3 1 3 Green Improving 5 2

Red Amber Amber New PI 4 1 Declining 1 1 Declining 2 Poverty 5 Poverty

Improving Green 4 7 Amber 1 Declining 4 GREEN AMBER RED Performance Report - 2017/18 Met Target Within 5% of Missed Target Quarter 2 Target

Comparison N – Numerator Result Target Performance Comments PI & desired to D – Denominator Head of direction of Travel Qtr 2 Qtr 2 Qtr 2 Qtr 2 Qtr 2 Qtr 2 (Explanation and Actions) Service 2017/18 2017/18 2016/17 2016/17 2017/18 2016/17

Priority 1 : Safeguarding Priority Lead's Overview Whilst the overall safeguarding arrangements to promote the safety and well being of our most vulnerable citizens are robust, the level of demand for both statutory children and adult services remains high. This high level of demand has led to performance falling just below the ambitious targets set for some of our assessment and decision making timescales. Clear and deliverable management plans are in place to address issues of capacity and improvements to process and we remain confident that improved performance will be achieved over the year. Despite variations in performance against some individual targets when taken as a whole, the health of Swansea's safeguarding and care and support arrangements remains strong. With regards the future sustainability of social care arrangements in Swansea and the shift towards a more preventative model, the positive performance in the areas of safe Looked After Children reduction, local area coordination, annual reviews, re-ablement and support for carers is particularly encouraging. However, a deterioration in performance of delayed transfers of care from hospitals is directly related to community services including social care services becoming saturated through a significant increase in demand for long term social care. Again specific management plans have been agreed between social services and the local health board to alleviate this pressure. Improvements in flow are already beginning to be evidenced as a result. The Council's focus on ensuring all staff and Elected Members understand their safeguarding responsibilities are evidenced by a continued uptake of mandatory training. Elected Member training as part of the induction program for new Councillors proved particularly effective. As more and more staff have been trained, having a realistic target for the number of new staff required to be trained each quarter is difficult to judge and whilst we didn't hit the target of 250, it's still positive that a further 200+ staff engaged this quarter. The number of adult protection enquiries completed in the quarter that were AS8 # AMBER RED completed within 24 hours Performance is slightly lower than Q1 2017/18 and Percentage of adult 204 215 also lower than Q2 2016/17. However, performance protection referrals to Total number of adult protection enquiries is on 1% below this year's target and we are Alex Williams continuing to monitor performance to improve Adult Services where 64.35% 65% 69.58%  completed in the period wherever possible. decision is taken within 24 317 309 hours The number of adult protection enquiries completed in the year that were completed Measure 18 # GREEN RED within seven working days

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08 (2 of 2): Quarter 2 2017-18 Performance Monitoring Report_v4.2 (2 of 2)Report 4.6 MB DownloadRead as text
PDF
Quarter 2 2017/18 Performance Monitoring Report.Report 150 KB Download

At this meeting

Whole meeting

Who was there

9 of 25 attended
RS
Rob StewartChair, present
JB
June BurtonshawCommittee Member, present
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, apologies
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, present
CL
Clive LloydCommittee Member, present
JR
Jennifer RaynorCommittee Member, present
MT
Mark ThomasCommittee Member, present
CS
Chris SiversOfficer, in attendance
MN
Martin NichollsOfficer, expected

All 25 on the meeting page

On this subject at Swansea

Search all
  1. Quarter 2 2017/18 Performance Monitoring Report.This decision
  2. Quarter 1 2026/27 Performance Monitoring Report.Noted
  3. Quarter 4 and End of Year Performance Monitoring Report 2025-26.Noted
  4. Quarter 3 2025/26 Performance Monitoring Report.Noted
  5. Quarter 2 2025/26 Performance Monitoring Report.Decided
  6. Quarter 3 2024/25 Performance Monitoring Report.Decided

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies