Governance & Audit Committee, Tuesday 9 February 2021 at 2.00pm

Internal Audit Annual Plan 2020/21 – Monitoring Report for the Period 1 October 2020 to 31 December 2021. (Simon Cockings)

Noted Finance 4 papers

Governance & Audit Committee noted this item on Tuesday 9 February 2021. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

Resolved that: - 1) The contents of the report be noted a long with the possibility of the CIA opinion involving limitation of scope; 2) An update report be provided to the next scheduled meeting regarding the Disclosure and Barring Service.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Chief Auditor

Audit Committee – 9 February 2021

Internal Audit Annual Plan 2020/21 - Monitoring Report for the Period 1 October 2020 to 31 December 2021

Purpose: This report shows the audits finalised and any other work undertaken by the Internal Audit Section during the period 1 October 2020 to 31 December 2020.

Recommendation: That the Audit Committee Members note the information contained in this report.

Policy Framework: None.

Consultation: Legal, Finance, Access to Services.

Report Author: Simon Cockings

Finance Officer: Ben Smith

Legal Officer: Debbie Smith

Access to Services Rhian Millar Officer:

1. Introduction

1.1The Internal Audit Annual Plan 2020/21 was approved by the Audit Committee on 1st June 2020. This is the third quarterly monitoring report to be presented to allow the Committee to review and comment upon the progress of the Internal Audit Section in achieving the Annual Plan.

1.2This report shows the audits finalised in the period 1st October 2020 to 31st December 2020. 1.3 Committee should be made aware that throughout this period the Internal Audit Function and the wider Authority have continued to adapt to the unprecedented challenges as a result of the Covid-19 pandemic, which has impacted every aspect of Council business and operations.

1.4As reported in previous monitoring reports, due to the Covid-19 pandemic access to all council sites has been restricted for the majority of the year. This had a significant impact on the Audit Team’s ability to complete on-site testing. However, the Team has continued to complete as much testing as possible remotely. At the time of compiling the Quarter 1 report we had hoped that the easing of restrictions would continue into Quarter 2 and 3 which would allow the Team to resume site visits. However, at the time of compiling this report, due to the second wave of Covid-19 infections, national lockdown restrictions have been reintroduced. As such, the team is still unable to complete on-site testing.

2. Audits Finalised 1 October 2020 to 31 December 2020

2.1A total of 16 audits were finalised during the quarter. The audits finalised are listed in Appendix 1 which also shows the level of assurance given at the end of the audit and the number of recommendations made and agreed. Appendix 2 provides a summary of the scope of the reviews finalised during the period.

2.2An analysis of the assurance levels of the audits finalised is shown in the following table.

Assurance High Substantial Moderate Limited Level Number 10 6 0 0

2.3A total of 73 audit recommendations were made and management agreed to implement all of the recommendations, i.e. 100% of the recommendations made were accepted against a target of 95%.

2.4All recommendations made are classified as high risk, medium risk, low risk or good practice. An analysis of the recommendations agreed during the quarter is shown in the following table

High Medium Low Good Total Risk Risk Risk Practice 0 11 42 20 73

2.5The implementation status for those audits that have been subject to a standard follow-up in the quarter is reported separately in the Recommendation Follow-up Report. This includes all follow-ups completed, except for the fundamental audits as the outcome of these follow-up reviews is reported to committee via the Fundamental Audit Recommendation Tracker Report. 2.6 The Internal Audit Section also certified the following grants in the quarter as required by the terms and conditions of the grant issued by the Welsh Government.

Grant Amount

Regional Consortia School Improvement £8,855,920.00 Grant (RCSIG) 2019/20 Additional Support for Disadvantaged £4,367,773.00 Learners Grant (Local Authority Education Grant) 2019/20 Supporting People Programme Grant £13,817,121.00 2019/20 Pupil Development Grant 2019/20 £7,506,433.09

2.7Additional work also undertaken by the team in the quarter included:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05 (2 of 4): Q3 Monitoring Report 2020&21: Appendix 1Appendix 230 KB Download
PDF
05 (3 of 4): Q3 Monitoring Report 2020&21: Appendix 2Appendix 343 KB Download
PDF
05 (4 of 4): Appendix 3: Audit Plan 2020&21 Progress at 18.01.21Appendix 483 KB Download
PDF
Internal Audit Annual Plan 2020/21: Monitoring Report for the Period 1 October 2020 to 31 December 2021. (Simon Cockings)Report 284 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 24 attended
CA
Cyril AndersonCommittee Member, present
PB
Peter Black CBECommittee Member, present
SC
Simon CockingsOfficer, present
JM
Julie Mary DaviesCo-Optee, present
MD
Michelle DaviesOfficer, present
JG
Jason GarciaCommunity Representative, absent
DH
David HelliwellCommittee Member, present
TH
Terry HenneganCommittee Member, absent
AH
Adam HillOfficer, present
PH
Paxton Hood-WilliamsCommittee Member, present
JJ
Jeff JonesCommittee Member, present
PK
Peter K JonesCommittee Member, apologies

All 24 on the meeting page

On this subject at Swansea

Search all
  1. Internal Audit Annual Plan 2020/21 – Monitoring Report for the Period 1 October 2020 to 31 December 2021. (Simon Cockings)This decision
  2. Internal Audit Monitoring Report – Q1 2026/27.Noted
  3. Internal Audit Annual Report 2025/26Decided
  4. Swansea Bay City Deal Internal Audit Recommendation Report 2025-26.Decided
  5. Internal Audit Strategy & Draft Annual Plan 2026/27.Agreed
  6. Internal Audit Monitoring Report - Q3 2025/26.Decided

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies