Resolved that: - 1) the contents of the report be noted; 2) the risk owner of Health & Safety (CR88) provide further information outlining why air quality was not included in the risk; 3) the Chief Auditor includes a review of Workforce Strategy in the programme of work next year.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Internal Audit Annual Plan Methodology Report 2020/21
Purpose: This report provides a briefing to the Audit Committee on the methodology used to prepare the Internal Audit Annual Plan in advance of the Annual Plan 2020/21 being reported to the Committee for approval on 14 April 2020.
Policy Framework: None
Consultation: Legal, Finance, Access to Services
Recommendation(s): It is recommended that:
1) the Committee note the methodology for preparing the Internal Audit Annual Plan 2020/21.
Report Author: Simon Cockings
Finance Officer: Simon Cockings
Legal Officer: Debbie Smith
Access to Services Rhian Millar Officer:
1. Introduction
1.1The Public Sector Internal Audit Standards (PSIAS) provide a framework for the delivery of a professional, independent and objective internal audit service and are mandatory for all internal audit providers in the public sector in the UK.
1.2One of the requirements of the PSIAS is that an annual risk-based Internal Audit Plan must be prepared to determine the priorities of Internal Audit and to ensure they are consistent with the Council’s goals. The Plan must allow sufficient audit coverage across the whole Council for the Chief Auditor to be able to provide an annual opinion to Council via the Section 151 Officer and Audit Committee on the control environment covering corporate governance, risk management and internal control.
1.3The Audit Plan should ensure that resources are targeted at the areas of the Council’s work where it can provide most benefit by providing assurance over key risks and controls.
1.4The Standards state that the Internal Audit Annual Plan must be discussed with senior management which in the Internal Audit Charter is defined as the Corporate Management Team before being reported to the Audit Committee for approval.
1.5This report provides a briefing on the methodology used to prepare the Annual Plan in advance of the Plan for 2020/21 being reported to the Committee for approval at the next meeting.
2. Internal Audit Plan Methodology
2.1The requirement to produce an Internal Audit Annual Plan is included in the PSIAS which are mandatory for all internal audit providers in the UK public sector.
2.2An extract of the PSIAS requirements regarding internal audit planning is attached in Appendix 1.
2.3The starting point for a risk-based audit approach is gaining an understanding of the Council’s objectives and goals as well as the current key risks faced by the Council as recorded in the Risk Registers.
2.4Information is gathered from a number of sources prior to the preparation of the detailed Audit Plan including:
The Corporate Plan, One Swansea Plan and the Well-Being Statement. Risk Registers. Areas of concern or request for audit coverage from management or the Audit Committee. The Assurance Map which details other sources of assurance available both from internal and external sources. Any recent or proposed significant changes to the Council’s systems or operations. Previous audit results and Internal Audit’s cumulative knowledge of systems and procedures across the Council.
2.5A diagram that illustrates the internal audit annual planning process can be found in Appendix 2. 2.6 Following the gathering of relevant information, an Audit Needs Assessment is completed utilising the risk assessment undertaken for each audit. The risk assessment takes account of a wide range of factors which are grouped into the following categories:
Materiality e.g. income, expenditure. Control Environment/Vulnerability e.g. previous frauds, staff turnover. Management Concerns e.g. direct request for help, potential for embarrassment. Sensitivity e.g. impact on service, effect on Council’s welfare.
2.7A copy of the Risk Assessment form used is attached in Appendix 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.