Internal Audit Monitoring Report - Quarter 3 - 2022/23.

Decided Finance 5 papers

Governance & Audit Committee decided this item on Wednesday 8 February 2023. Below is the council's own wording, with the papers it was decided on.

Item84

Resolved

For information.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Chief Auditor

Governance & Audit Committee – 8 February 2023

Internal Audit Monitoring Report Quarter 3 – 2022/23

Purpose: This report shows the audits finalised and any other work undertaken by the Internal Audit Section during the period 1 October 2022 to 31 December 2022.

Policy Framework: None.

Consultation: Legal, Finance, Access to Services.

Report Author: Simon Cockings

Finance Officer: Ben Smith

Legal Officer: Debbie Smith

Access to Services Rhian Millar Officer:

For Information

1. Introduction

1.1The Internal Audit Annual Plan 2022/23 was approved by the Governance & Audit Committee on 12 April 2022. This is the third quarterly monitoring report to be presented to allow the Committee to review and comment upon the progress of the Internal Audit Section in achieving the Annual Plan.

1.2This report shows the audits finalised in the period 1 October 2022 to 31 December 2022. 2. Audits Finalised 1 October 2022 to 31 December 2022

2.1A total of 10 audits were finalised during the quarter. The audits finalised are listed in Appendix 1 which also shows the level of assurance given at the end of the audit and the number of recommendations made and agreed. Appendix 2 provides a summary of the scope of the reviews finalised during the period.

2.2An analysis of the assurance levels of the audits finalised is shown in the following table.

Assurance High Substantial Moderate Limited Total Level Number 3 7 0 0 10

Assurance Level

23%

77%

High Substantial Moderate Limited

2.3A total of 80 audit recommendations were made and management agreed to implement all 80 recommendations, i.e. 100% of the recommendations made were accepted against a target of 95%.

2.4All recommendations made are classified as high risk, medium risk, low risk or good practice. An analysis of the recommendations agreed during the quarter is shown in the following table:

Risk High Medium Low Good Total Level Risk Risk Risk Practice Number 0 9 65 6 80 Recommendations Agreed

8% 11%

81%

High Risk Medium Risk Low Risk Good Practice

2.5The implementation status for those audits that have been subject to a standard follow-up in the quarter is reported separately in the Recommendation Follow-up Report. This includes all follow-ups completed, except for the fundamental audits as the outcome of these follow-up reviews is reported to the Committee via the Fundamental Audit Recommendation Tracker Report.

2.6The Audit Plan is a ‘living’ document which is likely to change during the course of the year due to e.g. emerging risks or new priorities. However it is important that the Committee can monitor progress against the plan approved at the start of the year. To achieve this, Appendix 3 shows each audit included in the Plan approved by Committee on the 12 April 2022 and identifies the position of each audit as at 31 December 2022.

2.7The team continues to work both from home and in the new office space in the Guildhall. The Office is shared with one other section, but to ensure confidentiality the Audit and Fraud Team has sole occupancy on set days. All audit paper files are also kept secure in locked cabinets with only Audit staff having access.

2.8An analysis of the details in Appendix 3 shows that as at 31/12/22, 41 audit activities from the 2022/23 audit plan had been completed to at least draft report stage (32%), with an additional 30 activities noted as being in progress (23%). As a result approximately 55% of the audit activities included in the 2022/23 Audit Plan had either completed or were in progress.

2.9As previously reported in previous reports, staff sickness in the Internal Audit Team has continued to been significant during the quarter, with a total of 61 days absence recorded. The cumulative number of days lost due to sickness in the year to date is approximately 180 days. At the time of compiling this report, one members of staff continues to be absent due to long-term sickness. They are currently being supported by Human Resources and Occupational Health.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
04 (2 of 5): Appendix 1: Audits Finalised Q3Appendix 126 KB Download
PDF
04 (3 of 5): Appendix 2: Audit Scope Q3Appendix 154 KB Download
PDF
04 (4 of 5): Appendix 3: Internal Audit Annual Plan 2022&23 status at 31-12-22Appendix 192 KB Download
PDF
04 (5 of 5): Appendix 4: IIA screening form Q3Appendix 185 KB Download
PDF
Internal Audit Monitoring Report: Quarter 3: 2022/23.Report 372 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

24 of 31 attended
PO
Paula O'ConnorChair, present
GA
Gordon AndersonCo-Optee, present, as expected, virtual
JM
Julie Mary DaviesCo-Optee, present, as expected, virtual
PS
Philip SharmanCo-Optee, present
TH
Terry HenneganCommittee Member, absent
PH
Paxton Hood-WilliamsCommittee Member, present
AJ
Allan JefferyCommittee Member, present
JJ
Jeff JonesCommittee Member, present
ML
Mike LewisCommittee Member, apologies
ML
Michael LockeCommittee Member, present
SP
Sam PritchardCommittee Member, present, as expected, virtual
KR
Kelly RobertsCommittee Member, apologies

All 31 on the meeting page

On this subject at Swansea

Search all
  1. Internal Audit Monitoring Report - Quarter 3 - 2022/23.This decision
  2. Internal Audit Monitoring Report – Q1 2026/27.Noted
  3. Internal Audit Annual Report 2025/26Decided
  4. Swansea Bay City Deal Internal Audit Recommendation Report 2025-26.Decided
  5. Internal Audit Strategy & Draft Annual Plan 2026/27.Agreed
  6. Internal Audit Monitoring Report - Q3 2025/26.Decided

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open