Q3 Budget Monitoring 2020-21 - Further Update from Chief Finance Officer

Noted Finance 1 paper

Scrutiny Performance Panel – Service Improvement & Finance noted this item on Monday 8 March 2021. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision is for members as to where money goes – general reserves would need to go up slightly, majority may go to earmarked reserves. Much debate on earmarked reserves – Chief Finance Officer will continue to give the advice that any decision taken must have due regard to previous decisions taken and the future longer-term consequences – e.g. funding the large scale borrowing to come. Outlook for public sector finances is likely bleak. Panel discussed Appendix A, P37 , taking £ 4M out of ear marked reserves, do we anticipate that £ 4m is no longer required? Officers confirm yes, the position at Q3 required that draw, however now certain this anticipated draw would not be needed . Welsh Government have distributed substantial sums to all 22 authorities. Q1 a projected overspend, this rapidly came in, now Q4 likely to be in underspend position. Cannot speculate on amount, although certainly will be a very material sum. Panel discussed Revenue Budget summary – contingency fund of £ 5.9M not currently utilised – given funding levels, why are we not taking money out of this fund? Officers confirmed that this report was written in Q3 and this picture has now changed. This may indeed not all be needed as result of substantial amounts announced due. Financing Charges – reduction noted from £ 36M to £ 28M . Panel queried whether this is due to MRP . With this extra borrowing over next few years, will we end up with capital financing charges of nearer £ 40M ? Officers explain it is difficult to know what the exact figure may be. MTFP that went to Council sets out millions of pounds additional costs going onto capital financing, when council agreed to borrow £ 180M additional borrowing (borrowed £ 90M thus far) MRP currently beneficial, longer term will have higher MRP costs. 50 year consequence – best assumption at time, officer advice is lots of the savings are temporal, we’ve not yet borrowed the full amount, at some point the MRP will reverse. Assumptions over what will benefit council over next 7 years re City Deal. After Year 7 further burden added to capital financing. Tempting to draw from capital equalisation reserve, however, the Well-being of Future Generations Act requires sufficient to fund over life cycle. Capital Equalisation Reserve – panel notes large sums going in , will this continue ? Officer advice is that, if there is a temporal underspend on capital financing, add it into the CER . Peak was borrowing anticipated in 2025/ 26, city deal funding changes may extend that to 2028-29. Cannot be absolutely certain . Commitment to fully fund school ICT infrastructure reserve in budget proposals, all to be funded from Capital Equalisation Reserve. Action point agreed - more detailed information needed about the expected increase in repayments due to the increase in the borrowing requirements.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Scrutiny Performance Panel – Service Improvement & Finance

Report of the Cabinet Member for Economy, Finance & Strategy

Cabinet – 18 February 2021

Revenue and Capital Budget Monitoring 3rd Quarter 2020/21 Purpose: To report on financial monitoring of the 2020/21 revenue and capital budgets

Policy Framework: Budget 2020/21. Transformation and Future Council (Sustainable Swansea –fit for the future)

Consultation: Cabinet Members, Corporate Management Team, Legal Services and Access to Services.

Recommendation(s): It is recommended that Cabinet:

1) Notes the comments and variations set out in the report and the actions in hand to address these;

2) Approves the virements in para 2.7;

3) Reduces the level of permitted, in extremis, in year overspending to £4m, to be fully financed from draws from earmarked reserves, well within the sums approved at Council on 4 November 2020, to ensure the overall budget remains balanced for the year;

4) Continue to endorse that no officer may consider any material further spending commitments and must wherever possible continue to defer and delay spending to contain and reduce the likely modest forecast overspend by year end as far as is practicable, whilst delivering agreed Council priorities set out in the approved budget.

Report Author: Ben Smith

Finance Officer: Ben Smith

Legal Officer: Tracey Meredith

Access to Services Officer: Rhian Millar 1. Background and Introduction

1.1This report details forecast variations from the agreed budget for 2020/21.

