Resolved
Approved
Council approved this item on Thursday 2 March 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Approved
Report of the Section 151 Officer
Council – 2 March 2023
Capital Budget & Programme 2022/23- 2027/28
Purpose: This report proposes a revised capital budget for 2022/23 and a capital budget for 2023/24 - 2027/28
Policy Framework: Sustainable Swansea – Fit for the Future
Consultation: Cabinet Members, Corporate Management Team (CMT), Legal, Finance and Access to Services
Recommendation(s): It is recommended that Council:
1) Approves the revised capital budget for 2022/23 and the capital budget for 2023/24 – 2027/28 as detailed in appendices A, B C, D, E, F and G is approved.
Report Author: Ben Smith
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Rhian Millar Officer:
1. Introduction
1.1This report details:
Revised capital expenditure and financing proposals for 2022/23 Capital expenditure and financing proposals for 2023/24 – 2027/28
1.2Capital spending and funding proposals in relation to the Housing Revenue Account (HRA) are detailed in a separate report to be considered. 1.3 The capital budget proposals are detailed in appendices to this report as follows:
Appendix A Total General Fund Capital Budget Expenditure 2022/23 - 2027/28
Appendix B Total General Fund Financing 2022/23 - 2027/28
Appendix C General Fund Capital Budget Expenditure (excluding C21st School programme and Swansea Central City Deal Schemes) 2022/23 - 2027/28
Appendix D C21st Schools Programme Band A Capital Expenditure and Budget 2012/13 – 2022/23
Appendix E QEd/Sustainable Communities for Learning Programme Capital Expenditure and Budget 2017/18 – 2027/28
Appendix F Swansea Central City Deal Capital Expenditure and Budget 2018/19 – 2023/24
Appendix G Material changes to the original 2022/23 budget
1.4Appendix A, C, D, E and F outline a comprehensive programme of capital investment including:
A continuing programme of IT investment across the Council The continued investment in Swansea Schools through Band B of the QED/Sustainable Communities for Learning Schools Programme, which now has four completed projects, and one project under construction. Swansea Bay City Deal schemes, the completion of Phase 1 the North Block including the Arena with further elements due for completion during the coming 12 months and commencement of construction of Phase 2 Digital Village 71-72 Kingsway Offices A significant programme of capital expenditure to assist the City’s economic recovery from the Covid 19 pandemic
1.5The additional capital investment identified above will attract significant grant funding (QED/Sustainable Communities for Learning Schools Programme and Swansea Bay City Deal), however the programme will still require material unsupported borrowing to enable completion alongside the use of capital receipts as they are realised. Furthermore some schemes have the potential to provide additional revenue streams of property income, or, subject to agreement, in due course, with Welsh Government, retained elements of non- domestic rates or possibly tax increment financing as further powers devolve to Welsh Government and then on to local government. 1.6 Notwithstanding this scale of ambition, each major scheme will, as is always the case, be considered on the overall merits of each business case, both in capital cost, and revenue income streams where appropriate, and unsupported borrowing will be undertaken on a phased basis within the overall medium/long term envelope of affordability.
Furthermore it has to be recognised that the scale of funding proposed to be injected by this Council, leverages in significant additional sums: £107m of Welsh Government funding for Band B schools a City Deal, worth, across the region, around £1.3 billion.
The Council continues to face significant challenges delivering the Capital Programme during uncertain economic times with high inflation impacting on capital budgets.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
11: Appendix AAppendix | 69 KB | Download |
PDF |
11: Appendix BAppendix | 78 KB | Download |
PDF |
11: Appendix CAppendix | 92 KB | Download |
PDF |
11: Appendix DAppendix | 70 KB | Download |
PDF |
11: Appendix EAppendix | 73 KB | Download |
PDF |
Capital Budget & Programme 2022/23- 2027/28.Report | 301 KB | DownloadRead as text |
Follow Council at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors C M J Evans, B Hopkins, D H Hopkins, N L Matthews & S J Rice – item 15 – personal & prejudicial Councillo... | Decided | Open |
| 3 Sep 2026 | Minutes.Approved | Approved | Open |
| 3 Sep 2026 | Written Responses to Questions asked at the Last Ordinary Meeting of Council.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Presiding Member.For Information | Decided | Open |
| 3 Sep 2026 | Announcements of the Leader of the Council.For Information | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.