Resolved – (1) That the aims and objectives set out in the Land Disposal Strategy, attached at Appendix 2 to the joint report of the Cabinet Member for Resources and the Group Directors for Environment and Leisure and Resources dated 16 th September 2005, be approved. (2) That, subject to the endorsement of a "Gateway 2" report by the Procurement Advisory Group, the Director of Property be authorised to appoint a Land Disposal Agent for the Southern Development Area. (3) That, further to the decision (2) above, the appointed agent be required to prepare a detailed disposal strategy document for approval by the Cabinet that addresses, explores and challenges all the opportunities for the Area as referred to in the joint report of the Cabinet Member for Resources and the Group Directors for Environment and Leisure and Resources dated 16 th September 2005. (4) That the current planning position with regard to the Swindon , as referred to in the joint report of the Cabinet Member for Resources and the Group Directors for Environment and Leisure and Resources dated 16 th September 2005, be noted. (5) That the Director of Property be authorised to take all steps required to action the recommendations set out in (1) to (4) above. (CM: FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
2.1To agree the aims and objectives set out in the land disposal strategy attached at Appendix 2.
2.2Subject to endorsement of a Gateway 2 report by the Procurement Advisory Group, to authorise the appointment of a land disposal agent.
2.3To require the appointed agent to prepare a detailed disposal strategy document for the approval of Cabinet that addresses, explores and challenges all the opportunities referred to in the report.
2.4To note the current planning position.
2.5To authorise the Director of Property to take all steps required to action the recommendations set out above.
3 Financial and Procurement Implications
3.1The appointment of a land disposal specialist will exceed the OJEU limit on fees of £153,000 and therefore a formal notice must be placed following approval by Procurement Advisory Group of the Gateway 2 report.
3.2Subject to tender, the fees for this appointment will be met from capital receipts. 4 Social, Environmental, Staffing, Legal/Human Rights, Risk and Other Implications
4.1Social Implications – There are many potential social implications when building a new community which are largely to be addressed when considering the opportunities referred to in the report.
4.2Environmental Implications – Development of the Southern Development Area (SDA) will meet and hopefully exceed the environmental requirements conditioned by the planning consent.
4.3Staffing implications – There are no new staffing implications arising from this report and the trade unions have not been consulted.
4.4Legal / Human Rights Implications – Relevant documentation will be completed. There are no known new human rights issues arising from this report.
4.5All other Risk Implications – There is a risk that market conditions may change to reduce receipts and slow down development. Delays in proceeding with this project may lead to difficulties in achieving 2010 promises.
5 Detail
5.1The Southern Development Area (SDA) offers the Council a tremendous opportunity to influence and promote an exemplar development over the next 10 – 15 years.
5.2Set out in Appendix 1 is a précis of the planning situation on this site dealing with the current situation and the flexibility to influence the final development.
5.3The Council has also entered into a Collaboration Agreement to further reinforce the guiding principles set down in the planning consent and to secure funding for the development infrastructure to proceed.
5.4Set out in Appendix 2 are the agreed Goals and Objectives to be applied in developing a land disposal strategy.
5.5The land disposal strategy will challenge our perception of how we wish to see development proceed e.g. what type of retail provision is needed as a main food anchor or the nature, size and style of the employment land.
5.6There will be wider opportunities to forge major partnerships to secure these elements of the development that will also engage with sustainability issues and energy management.
5.7Leisure and recreation are other areas where new and innovative means of provision and management can be explored and in all these cases the opportunity exists for the Council and other stakeholders to play a major part in shaping the direction of these activities.
5.8We are currently setting up robust project arrangements. These include a joint Council / Taylor Woodrow board, which deals solely with the provision of primary infrastructure and, under the terms of the Collaboration Agreement, a jointly appointed project manager, who will take responsibility for the day to day coordination of that task.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.