Financial Procedure Rule 7 – Award of Grant Funding - Regional Transport Fund – Financial Years 2026/27, 2027/28 and 2028/29.
ApprovedExecutive2 papers
AI summarySwansea Cabinet approves accepting Regional Transport Fund grants for transport, active travel, EV charging and road safety schemes across 2026/27 to 2028/29.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevenue grant added to Road Safety budget
Money£8,250Inner Swansea Masterplan / Tawe Riverside Corridor total, in £'000
What happens nextNot stated
Who it affectsNot stated
What was decided
Cabinet approved receipt of the Regional Transport Fund grant and delegated authority to the Director of Finance with the Cabinet Member for Environment and Infrastructure and the Director of Place to accept the grant for all RTF schemes.
Cabinet approved the addition of the funded schemes to the Council's capital programme in line with Financial Procedure Rule 7.
Cabinet approved adding the revenue grant funding to the Council's revenue budget for Road Safety.
Why
The schemes rely upon the Regional Transport Fund to provide grant funding to secure their delivery. Report P2
Accepting the funding and approving the schemes will enable the Council to comply with its obligations under the Active Travel (Wales) Act 2013. Report P18
Claims are to be made to the Welsh Government on a quarterly basis for any schemes granted funding. Report P3
What happens next
Schemes will be added to the Council's capital programme and the Road Safety revenue budget.
Quarterly claims to be submitted to the Welsh Government, with any grant awarded claimed in full by the 31st of March 2027 or it will be lost. Report P3
Land agreements, whether by purchase or lease, should be in place prior to the commencement of scheme construction and delivery. Report P12
The money
8,250 Inner Swansea Masterplan / Tawe Riverside Corridor total capital expenditure, in £'000 Report P72
4,830 Swansea Bay & West Wales Metro total capital expenditure, in £'000 Report P25
800 Killay Square Flood Alleviation total capital expenditure, in £'000 Report P48
750 Swansea E-Bike Micro-Mobility Hire total capital expenditure, in £'000 Report P108
700 NCN Improvements / Gowerton to Loughor total capital expenditure, in £'000 Report P96
545 Road Safety Capital total capital expenditure, in £'000 Report P167
500 NCN Improvements / Dunvant to Gowerton Widening total capital expenditure, in £'000 Report P84
111,670 Road Safety Revenue total expenditure, including £96,670 RTF Revenue Grant and £15,000 match funding Report P185, P187
Options considered
Chosen: Approve receipt of Regional Transport Fund grant, add schemes to capital programme and add revenue grant to Road Safety budget. Schemes rely on RTF funding to be delivered and acceptance supports compliance with the Active Travel (Wales) Act 2013 Report P2, P18
Implications
Financial: Any revenue costs (such as highway maintenance) arising from capital schemes must be met by existing internal revenue budgets, with no additional funding available, placing additional pressures on Highways Maintenance and Cleansing. Report P4
Financial: Ongoing maintenance of new active travel routes will be needed, though significant improvements to existing routes are intended to increase longevity. Report P5
Financial: All maintenance, servicing, operation and ongoing revenue costs for the proposed e-bike hire scheme will be placed on the commercial operator. Report P5
Legal: Welsh Government transport capital infrastructure grants will require spend to be compliant with the Council's Contract Procedure Rules and Procurement Legislation. Report P7
Legal: Delivery of transport schemes will require compliance with relevant Highways and Transport Act measures and guidelines, and the Active Travel (Wales) Act 2013. Report P8
Legal: Where the Council wishes to acquire land, terms must be negotiated by the Head of Property Services in line with the Council's Land Transaction Procedure Rules. Report P10
Risk: Any grant awarded must be claimed in full by the 31st of March 2027, otherwise it will be lost. Report P3
Other: Planning consent may be required for the Electric Vehicle Charging Infrastructure and Active Travel Fund schemes, including a submitted application for Phase 1 of Loughor to Gowerton. Report P13, P14, P15, P16
Who and where
Council's Highways and Transport service Report P4
Walking, cycling and wheeling users Report P19
Electric vehicle owners and on-street charging trial participants Report P14, P152
Residents in flood alleviation scheme areas including Killay Square and Scurlage to Llandewi Corner Report P44, P56
Communities along the Loughor to Gowerton active travel route Report P16
Landowners where acquisitions or licences are required for scheme delivery Report P10, P16
Timeline