1.2In respect of Revenue Budgets, this report provides a consolidated forecast which combines:

 projected variations (mainly shortfalls) in relation to budget savings agreed by Council in March 2020

 Variations arising from other service pressures not directly linked to specific savings plans (e.g. increased service demand, price and pay inflation, increased, but most often unfunded, regulatory obligations and burdens from both UK and Welsh governments)

1.3The report includes comments from Directors in relation to the variations highlighted and the action that is in hand or proposed as appropriate.

2. Revenue Outturn Forecast Based on 3rd Quarter position

2.1Appendix ‘A’ to this report details the approved Revenue Budget for 2020/21 and the forecast variation at this time.

2.2Other than projected variations on Directorate expenditure, it is still too early to confidently forecast final variations that may arise on some significant Corporate items, including the level of Council Tax collection (which posted a deficit in 2019- 20 of £0.7m and 2018-19 of £0.3m). However, given the likely impact of COVID on collection it is inevitable that a further shortfall will arise in 2020-21. An updated forecast is that there remains a potential shortfall of £3.8m in 2020-21. This may be subject to some form of grant underpin support in due course from the Welsh Government, but is far from assured.

2.3The overall Directorate position is summarised below:-

DIRECTORATE FORECAST NET COVID OTHER VARIATION VARIATION VARIATION 2020/21 2020/21 2020/21 £000 £000 £000 RESOURCES 3,366 4,071 -705 PEOPLE - SOCIAL SERVICES 1,983 7,760 -5,777

PEOPLE - EDUCATION 4,898 3,225 1,673 PLACE 6,700 6,700 0 Additional Savings 194 194 NET DIRECTORATE EXPENDITURE 17,141 21,756 -4,615

2.4Directors’ comments on the above variations are shown at Appendix B 2.5 Within the Sustainable Swansea Delivery Programme, work continues to develop service delivery plans that will include all savings requirements across all strands. This includes the cross cutting nature of new reviews as well as the completion of current in-flight reviews.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q3 Budget Monitoring 2020-21: Further Update from Chief Finance OfficerReport 444 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 13 attended
PB
Peter Black CBECommittee Member, present
ED
Emily-Jayne DaviesOfficer, present
PD
Philip DowningCommittee Member, present
CH
Chris Holley OBEChair, present
PH
Paxton Hood-WilliamsCommittee Member, present
LJ
Lynda JamesCommittee Member, present
JJ
Jeff JonesCommittee Member, present
MJ
Mary JonesCommittee Member, present
PK
Peter K JonesCommittee Member, present
IM
Irene MannCommittee Member, present
BR
Brigitte RowlandsCommittee Member, present
BS
Ben SmithOfficer, present

All 13 on the meeting page

On this subject at Swansea

Search all
  1. Q3 Budget Monitoring 2020-21 - Further Update from Chief Finance OfficerThis decision
  2. Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Noted
  3. Revenue and Capital Budget Monitoring 3rd Quarter 2025/26.Decided
  4. Revenue and Capital Budget Monitoring 3rd Quarter 2025/26.Noted
  5. Revenue and Capital Budget Monitoring 2nd Quarter 2025/26.Decided
  6. Revenue and Capital Budget Monitoring - 3rd Quarter 2024/25.Decided

More from Swansea Scrutiny Performance Panel – Service Improvement & Finance

All decisions
MeetingDecisionOutcome
10 May 2021 Welsh Housing Quality Standards Annual UpdateAGREED that officers would circulate housing project information to relevant ward members. The Panel took the opportu... Agreed Open
12 Apr 2021 Corporate Complaints Annual ReportAGREED that Members request further information about The Ombudsman criteria around justified and not justified cases... Agreed Open
6 Sep 2017 End of Year 2016/17 Performance Monitoring ReportIt was agreed that the following queries be referred to relevant officers for response: 1. Priority 3 EC3 states that... Agreed Open
6 Sep 2017 Capital Outturn and Financing 2016/17It was agreed that the following queries be referred to relevant officers for response: 1. The Panel received a prese... Agreed Open
6 Sep 2017 Quarter 1 Revenue and Capital Budget Monitoring 2017/18It was agreed that the following query be referred to relevant officers for response: 1. Within the Budget Monitoring... Agreed Open