AI summarySwansea Council deferred item 111, councillors' questions, at its 5 March 2026 meeting. The appendix lists school capital projects totalling 57,574,335 spent, 7,936,935 in construction and 304,314,929 planned.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDeferredItem 111, councillors' questions, deferred at 5 March 2026 council meeting
MoneyNot stated
What happens nextTo be considered laterDeferred item 111 to a future council meeting
Who it affectsSchool projects, councillors, residentsAppendix lists capital projects across multiple Swansea schools

What was decided

Swansea Council deferred item 111, councillors' questions, at the 5 March 2026 meeting.

What happens next

The deferred item is to be considered at a future council meeting.

The money

  • 57,574,335 Total spend on completed school capital projects Report P23
  • 7,936,935 Total expected spend on projects in construction phase Report P26
  • 304,314,929 Total expected spend on projects in pre-construction phase Report P35
  • 11,253,361 Ysgol Gynradd Gymraeg Tirdeunaw Band B new build school on new site Report P3
  • 15,086,893 Bishopston Comprehensive Band B new build block and refurbishment Report P6
  • 7,955,747 Cefn Hengoed Community hub, sports barn and family engagement centre Report P14
  • 102,860,614 Ysgol Calon Lân Rolling Programme new build school on new site Report P31
  • 90,599,507 Bishop Vaughan Catholic Comprehensive new build school on new site Report P33

Implications

  • Other: The deferral means councillors' questions on the listed school capital projects will be addressed at a later meeting rather than 5 March 2026. Report P1

Who and where

  • School pupils, staff and communities across Swansea served by listed capital projects Report P3, P4, P5, P6, P14, P31, P33
  • Councillors submitting questions under item 111

Timeline

  • Sept 2020: Ysgol Gynradd Gymraeg Tirdeunaw start on site, completed Oct-21 Report P3
  • Feb 2026: Demolition of buildings on the former Daniel James site, Rolling Programme, completion Autumn 2026 Report P24
  • May-27: Ysgol Calon Lân new build school on new site start on site, completion May-29 Report P31
  • 2029: Portmead/Blaenymaes Primary amalgamated new build school start on site, completion 2031 Report P34
  • 5 March 2026: Council meeting where item 111 was deferred
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item111

Resolved

Deferred
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Council

Appendix A proposed Date of Amount spent to School Funding stream Description of works start on site completion date

Completed schemes

Ysgol Gynradd Gymraeg Tirdeunaw Band B New build school on new site Sept 2020. Oct-21 11,253,361

Ysgol Gynradd Gymraeg Tan-y-lan Band B New build school on new site July 2020. Dec-21 9,828,735

New build block and Ysgol Gyfun Gŵyr Band B refurbishment of the former July 2020. June 2022. 6,930,077 canteen building and drama block

New build block and refurbishment of the school Bishopston Comprehensive Band B Jun-20 Jun-23 15,086,893 buildings and removal of all demountable buildings

Olchfa School CFS and land sale New 3 G pitch 2023 2024 1,638,782

Remodel of existing building into St Joseph's Cathedral Primary UFSM grant 2024 2025 758,636 new dining hall and kitchen

Mayals Primary UFSM grant refurbished kitchen 2025 2026 862,866

Pontarddulais Comprehensive CFS scheme 2022 2023 265,116

Pontarddulais Primary CFS scheme 2023 2025 123,336

Casllwchwr Primary CFS scheme Toilet refurb throughout school 2023 2025 272,205

Seaview Primary CFS scheme new build block 2024 2026 329,245 Appendix A remodel and refurb of pool Pennard Primary CFS scheme 2024 2026 178,561 changing rooms

Cefn Hengoed Community hub and community hub, sports barn and CFS scheme 2020 2023 7,955,747 family engagement centre community engagement centre