2026/27: First financial year of grant-funded scheme delivery Report P22, P33, P45
2027/28: Second financial year of capital expenditure for multi-year schemes Report P22, P69
2028/29: Third and final financial year of capital expenditure for multi-year schemes Report P22, P69
31st of March 2027: Deadline to claim in full any RTF grant awarded, otherwise the funding will be lost Report P3
Before scheme construction and delivery: Land agreements, whether by purchase or lease, must be in place Report P12
Plain English for the jargon
RTF: Regional Transport Fund (Welsh Government grant funding stream)
FPR7: Financial Procedure Rule 7, the Council's rule for award of grant funding
ATF: Active Travel Fund, used for walking and cycling infrastructure
NCN: National Cycle Network
EV: Electric Vehicle
P&R: Park and Ride
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item190
Resolved
Resolved that: 1) The receipt of the grant funding and delegates authority to the Director of Finance in conjunction with the Cabinet Member for Environment and Infrastructure and the Director of Place to accept the grant funding awarded for all RTF schemes be approved. 2) The addition of the funded schemes to the Council’s capital programme in line with FPR7 be approved. 3) The addition of the revenue grant funding to the Council’s revenue budget for Road Safety be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Environment & Infrastructure
Cabinet – 16 April 2026
Financial Procedure Rule 7 – Award of Grant Funding - Regional Transport Fund 2026/27, 2027/28 and 2028/29 Executive Summary Purpose of Report: To approve the capital and revenue grant funding awarded from the Regional Transport Fund (RTF), approving expenditure on the associated projects in 2026/27, 2027/28 and 2028/29.
To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals): to commit and authorise schemes in the Capital Programme.
Recommendation(s). It is recommended that Cabinet: 1) Approves receipt of the grant funding and delegates authority to the Director of Finance in conjunction with the Cabinet Member for Environment and Infrastructure and the Director of Place to accept the grant funding awarded for all RTF schemes. 2) Approves the addition of the funded schemes to the Council’s capital programme in line with FPR7. 3) Approves the addition of the revenue grant funding to the Council’s revenue budget for Road Safety. Decision-Making Authority www.swansea.gov.uk/constitution: ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why
Relevance to Corporate Plan Wellbeing Objectives: Capital investment in walking, cycling and public transport schemes improve public health, well-being and footfall, enabling mixed use centres and boosting local economic resilience.
Expanding public electric vehicle (EV) charging infrastructure supports the adoption of EVs. Providing walking, cycling, and public transport alternatives reduces reliance on private vehicles for everyday journeys, accelerating decarbonisation and supporting a net zero Swansea in 2050. Walking, cycling, and public transport infrastructure provide affordable and accessible alternatives to private vehicles, helping to connect communities, reduce transport poverty, provide access to employment and education.
Reviewed and approved by: Access to Services, Finance, Legal & Cabinet Member.
Report Author & Job Title: Chloe Lewis, Team Leader – Transport Strategy & Monitoring
1. Introduction
2. Funding applications for the Regional Transport Fund (RTF) were submitted by the South West Wales Corporate Joint Committee (CJC) to the Welsh Government (WG) on 31st January 2026.
3. The schemes submitted form the South West Wales region’s Year 1 capital transport delivery programme for 2026-27, mark the first phase of a five-year Regional Transport Delivery Plan (RTDP) to 2030. Schemes within Swansea Council’s Year 1 delivery plan include the following scheme categories, as prescribed by WG.
Capital: • Road Safety Engineering & Signage • Walking, Cycling and Wheeling • Public Transport • Electric Vehicle Charging • Highways Revenue: • Road Safety Education, Training and Publicity
4. Local Authorities are responsible for scheme delivery, with programme oversight and coordination provided by the CJC.
5. On 18 March 2026 the Welsh Government confirmed the grant award for the 2026-27 RTF delivery programme, with Swansea Council receiving grant awards for schemes within the local authority area and funding for the Swansea Bay and West Wales Metro, on behalf of the wider South West Wales region.
6. Swansea Council has received a capital grant award for transport schemes within Swansea, of £5,955,000 and revenue grant award of £96,670 for 2026/27. A further £1,500,000 for 2027/28 and £3,500,000 for 2028/29 has also been awarded.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.