Resolved that: 1) The key aims and focus of the Strategic Outline Programme previously supported by the Welsh Government be re-affirmed. 2) The proposed future capital investment priorities for the Sustainable Communities for Learning Strategic Outline Programme (Rolling) be endorsed, recognising that there is no absolute commitment to the funding on either Council or Welsh Government as it is approved in due course on a case-by-case basis even if the SOP is otherwise approved by both Council or Welsh Government. 3) The scale of the overall funding ask and proposed funding strategy to meet Council’s local contribution be noted, recognising the future detailed funding and affordability decisions will be for future Councils, future budgets and medium term plans in the early 2030’s.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Education and Learning
Cabinet - 15 February 2024
Quality In Education (Qed) – Emerging Proposals and Investment Priorities for the Sustainable Communities for Learning Strategic Outline Programme (Rolling) Purpose: To consider and endorse the Sustainable Communities for Learning Strategic Outline Programme (Rolling) for submission to the Welsh Government.
Policy Framework: Corporate Plan 2023/2028 QEd programme Abertawe 2028
Consultation: Education, Finance, Legal and Access to Services, Corporate Building Services and Corporate Property Services
Recommendation(s): It is recommended that Cabinet:
1) Re-affirms the key aims and focus of the Strategic Outline Programme previously supported by the Welsh Government
2) Endorses the proposed future capital investment priorities for the Sustainable Communities for Learning Strategic Outline Programme (Rolling), recognising that there is no absolute commitment to the funding on either Council or Welsh Government as it is approved in due course on a case-by-case basis even if the SOP is otherwise approved by both Council or Welsh Government.
3) Notes the scale of the overall funding ask and proposed funding strategy to meet Council’s local contribution, recognising the future detailed funding and affordability decisions will be for future Councils, future budgets and medium term plans in the early 2030’s.
Report Author: Louise Herbert-Evans Finance Officer: Ben Smith Legal Officer: Caritas Adere Access to Services Officer: Catherine Window 1.0 Background
1.1The purpose of this paper is to consider and endorse the future proposals and investment priorities for the next phase of the Sustainable Communities for Learning Programme, previously known as the 21st Century Schools Programme, for submission to the Welsh Government.
1.2In July 2017 Cabinet endorsed the council’s Band B of the 21st Century Schools Strategic Outline Programme and the proposed capital investment priorities. Since the initial approval there have been several other changes within the programme. The Welsh Government capital grant intervention rate was set at 50% for Band B, but Welsh Government announced on 21 November 2018, that the Band B intervention rate for capital projects would be increased to 65%, and for special schools and PRUs to 75%. The intervention rate for voluntary aided projects remained unchanged at 85%. In September 2023, Cabinet endorsed an uplift to the programme envelope to £176m, with a switch to wholly capital funding (instead of using the Mutual Investment Model for some of the projects).
1.3Since 2017, the remaining Band A project - a new build for Gorseinon Primary School - has been completed. The completed Band B projects are new builds for the Pupil Referral Unit (Maes Derw), YGG Tan y lan and YGG Tirdeunaw, and new blocks and refurbishment and remodelling for Ysgol Gyfun Gwyr and Bishopston Comprehensive School.
1.4In January 2022 the Programme was renamed ‘Sustainable Communities for Learning (SCfL)’ by the Welsh Government (WG) to make a clear statement about its commitment towards the environment, community cohesion, and our future generations. This Programme is expected to see a further £2.3 billion investment in school and college infrastructure utilising both public capital and revenue.
1.5Band B ends on 31 March 2024 and councils are now required to submit a new Strategic Outline Programme (SOP) to WG for a rolling programme by 31 March 2024.
1.6The nine-year capital programme, including an indicative funding forecast for the nine years, is required to be submitted to the Welsh Government for consideration towards providing a commitment and support for the first three years along with in-principle support for years 4, 5 and 6. Years 7 to 9 will reflect the longer-term project pipeline. Band B projects not yet completed can be included at the beginning of the nine- year capital programme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quality In Education (Qed): Emerging Proposals And Investment Priorities For The Sustainable Communities For Learning Strategic Outline Programme.Report
117Quality In Education (Qed) – Emerging Proposals And Investment Priorities For The Sustainable Communities For Learning Strategic Outline Programme.This decision
Quality In Education (Qed) – Emerging Proposals And Investment Priorities For The Sustainable Communities For Learning Strategic Outline Programme.This decision
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.