Resolved that 1) future Tree Preservation Orders to be served as a Provisional Order are executed by the Head of Planning & City Regeneration( HoP&CR ) and not signed and sealed by the Legal Department. 2) the HoP&CR give authority to the Strategic Planning and Natural Environment Manager and the Landscape Team Leader to execute the orders as set out in paragraph 5.1 to the report in his absence; If this were required, the HoP&CR would be notified of the creation of a new TPO and given the reasons for the required expediency. 3) that the current procedure for confirming the Provisional Orders remain.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Head of Planning & City Regeneration
Planning Committee - 1 May 2018
Proposed Changes To The Creation Of Tree Preservation Order (TPO) Procedure And Scheme Of Delegation.
This report sets out the current signing and sealing procedure for making new TPOs and suggests alterations to the procedure, to allow TPOs to be made more quickly ensuring that trees that are under immediate threat can be protected. The proposed changes will also achieve officer time savings in accordance with Commissioning Review recommendations
1. Introduction
1.1Section 198 of the Town and Country Planning Act give local authorities power to make tree preservation orders: “(1) If it appears to a local planning authority that it is expedient in the interests of amenity to make provision for the preservation of trees or woodlands in their area, they may for that purpose make an order with respect to such trees, groups of trees or woodlands as may be specified in the order.”
1.2Trees that are known to be under threat from removal can only be protected by the formation of a new TPO.
2 Current procedure
2.1The current procedure is that a draft order is made by the Tree Officer and passed to the Strategic Planning and Natural Environment Manager with a report for approval.
2.2Once approved the draft order, report and authority for signing and sealing under delegated powers A37 is passed to the Head of Planning & City Regeneration (HoP&CR) for signing.
2.3The signed report and authority for sealing under delegated power A37 is then taken to the Legal department for sealing and then signing by a Solicitor.
2.4When the Order is signed and sealed it is then served on people with interest in the land affected. 3 Appraisal of current procedure
3.1The current process allows a new TPO to be made in two to three days, depending on availability of officers. This period is often extended due to officer absence during periods of illness or leave. Even the shorter time scale for making a new TPO does not allow a tree to be protected that is under an immediate threat.
3.2There are two steps in the current procedure that could be removed: Legal / Solicitor signing and sealing the Order. HoP&CR signing the report and authority for signing and sealing.
Sealing of Orders 3.3 There is no requirement in the Town and Country Planning Act 1990 or the Town and Country Planning (Trees) Regulations 1999 for the sealing of TPO’s. This is confirmed in Tree Preservation Orders: A Guide to the Law and Good Practice ( the ‘Blue Book’): “It is up to each LPA to decide whether or not their TPOs should be sealed; the TPO legislation does not require the sealing of TPOs”.
3.4The Council’s Constitution in Part 4: Rules of Procedure, page 25 allows for the TPO document to be signed by HoP&CR where other provisions allow it: “33. Signature of Documents Where it is proper that any document be signed on behalf of the Council, it shall, unless any enactment otherwise requires or authorises or the Council shall have given the necessary authority to some other person for the purpose of such proceedings be signed by the Head of Legal, Democratic Services & Business Intelligence (sic) the Solicitor to the Council or Chief Executive where relevant.”
3.5Delegated powers A37 is the document whereby the Council has given the authority to some other person via the Scheme of Delegation, permitting the HoP&CR to sign TPOs.: “A37 Powers relating to the preservation of trees. Sections 197 to 214D of the Town and Country Planning Act 1990 and the Trees Regulations 1999 (S.I. 1999/1892) PC / HoP&CR”
Signing of Orders 3.6 As discussed in 3.3 – 3.5 there is no reason for sealing of the document or signing by a solicitor. The Scheme of Delegation permits execution of the document by the HoP&CR.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.