Call-In of Cabinet Decision on 21 February 2019 - Item 9 - 21st Century Schools Programme - New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).
AgreedScrutiny5 papers
Scrutiny Programme Committee agreed this item on Monday 11 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved that: - 1) That Committee agreed Paragraph 4.2 i) as set out in the report, which stated “If satisfied with the explanation it will so indicate to enable the decision to be implemented”. 2) The Vice Chair of the Scrutiny Programme Committee write a letter to the Cabinet Member for Education Improvement, Learning and Skills outlining the views of the Committee.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Education Improvement, Learning and Skills
Cabinet – 21 February 2019
21st Century Schools Programme - New Build For Gorseinon Primary School Purpose: To confirm the commitment to the Capital Programme of the project for the new build for Gorseinon Primary School subject to entering into a contract with Welsh Government, in accordance with Financial Procedure Rule 7.
Policy Framework: The Revenue and Capital Budget as reported to and approved by Council on the 6 March 2018 QEd Programme and Strategic Outline Programme for Band B of the 21st Century Schools Programme Corporate Priority 1 - Safeguarding people from harm Corporate Priority 2 - Improving Education and Skills Corporate Priority 3 – Transforming our Economy and Infrastructure Corporate Priority 4 – Tackling Poverty Corporate Priority 5 - Transformation and Future Council development One Swansea Plan Asset Management Plan 2014-17 Financial Procedure Rule 7.
Consultation: Access to Services, Finance, Legal, Procurement, Corporate Building Services.
Recommendation(s): It is recommended that:
1) The capital project as detailed together with the financial implications set out in Appendix 1 is approved, subject to entering into a contract with the Welsh Government. Report Author: Louise Herbert-Evans
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Catherine Window
1. Introduction and background
1.1The budget book for 2018/19– 2024/25 includes in Band A £6.642m and Band B £500k for a new build for Gorseinon Primary School.
1.2The project has been subject to the successful approval of a Business Case by Welsh Government (WG) and obtained planning approval in December 2015, application number 2015/2074.
1.3The site on which it is proposed to construct the new school build is contained within Parc y Werin in Gorseinon, which was the subject of a Village Green application (VGA) in November 2015.
1.4Consequently, the project was put on hold pending the outcome of that application. The VGA inquiry was held on the 14-16 February 2017.
1.5The application to register Parc y Werin, Gorseinon as a Village Green was recommended for refusal by the Independent Inspector. The Inspector’s report was considered by Swansea Council’s Planning Committee on the 6 June 2017, when in accordance with the Inspector’s recommendation, the application to register the land known as Parc y Werin as a Village Green was refused. The Planning Committee resolved that; the application for Village Green status at Parc y Werin be refused, and ‘that no part of the land of the application site be added to the Register of Town or Village Greens under section 15 of the Commons Act 2006.’
1.6Cabinet again considered this matter on the 19 October 2017, and resolved that; a) The land currently held by the Council as housing and leisure land identified at Appendix A in the report is no longer required for the purpose for which it is currently appropriated;
b) The land at Parc y Werin, Gorseinon identified on the plan at Appendix A of the report be appropriated for the purposes of education under section 122 Local Government Act 1972, namely the construction of a new primary school building;
c) The capital scheme as detailed together with the financial implications set out in Appendix C of the report be approved, subject to entering into a contract with the WG; d) The area of land being approximately 3.212 acres, which is proposed to incorporate an all-weather pitch and Multi Use Games Area (MUGA) and is shown on the plan attached at Appendix B of the report, will form part of the new school grounds and as such will remain under the control of the school, but the (all-weather pitch and MUGA shall be made available for community use when they are not required to be used by the school, the details of which shall be set out in a community use agreement;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Call-In of Cabinet Decision on 21 February 2019: Item 9: 21st Century Schools Programme: New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).Decisions
125Call-In of Cabinet Decision on 21 February 2019 - Item 9 - 21st Century Schools Programme - New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).This decision
Call-In of Cabinet Decision on 21 February 2019 - Item 9 - 21st Century Schools Programme - New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.