Resolved
Resolved that pursuant to paragraph 100B (4)(b) of the Local Government Act 1972, the Leader of the Council agreed that the report on the Redevelopment of St Helens should be considered at the meeting as a matter of urgency. Reason for Urgency : An urgent decision of Cabinet is required due to the need to commence works on the Artificial Grass Pitch (AGP) / 4G pitch in April if the ground is to be available for the start of the 2026/27 rugby season. The Ospreys have already appointed contractors to undertake the works, and it is proposed that the Council, subject to due diligence checks, appoint the same contractors to avoid incurring any delay.