Resolved
Resolved that: 1) Fees of £782k for the Castle Square Regeneration scheme be added to the capital programme in line with Financial Procurement Rule 7 to progress to detailed design, planning and public consultation.
Cabinet decided this item on Thursday 18 February 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) Fees of £782k for the Castle Square Regeneration scheme be added to the capital programme in line with Financial Procurement Rule 7 to progress to detailed design, planning and public consultation.
Report of the Cabinet Member for Investment, Regeneration and Tourism
Cabinet - 18 February 2021
Castle Square Regeneration FPR7 Purpose: To confirm approval of a first stage feasibility and concept study for the regeneration of Castle Square and to seek budget authorisation to progress to the next stages of detailed design, planning and consultation in accordance with Financial Procedure Rule No.7 (Capital Programming and Appraisals) - to commit and authorise the addition of new schemes to the Capital Programme.
Policy Framework: Swansea Local Development Plan (2019), Swansea Central Area Regeneration Framework (2016), Regenerating our City for Well Being and Wildlife (2020) Corporate Priority Creating a Vibrant and Viable City and Economy Council constitution:- Financial Procedure Rules
Consultation: Access to Services, Finance, Legal, Highways and Transportation, Culture and Tourism, City Centre Management, Planning.
Recommendation(s): It is recommended that:
1) Fees of £782k for the Castle Square Regeneration scheme are added to the capital programme in line with Financial Procurement Rule 7 to progress to detailed design, planning and public consultation.
Report Author: Gail Evans Finance Officers: Ben Smith/Jayne James Legal Officer: Debbie Smith Access to Services Officer: Catherine Window
1.0Introduction
1.1Development managers Spider management along with a multi- disciplinary team of consultants were appointed by the Council in 2019 to deliver a regeneration programme for Castle Square from an assessment of feasibility, through to design and construction. Progress to each stage of the project is subject to Council Cabinet approval and subject to a review of available Council funding.
1.2The regeneration project is based on an agreed brief which set out the objectives for an appropriate scale commercial opportunity in the Square, and for the delivery of a step change in the quality of its public realm. The overall aim for these interventions is to increase visitor dwell time in the City centre, create a destination suitable for a range of events, and to make it more active, distinctive and vibrant in line with other regeneration investment which is taking place in the City. The creation and repurposing of space at Castle Square will also make a significant contribution to how the City centre recovers from the economic and social effects of Covid 19, and meets other challenges which may be present post Brexit.
1.3This report summarises the outcome of the first stage feasibility study and the development of the preferred scheme concept, following a series of member and officer workshops. It also sets out the initial estimated scheme cost, anticipated programme for delivery of the proposals, and seeks a budget and authorisation to take the scheme forward to detailed design and planning stage.
2.0Design Concept The concept scheme is based on the overall basic assumption of retaining the stepped amphitheatre form of the Square, removing the existing the fountain, and introducing a range of key interventions which are as summarised below and in Appendix A1, A2 and A3.
2.1Green Infrastructure- A greener Castle Square will have multi-functional benefits for residents and contribute positively to creating an attractive destination space for visitors, connecting the City centre to the waterfront by reinforcing the City’s green artery (as identified in the Swansea Central Area Regeneration Framework-SCARF, 2016).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Castle Square Regeneration FPR7.Report | 1.2 MB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.