Resolved
Noted.
Governance & Audit Committee noted this item on Wednesday 5 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted.
Report of the Chief Auditor
Governance & Audit Committee – 5 March 2025
Internal Audit Monitoring Report Quarter 3 – 2024/25 Purpose: This report shows the audits finalised and any other work undertaken by the Internal Audit Section during the period 1 October 2024 to 31 December 2024.
Policy Framework: None.
Consultation: Legal, Finance, Access to Services.
Recommendation: It is recommended that the report is noted.
Report Author: Simon Cockings
Finance Officer: Ben Smith
Legal Officer: Lucy Moore
Access to Services Rhian Millar Officer:
1. Introduction
1.1The Internal Audit Annual Plan 2024/25 was approved by the Governance & Audit Committee on 5 June 2024. This is the third quarterly monitoring report to be presented to allow the Committee to review and comment on the progress of the Internal Audit Section in achieving the Annual Plan.
1.2This report shows the audits finalised in the period 1 October to 31 December 2024.
2. Audits Finalised 1 October to 31 December 2024
2.1A total of 14 audits were finalised during the quarter. The audits finalised are listed in Appendix 1 which also shows the level of assurance awarded at the end of the audit and the number of recommendations made and agreed. Appendix 2 provides a summary of the scope of the reviews finalised during the period.
2.2An analysis of the assurance levels of the audits finalised is shown in the following table and chart:
Assurance High Substantial Moderate Limited Total Level Number 7 7 0 0 14
Assurance Level
50% 50%
High Substantial Moderate Limited
2.3A total of 85 audit recommendations were made and management agreed to implement all of them. i.e., 100% of the recommendations were accepted against a target of 95%.
2.4All recommendations are classified as High Risk, Medium Risk, Low Risk or Good Practice. An analysis of the recommendations agreed during the quarter is shown in the following table and chart:
Risk High Medium Low Good Total Level Risk Risk Risk Practice Number 0 10 61 14 85 Recommendations Agreed
16% 12%
72%
High Risk Medium Risk Low Risk Good Practice
2.5The Audit Plan is a ‘living’ document which is likely to change during the year due to emerging risks or new priorities. However, it is important that the Committee can monitor progress against the plan approved at the start of the year. To achieve this, Appendix 3 shows each audit included in the Plan approved by Committee on the 5 June 2024 and identifies the position of each audit as at the 31 December 2024.
2.6A successful recruitment campaign resulted in three full-time auditor posts being filled in December. However, unfortunately 71 days were lost in quarter two due to vacant posts. This represents approximately 12% of the total available days in quarter 2, or 10% cumulative days lost of the total available days in the year to date due to vacant posts. 49 days were also lost in the quarter due to one instance on long-term sickness absence, which is ongoing. Note however that contingencies for vacancies and sickness absence have been built into the annual plan.
2.7The Internal Audit Annual Plan for 2024/25 contains 120 separate audit activities. As at 31 December 2024, 55 audit activities (46%) had been completed, with two additional activities (3%) substantially complete with the audit report issued as draft. As a result, 57 audit activities have been completed to at least draft report stage (48%). An additional 32 activities were in progress at the end of the quarter (27%). As a result, approximately 75% of the audit activities included in the 2024/25 Audit Plan had either been completed or were in progress. A copy of the plan showing the status of the activities as at the 31 December 2024 can be found in Appendix 3.
2.8No ‘Moderate’ or ‘Limited’ assurance audit reports were issued in the quarter. 3. Additional work undertaken by Internal Audit in the Quarter
3.1The Internal Audit Team also certified the following grants as required by the terms and conditions of the grants issued by the Welsh Government.
Grant Amount
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
07 (2 Of 7) Appendix 1: Audits Finalised Q3Appendix | 506 KB | Download |
PDF |
07 (3 of 7) Appendix 2: Audit Scope Q3Appendix | 525 KB | Download |
PDF |
07 (4 of 7) Appendix 3: Internal Audit Annual Plan 2024&25 status at 31-12-24Appendix | 159 KB | Download |
PDF |
07 (5 of 7) Appendix 4: High & Substantial Follow Up Results Q3Appendix | 735 KB | Download |
PDF |
07 (6 of 7) Appendix 5: High & Substantial Q3 Recs Not ImplementedAppendix | 742 KB | Download |
PDF |
07 (7 of 7) Appendix 6: IIA screening form Q3Appendix | 145 KB | Download |
PDF |
Internal Audit Monitoring Report: Quarter 3: 2024-2025.Report | 194 KB | DownloadRead as text |
Follow Governance & Audit Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. | Decided | Open |
| 2 Sep 2026 | Minutes.Approved. | Approved | Open |
| 2 Sep 2026 | Internal Audit Monitoring Report – Q1 2026/27.Noted. | Noted | Open |
| 2 Sep 2026 | Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. | Decided | Open |
| 2 Sep 2026 | Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.