Resolved that: - 1) The contents of the report be noted; 2) The Chief Auditor provides the Committee with additional information regarding previous audits at the Village Lane site and why arrears dating back approximately 10 years were allowed to accrue; 3) The Chief Auditor provides the Committee with additional information regarding the significant arrears recorded where no write-off process was in place in respect of the audit of libraries and the lack of appropriate evidence to reconcile overtime payments in respect of the audit of the Food and Safety Division; 4) The Chair writes to Human Resources regarding DBS checks to clarify the time limit for staff to be removed from their job in the event of a negative check.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Internal Audit Annual Plan 2019/20 - Monitoring Report for the Period 1 July 2019 to 30 September 2019
Purpose: This report shows the audits finalised and any other work undertaken by the Internal Audit Section during the period 1 July 2019 to 30 September 2019.
Policy Framework: None.
Consultation: Legal, Finance, Access to Services.
Recommendation(s): It is recommended that Committee review and discuss the work of the Internal Audit Section and note the contents of the report.
Report Author: Simon Cockings
Finance Officer: Simon Cockings
Legal Officer: Tracey Meredith
Access to Services Rhian Millar Officer:
1. Introduction
1.1The Internal Audit Annual Plan 2019/20 was approved by the Audit Committee on 9th April 2019. This is the first quarterly monitoring report to be presented to Committee. Further reports will be presented throughout the year to allow Committee to review and comment upon the progress of the Internal Audit Section in achieving the Annual Plan.
1.2This report shows the audits which were finalised in the period 1st July 2019 to 30th September 2019.
1 2. Audits Finalised 1 July 2019 to 30 September 2019
2.1A total of 25 audits were finalised during the quarter. The audits finalised are listed in Appendix 1 which also shows the level of assurance given at the end of the audit and the number of recommendations made and agreed. Appendix 2 provides a summary of the scope of the reviews finalised during the period.
2.2An analysis of the assurance levels of the audits finalised is shown in the following table.
Assurance High Substantial Moderate Limited Level Number 9 13 3 0
2.3A total of 203 audit recommendations were made and management agreed to implement 201 recommendations, i.e. 99% of the recommendations made were accepted against a target of 95%.
2.4All recommendations made are classified as high risk, medium risk, low risk or good practice. An analysis of the recommendations agreed during the quarter is shown in the following table
High Medium Low Good Total Risk Risk Risk Practice 4 27 123 47 201
2.5The implementation status for those audits that have been subject to a standard follow-up in the quarter is reported separately in the Recommendation Follow-up Report. This include all follow-ups completed, except for the fundamental audits as the outcome of these follow-up reviews is reported to committee via the Fundamental Audit Recommendation Tracker Report.
2.6The Internal Audit Section also certified the following grants in the quarter as required by the terms and conditions of the grant issued by the Welsh Government.
Grant Amount
Regional Consortium School Improvement £8,968,203 Grant (RCSIG / EIG) 2018/19 (£9,408,028 inc. Match Funding) Pupil Deprivation Grant (PDG) 2018/19 £7,469,677 LEA Disadvantaged Learners Grant £2,887,214 SPPG Main Grant 2018/19 £14,086,658 (£178,000 income from partners)
2 2.7 The Audit Plan is a ‘living’ document which is likely to change during the course of the year due to e.g. emerging risks or new priorities. However it is important that the Audit Committee can monitor progress against the Plan approved at the start of the year. To achieve this, Appendix 3 shows each audit included in the Plan approved by Committee in April 2019 and identifies the position of each audit as at 30th September 2019.
2.8An analysis of the details in Appendix 3 shows that by the end of September 2019, 35% of the planned reviews had been completed to at least draft report stage, with an additional 42% of the planned audits in progress. As a result approximately 77% of the Audit Plan was either completed or in progress.
2.9Three moderate reports were issued in the quarter. The following tables provide brief details of the significant issues which led to the moderate ratings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.