AI summarySwansea Council Cabinet approves refreshed draft Active Travel Network Map for a 12-week statutory public consultation, ahead of submission to Welsh Government by 1 December 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedRefreshed draft ATNM to go to 12-week statutory public consultation
MoneyNot stated
What happens nextStatutory consultation then Welsh Government12-week consultation followed by finalisation and submission by 1 December 2026
Who it affectsResidents and stakeholders across SwanseaInvited to comment on proposed walking, wheeling and cycling routes
What was decided
The refreshed draft Active Travel Network Map was approved to enable the Council to carry out statutory public consultation. Report P3
Authority was delegated to the Cabinet Member for Environment & Infrastructure and the Director of Place to finalise recommendations and submit the map to Welsh Government after consultation. Report P3
Why
The Active Travel (Wales) Act 2013 places a statutory duty on local authorities to review and submit an updated Active Travel Network Map; the current map was approved in 2022 and a new one must be submitted by 1 December 2026 under a Welsh Ministerial Direction of 23 November 2023. Report P3
An initial six-week public consultation ran from 17 November 2025 to 4 January 2026, gathering suggestions from councillors, officers, residents, businesses and organisations, which have been used to develop the draft map. Report P3, P10, P12
What happens next
The Council will undertake a 12-week statutory public consultation on the draft ATNM, including further engagement with disability groups, internal and external stakeholders and the public. Report P3, P13
Following consultation, the Cabinet Member for Environment & Infrastructure and the Director of Place will finalise recommendations and submit the ATNM to Welsh Ministers for approval. Report P3
Subject to Welsh Government approval, the refreshed map will replace the 2022 iteration as the strategic tool guiding Welsh Government-funded active travel schemes in Swansea. Report P3
Options considered
Chosen: Approve the refreshed draft ATNM for statutory consultation and delegate authority to finalise and submit to Welsh Government. Required to meet statutory duty under the Active Travel (Wales) Act 2013 and the 1 December 2026 submission deadline Report P3
Implications
Legal: The ATNM supports compliance with the Council's statutory duty under the Active Travel (Wales) Act 2013 and does not itself commit the authority to delivery of any route. Report P3, P28
Equalities: Screening identified no adverse implications; expected positive impact on groups facing travel barriers, including those without access to a private car. Report P4, P25, P27
Climate: Promotes sustainable transport by guiding future walking, wheeling and cycling routes, contributing to a healthier and more environmentally resilient Wales. Report P25, P28
Other: Other Council service areas will need to consider the ATNM where their work interfaces with existing and proposed routes. Report P20
Who and where
Residents across Swansea, including those without access to a private car Report P25
Local councillors, Swansea Council officers, businesses and other organisations in Swansea Report P10
Disability groups Report P13
Welsh-medium schools, community centres and cultural facilities Report P8
Timeline
2022: Current ATNM approved by Welsh Ministers Report P3
23 November 2023: Welsh Ministerial Direction extended next ATNM resubmission period from three years to five years Report P3
17 November 2025 to 4 January 2026: Initial six-week public consultation and stakeholder engagement exercise Report P10
10/04/2026: Integrated Impact Assessment screening completed by Chloe Lewis Report P30
14/04/2026: Screening approved by Head of Service Stuart Davies Report P30
2026: 12-week statutory public consultation to be undertaken on the draft ATNM Report P3, P13
1 December 2026: Deadline for submission of final ATNM to Welsh Ministers for approval Report P3
Plain English for the jargon
ATNM: Active Travel Network Map, a strategic map showing existing and proposed future walking, wheeling and cycling routes.
ATA: Active Travel (Wales) Act 2013, which places statutory mapping, planning and promotion duties on local authorities in Wales.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
Resolved that: 1) The refreshed draft Active Travel Network Map, in order that the Council can carry out statutory public consultation be approved. 2) Following the consultation, authority be delegated to the Cabinet Member for Environment & Infrastructure and Director of Place to finalise recommendations for final amendments to the Active Travel Network map and to submit to Welsh Government.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Integrated Impact Assessment Screening Form Appendix F
Please ensure that you refer to the Screening Form Guidance while completing this form. Which service area and directorate are you from? Service Area: Highways and Transportation Directorate: Place Q1 (a) What are you screening for relevance? New and revised policies, practices or procedures Service review, re-organisation or service changes/reductions, which affect the wider community, service users and/or staff Efficiency or saving proposals Setting budget allocations for new financial year and strategic financial planning New project proposals affecting staff, communities or accessibility to the built environment, e.g., new construction work or adaptations to existing buildings, moving to on-line services, changing location Large Scale Public Events Local implementation of National Strategy/Plans/Legislation Strategic directive and intent, including those developed at Regional Partnership Boards and Public Services Board, which impact on a public bodies functions Medium to long term plans (for example, corporate plans, development plans, service delivery and improvement plans) Setting objectives (for example, well-being objectives, equality objectives, Welsh language strategy) Major procurement and commissioning decisions Decisions that affect the ability (including external partners) to offer Welsh language opportunities and services Other
(b) Please name and fully describe initiative here: The Active Travel (Wales) Act 2013 (ATA) places a statutory duty on local authorities in Wales to map, plan for and promote active travel journeys. As part of the act, a map of both existing and future routes must be produced. The maps are known as Active Travel Network Maps (ATNM). They show existing active travel routes and related facilities and proposed future routes across the local authority area. To meet the duties of the ATA, local authorities in Wales must review and submit an updated ATNM to the Welsh Ministers for approval every three years, unless directed otherwise by Ministers. The current ATNM was approved by Welsh Ministers in 2022. A Welsh Ministerial Direction issued on 23 November 2023 extended the next ATNM resubmission period from three years to five years, to be submitted for approval no later than 1 December 2026. A programme of work has been undertaken during 2025/26 to prepare for the December 2026 ATNM submission including route auditing, route review and rationalisation and initial public consultation and stakeholder engagement. This has resulted in a Draft ATNM update being developed that will form the basis of a 12-week statutory public consultation in 2026. Subject to approval by Welsh Ministers, the final refreshed ATNM will replace the 2022 iteration as the new strategic map used to support the delivery of the Council’s active travel programme, guiding the long-term planning and development of Welsh Government‑funded active travel schemes in Swansea.
Q2 What is the potential impact on the following: the impacts below could be positive (+) or negative (-) High Impact Medium Impact Low Impact Needs further No Investigation Impact + - + - + - Children/young people (0-18) OIder people (50+) Any other age group Future Generations (yet to be born) Disability 1 Integrated Impact Assessment Screening Form Appendix F
Race (including refugees) Asylum seekers Gypsies & travellers Religion or (non-)belief Sex Sexual Orientation Gender reassignment Welsh Language Poverty/social exclusion Carers (inc. young carers) Community cohesion Marriage & civil partnership Pregnancy and maternity Human Rights
Q2b) Welsh Language Impacts
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.