Ysgol Gyfun Gŵyr ALN scheme improving STF provision 2024 2025 330,261

Bishop Gore Comprehensive ALN scheme improving STF provision 2024 2026 133,493

Clwyd Primary ALN scheme improving STF provision 2024 2025 168,237

STF cluster Birchgrove Primary, YGG Bryniago, Craigfelen Primary and Grange ALN scheme improving STF provision 2024 2025 576,389 Primary, Penclawdd Primary

Oystermouth primary ALN scheme improving STF provision 2024 2025 100,949

Cwmglas Primary ALN scheme improving STF provision 2024 2026 197,376

Penyrheol Primary ALN scheme improving STF provision 2024 2026 256,000

Cadle Primary ALN scheme improving STF provision 2024 2026 328,070

Total spend on completed projects 57,574,335

Proposed proposed Projects currently in construction phase date of Scheme budget start on site completion Demolition of the buildings on the February Former Daniel James demolition Rolling Programme Autumn 2026 2,000,000 former Daniel James site 2026. February Waun Wen Primary UFSM grant refurbished kitchen Jun-26 599,508 2026. Appendix A new build block for kitchen and Townhill Primary UFSM grant 2026 2027 4,987,427 dining hall, new MUGA

Clase Primary CFS scheme new build block 2025 2026 350,000

Total expected spend 7,936,935

Proposed proposed Projects currently in pre-construction phase date of Scheme budget start on site completion

Bishopston Primary ALN scheme new build block 2026 2027 300,000

new build block with new kitchen Brynhyfryd Primary UFSM grant and dining hall and some 2026 2027 2,578,420 refurbishment of existing building New build block and Rolling Programme Ysgol Gyfun Gymraeg Bryn Tawe refurbishment of some of the Jul-26 Mar-28 33,255,894 and CFS scheme existing buildings

Clydach Primary Rolling Programme Refurbishment of existing building 2027 2028 2,042,414

Ysgol Calon Lȃn Rolling Programme New build school on new site May-27 May-29 102,860,614

New build block and Gowerton School (secondary) Rolling Programme refurbishment of some of the Autumn 2027 Jun-29 47,202,967 existing buildings

Bishop Vaughan Catholic Comprehensive Rolling Programme New build school on new site 2027 2029 90,599,507

Portmead/Blaenymaes Primary Rolling Programme Amalgamated new build school 2029 2031 25,475,113

Total expected spend 304,314,929

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cllr Questions AppendReport 124 KB DownloadRead as text
PDF
Councillors' Questions.Report 252 KB Download

At this meeting

Whole meeting

Who was there

76 of 80 attended
CA
Cyril AndersonCommittee Member, present
AA
Alyson AnthonyCommittee Member, present
MB
Matthew BaileyCommittee Member, present
MB
Mair BakerCommittee Member, present
SB
Sam BennettCommittee Member, present
PB
Patience BentuCommittee Member, present
PB
Peter Black CBECommittee Member, present
JC
Jan CurticeChair, present
AD
Adam DavisCommittee Member, present, as expected, virtual
MD
Mike DayCommittee Member, apologies
PD
Philip DowningCommittee Member, present
RD
Ryland DoyleCommittee Member, present, as expected, virtual

All 80 on the meeting page

On this subject at Swansea

Search all
  1. Councillors' Questions.This decision
  2. Councillors' Questions.Decided
  3. Councillors' Questions.Decided
  4. Councillors' Questions.Decided
  5. Councillors' Questions.Decided
  6. Councillors' Questions.Decided

More from Swansea Council

All decisions
MeetingDecisionOutcome
3 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors C M J Evans, B Hopkins, D H Hopkins, N L Matthews & S J Rice – item 15 – personal & prejudicial Councillo... Decided Open
3 Sep 2026 Minutes.Approved Approved Open
3 Sep 2026 Written Responses to Questions asked at the Last Ordinary Meeting of Council.For Information Decided Open
3 Sep 2026 Announcements of the Presiding Member.For Information Decided Open
3 Sep 2026 Announcements of the Leader of the Council.For Information Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies