Report of the Head of Planning and City Regeneration
Planning Committee – 5 June 2018
Abergelli Power Limited (APL) – Gas Fired Power Station Item Report
Purpose: This report provides an overview of the APL submission for Development Consent Order for a gas fired power station at Felindre and seeks delegated powers to respond to the ‘Adequacy of Consultation’ representation.
Legislative Framework: The Planning Act 2008 (as amended). The DCO application will be examined by the Planning Inspectorate who will make a recommendation to the Secretary of State for Business, Energy & Industrial Strategy. The Secretary of State will take a decision on the application on receipt of a recommendation from the Planning Inspectorate.
Policy Framework: National Policy Statements EN-1 and EN-2 provide the overarching national level policy framework for consideration of DCO applications for gas fired power stations and set out the Government's policies for the assessment of DCO applications. City and County of Swansea Unitary Development Plan (Adopted November 2008). The Emerging Local Development Plan (LDP) expected to be the approved plan by late 2018.
Reason for Decision: To enable the Local Planning Authority to respond to the tight deadlines set by the Examining Authority (PINS).
Recommendation: 1) That Committee grant delegated powers to the Head of Planning and City Regeneration to provide a response to the ‘Adequacy of Consultation’ Representation.
Report Author: Andrew Ferguson, Principal Planner Area 1
1.0Introduction:
1.1Abergelli Power Limited (APL), a subsidiary business of Drax Group, wishes to build a gas-fired power station on land located at Abergelli Farm, south of Felindre, adjacent to the National Grid Gas Compressor Station and to the north of the M4 motorway. 1.2 The Project includes a power generation plant and its electrical and gas connections. The Project would have a rated electrical output of up to 299MW. The power generation plant is designed to provide back-up generation capacity which can operate flexibly to respond quickly and efficiently to both short-term variation in customer demand and intermittent output from renewable power generation. It is anticipated that it will operate for up to 2,250 hours p.a. and 1,500 running hours rolling average over 5 yrs.
1.3Given that the proposal is for a thermal generating station with an electrical output in excess of 50 MW the output, the Project is classified as a Nationally Significant Infrastructure Project, which means that a Development Consent Order (DCO) is required to build, operate and maintain it.
1.4The DCO Application will be examined by the Planning Inspectorate (PINS) who will make a recommendation to the Secretary of State for Business, Energy & Industrial Strategy. The Secretary of State will take a decision on the application on receipt of a recommendation from PINS. PINS take around six months to examine an application once submitted. The process will be similar to that of the Tidal Lagoon DCO, albeit that the proposed technology is more common place than the tidal lagoon and various other ‘peaking’ plants have been already been granted a DCO (such as Hirwaun, RCT) so the process should be more straightforward in this regard.
1.5PINS have informed the Local Planning Authority that APL intend to submit their application for an order granting development consent to them on Friday 25 May 2018.
2.0The Site and its Surroundings:
2.1The red line boundary of the project, encompassing all the elements proposed and the maximum extent of land over which powers are sought, is shown below. 2.2 The land at Abergelli Farm consists of grazing fields for sheep, is divided by hedgerows and is generally flat in a slightly undulating landscape. The site is located within the open countryside and lies approximately 1.5km north west of Morriston Hospital. The western extent of the project site encompasses National Grid’s Swansea North electrical substation and Felindre Gas Compressor Station.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Abergelli Power Limited (APL): Gas Fired Power Station.Report | 2.1 MB | DownloadRead as text |
Follow Planning Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Disclosures of Personal and Prejudicial Interests.None | Decided | Open |
| 8 Sep 2026 | Items for deferral/withdrawal.None | Decided | Open |
| 8 Sep 2026 | Determination of Planning Applications under the Town and Country Planning Act 1990.2025/0189/FUL - Approved | Approved | Open |
| 4 Aug 2026 | Disclosures of Personal and Prejudicial Interests.None | Decided | Open |
| 4 Aug 2026 | Minutes.Approved | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.