CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Swansea Council
Governance & Audit Committee, Wednesday 8 March 2023 at 2.00pm

Progress on the Upgrade of Oracle.

Decided Finance 2 papers

Governance & Audit Committee decided this item on Wednesday 8 March 2023. Below is the council's own wording, with the papers it was decided on.

Item102

Resolved

For information.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Interim Director of Corporate Services

Governance & Audit Committee – 8 March 2023

Progress on the Upgrade of Oracle Purpose: To provide assurance on progress of the upgrade to the Oracle system.

Policy Framework: Digital Strategy 2022-23 Corporate Plan Transformation and Future Council Wellbeing Objective

Consultation: Finance, Legal.

Report Author: Sarah Lackenby

Finance Officer: Ben Smith

Legal Officer: Tracey Meredith

For Information

1. Introduction

1.1The Oracle upgrade will go-live in April 2023, after which there will be five to six weeks of support whilst the system stabilises into the day-to-day business of the Council.

1.2The project will then move towards an orderly close down until the end of June, after which an internal audit of the project will be undertaken in July.

1.3This report provides the Governance & Audit Committee with an interim update and assurance on progress of the project. 2. Background and Context

2.1In September 2019, Cabinet approved the upgrade of the council’s Enterprise Resource Planning (ERP) System 1 because the current system was becoming end of life and would no longer be supported.

2.2The initial agreed go-live date for the new system was November 2020 but delivery was delayed by the onset of the pandemic at the end of March 2020 when the council went into business continuity mode. The pandemic and its aftereffects continued to impact the project as the council prioritised support for residents and businesses. In October 2022 Cabinet agreed a revised go-live deadline of April 2023.

2.3The high-level project plan (Appendix A) includes milestones. Each of the milestones has defined entry and exit criteria. These must be met before moving forward, or in a small number of cases, plans are put in place if any activities are carried forward into future phases, e.g., where Oracle may be working on change requests to the system.

3. Current Status

3.1Good progress has been made since the completion of the testing phase (User Acceptance Testing) in October 2022. In addition, the governance of the project has been strengthened, with the Interim Director of Corporate Services, as project sponsor, assuming chair of the project board. The membership of the board has also been strengthened with the addition of two Heads of Service from the business side.

3.2Since October the project board has met every fortnight, receiving highlight and risk monitoring reports as well as regular budget updates. Now the project is moving towards go-live we have introduced additional light touch board meetings in between the full board meetings to ensure there is a weekly opportunity to review progress, the action log, risks and issues. The Board also keeps the corporate risk continually under review.

3.3The project is currently in the payroll parallel run (PPR) phase. This is where payrolls are run simultaneously between the old and the new system to compare details and ensure they are correct. The threshold for passing the PPR is that 99% of records on the old and new system match.

3.4Swansea has three payrolls; Teachers’, Pensions’ and the monthly payrolls and all three have now reached the 99% target. The PPR phase is scheduled to end by 3rd March 2023.

3.5Report testing is ongoing and has been run in parallel to all the milestones. The teams are making progress in the build and testing of priority one

1 The ERP system provides the following council back-office functions: finance, payroll, HR and

capital project management reports (i.e., reports that must be ready on go-live), with a plan to deliver lower priority reports due after go live.

3.6The table below shows the progress on each milestone:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09 (2 of 2): DocumentsAppendix A High Level PlanAppendix 226 KB Download
PDF
Progress on the Upgrade of Oracle.Report 157 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 23 attended
PO
Paula O'ConnorChair, present
GA
Gordon AndersonCo-Optee, apologies
JM
Julie Mary DaviesCo-Optee, present, as expected, virtual
PS
Philip SharmanCo-Optee, present, as expected, virtual
PH
Paxton Hood-WilliamsCommittee Member, present
AJ
Allan JefferyCommittee Member, present
JJ
Jeff JonesCommittee Member, present, as expected, virtual
ML
Mike LewisCommittee Member, present
ML
Michael LockeCommittee Member, present
SP
Sam PritchardCommittee Member, present, as expected, virtual
KR
Kelly RobertsCommittee Member, present, as expected, virtual
LW
Lesley WaltonCommittee Member, present, as expected, virtual

All 23 on the meeting page

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies