Corporate Services Directorate Risk Management Arrangements and Key Risks.

Noted Finance 3 papers

AI summaryGovernance and Audit Committee noted Swansea Council's Corporate Services Directorate risk management report, covering strategic and operational risks as at 31 March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCorporate Services Directorate strategic and operational risks
MoneyNot stated
What happens nextNot stated
Who it affectsCorporate Services DirectorateStrategic and operational risk oversight

What was decided

The committee noted the Corporate Services Directorate risk management arrangements and key risks report, which is accompanied by two appendices: a strategic risks report and an operational risks report, both dated 31 March 2026. Report P4

Why

The report supports the Governance and Audit Committee's assurance role and reflects the Council's corporate risk management policy and framework. Report P3, P5

Implications

  • Financial: No additional financial implications for the Council, as the report is for information only. Report P1
  • Legal: No legal or governance implications beyond those identified within the report itself. Report P3
  • Risk: The report forms part of the Council's corporate risk management policy and framework for the directorate. Report P3, P5

Who and where

  • Swansea Council's Governance and Audit Committee Report P3
  • Corporate Services Directorate Report P4

Timeline

  • 31 March 2026: Strategic and operational risk reports prepared Report P4
  • 15 April 2026: Report considered by Governance and Audit Committee
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item107

Resolved

Noted.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Director of Corporate Services

Governance and Audit Committee – 15 April 2026

Corporate Services Directorate Risk Management Arrangements and Key Risks Executive Summary Purpose of Report:

To provide assurance to the Governance and Audit Committee that risk management arrangements within the Corporate Services Directorate are effective, embedded and operating in line with the Council’s corporate risk management policy and framework, including use of the corporate InPhase risk system and routine review and escalation arrangements.

Recommendation(s). It is recommended that the Committee notes the: 1) Corporate Services Directorate’s risk management arrangements as set out in this report, including how risks are identified, recorded, reviewed, escalated and assured; and 2) key strategic and operational risks currently being managed within Corporate Services, as referenced in this report and Appendix A.

Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☐ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☒ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution:

Terms of Reference of the Governance and Audit Committee, as set out in the Council Constitution, including the Committee’s responsibility “to monitor the effective development and operation of risk management in the Council” and “to provide independent assurance of the adequacy of the risk management framework.”

Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☒ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☐ Not Applicable Relevance to Corporate Plan Wellbeing Objectives: This report supports effective corporate governance and financial resilience by providing assurance that key risks are identified, monitored and managed in line with the Council’s corporate risk management policy and framework. The report reflects corporate arrangements and risks that can have cross-council impacts (for example cyber security, ICT resilience and business continuity).

This report relates to corporate risk management arrangements and therefore has relevance beyond Corporate Services. The corporate policy and framework apply across the whole Council.

Reviewed and approved by: Access to Services, Finance, Legal, Relevant Cabinet Member.

Report Author & Job Title: Ness Young, Director of Corporate Services

1. Introduction

2. The Governance and Audit Committee has a role in challenging and providing independent assurance on the adequacy and effective operation of the Council’s risk management policy and framework.

3. The Council’s Risk Management Policy and Risk Management Framework establish the principles, roles and practical approach for identifying, evaluating, responding to, and monitoring risks, including the distinction between strategic and operational risks and the application of risk appetite and tolerance.

4. This report sets out the risk management arrangements operating within the Corporate Services Directorate and highlights the key strategic and operational risks currently being managed, referencing specific risks recorded on the directorate risk register extract provided at Appendix A.

5. The report is intended to provide assurance that Corporate Services is identifying, monitoring and managing risk effectively and consistently, in line with the corporate framework and reporting expectations.

6. Advice

7. Corporate Services risk management arrangements

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09 (2 of 3) Appendix A: Public Strategic Risks: 31 March 2026 v1Appendix 4.3 MB Download
PDF
09 (3 of 3) Appendix B: Public Operational Risks: 31 March 2026Appendix 304 KB Download
PDF
Corporate Services Directorate Risk Management Arrangements and Key Risks.Report 179 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 17 attended
PO
Paula O'ConnorChair, present
GA
Gordon AndersonCo-Optee, apologies
DR
David RobertsCo-Optee, present
PB
Patience BentuCommittee Member, present, as expected, virtual
OJ
Oliver JamesCommittee Member, absent
JJ
Jeff JonesCommittee Member, apologies
ML
Michael LockeCommittee Member, present
SP
Sam PritchardCommittee Member, present
MW
Mike WhiteCommittee Member, present, as expected, virtual
NY
Ness YoungOfficer, present
AJ
Adrian JeremiahOfficer, present
SC
Simon CockingsOfficer, present, as expected, virtual

All 17 on the meeting page

On this subject at Swansea

Search all
  1. Corporate Services Directorate Risk Management Arrangements and Key Risks.This decision
  2. Social Services Directorate Assurance on Corporate Risk ManagementNoted
  3. Update on Internal Control Environment - Director of Corporate Services.Noted
  4. Options for the Appointment for the Post of Director of Corporate Services.Approved
  5. Corporate Services Directorate: Internal Control Environment 2022/23.Decided
  6. Scrutiny of Cabinet Member Portfolio Responsibilities: Houses in Multiple Occupation - Councillor David Hopkins, Cabinet Member for Corporate Services & Performance.Decided

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies