Resolved that: 1) This new FPR7 and its financial implications be agreed, in line with the Swansea Vale Development Strategy Review (2013) and that this anticipated spend be reflected in the Council's Capital Programme for 2018-2019, 2019-2020 & 2020-2021. 2) Authorisation be granted for the submission of any applications for statutory consent required to deliver the project.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Investment, Regeneration & Tourism
Cabinet – 18 October 2018
Swansea Vale Development Strategy Review FPR7
Purpose: To agree a programme of works in relation to the Swansea Vale Development Strategy Review in line with the Council's Financial Procedure Rule 7 (Capital Programming and Appraisals).
Policy Framework: Swansea Vale Development Strategy Review (2013) Swansea Local Development Plan (Deposit Plan 2016).
Consultation: Legal, Finance and Access to Services.
Recommendation(s): It is recommended that:
1) This new FPR7 and its financial implications is agreed, in line with the Swansea Vale Development Strategy Review (2013) and that this anticipated spend be reflected in the Council's Capital Programme for 2018/19, 2019/20 & 2020/21.
2) Authorisation is granted for the submission of any applications for statutory consent required to deliver the project.
Report Author: Kathryn Morris
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Rhian Millar
1.0Introduction
1.1The Swansea Vale development area is a 190 hectare mixed use development area in the Lower Swansea Valley and has over the last 20 years been an important area for regeneration and investment. 1.2 The Swansea Vale Development Strategy was adopted by the City and County of Swansea in February 2013, and has informed the preparation of the Swansea Vale strategic development area policy (SD I) within the Swansea Local Development Plan (Deposit Plan 2016) . The Strategy and policy confirms that the area still has the potential to deliver a high quality, sustainable mixed use development with an important role to play in the area’s economy.
1.3The previous FPR7 which was taken to Corporate Briefing on 1st October 2013 is now outdated and a new phased programme of implementation has been devised which will enable the full potential for development and enhancement of Swansea Vale to be realised. The programme will require further capital investment to overcome a range of technical and infrastructure issues and deliver a range of environmental enhancements. Cabinet approval of an FPR7 is therefore required to agree the principles of a spending programme to be delivered over the next 3 years. Separate FPR reports will be prepared in line with the council constitution as required.
2.0Delivery of the Development Strategy
2.1Development at Swansea Vale has to date been delivered via a Joint Venture between Welsh Government and City and County of Swansea. Subject to agreement by both parties, the recent agreement dated 30th March 2017, allows for the agreement to run until 31st March 2025.
2.2The Development Strategy incorporates a comprehensive package of projects for delivery over the coming years. Whilst the long term success of the scheme will depend largely upon private sector investment, it is clear that the public sector will also continue to have a crucial role to play in facilitating the ongoing development of Swansea Vale. In order to achieve the overarching vision for the site, there are key preparatory and enabling initial phases of the development which the Joint Venture partners will need to proactively deliver and these include the implementation of flood risk management, site mitigation measures, undertaking feasibility work and where necessary, the provision of infrastructure to facilitate the planned levels of development where required.
2.3Each element of future expenditure and any disposals will require the formal agreement of each of the JV partners. It is intended that the works will be funded by CCS and WG funds currently held on trust and supplemented by new capital and revenue receipts. The new agreement does not require either party to input any new capital funding into the project.
3.0Description of key areas of work
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.