Resolved – (1) That the progress of the project for the development of a new Swindon Central Library and First Stop Shop carried out to date be noted. (2) That a decision on selecting the preferred procurement route for the new Swindon Central Library be deferred, in order to enable further design studies to be carried out to ensure that the design is sympathetic to the Town Hall and fully meets the requirements of English Heritage. (3) That the Group Director, Environment and Leisure, be authorised to identify a suitable location for a temporary Swindon Central Library within the Central Area and to make arrangements for temporary provision within the Council's Capital Budget. (4) That the Group Director, Environment and Leisure be authorised to let an "enabling works contract" on terms to be agreed in consultation with the Director of Law and Democratic Services, in order to clear the site ahead of construction. (CM: RB)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
By: Cabinet Members for Leisure, Parish/Ward: All Culture and Recreation and Regeneration, Sustainability and Transport Planning and the Director of Planning
Procurement Options for the New Swindon Central Library 1 Purpose 1.1 To consider options for procurement processes and enabling works for the new Swindon Central Library and First Stop Shop. 2 Recommendations
2.1That the progress on the project carried out to date be noted.
2.2That the Group Director, Environment and Leisure be authorised to go out to tender, on terms to be agreed in consultation with the Director of Law and Democratic Services, to procure provision of the Swindon Central Library and First Stop Shop through a ‘traditional construction route’ employing project management consultants and lead design consultants, controlled by an internal project manager with appropriate support.
2.3That the Group Director, Environment and Leisure be authorised to identify a suitable location for a temporary Swindon Central Library within the central area, and to make arrangements for temporary provision within the capital budget.
2.4That the Group Director, Environment and Leisure be authorised to let an enabling works contract, on terms to be agreed in consultation with the Director of Law and Democratic Services, in order to clear the site ahead of construction.
3 Financial and Procurement Implications
3.1The Swindon Full Recovery report approved by the Council on 9 June 2005 included a provisional capital budget of £10 million for the library and First Stop Shop. These estimated capital costs include indicative provisions for professional fees, and for temporary relocation of the library, as well as build costs for the new library and First Stop Shop. Appendix 4 shows that the estimated cost has now increased to £10.8m. This estimate excludes the costs associated with fitting out the First Stop Shop, any potential relocation of Cre-8 and/or Swindon Dance and refurbishment costs of the existing buildings. The exact costs will not become clear until the tenders have been received. However, Members will need to agree that any increase in costs becomes a first calling on future years capital budgets.
3.2Indicative revenue projections of £348K per annum were identified in the 24 August 2005 Cabinet report. Cabinet further required that a report be submitted to Cabinet on 14 December 2005 on the progress of the scheme, clarifying the costs, both revenue and capital, associated with the delivery of the Swindon Central Library and First Stop Shop project.
3.3The procurement implications, the subject of this report, are shown in detail in Appendix 1 (recommendations from project management consultants Faithful & Gould) and Appendix 2 (a Gateway 1 and 2 report prepared in collaboration with the Corporate Procurement Team and Technical Services Group, but not submitted to the Procurement Advisory Group for scrutiny).
4 Social, Environmental, Staffing, Legal/Human Rights, Risk and Other Implications
4.1Social Implications – Provision of a new Swindon Central Library will ensure the replacement of the existing life-expired Central Library temporary buildings, and will contribute to the cultural and economic regeneration of the Town Centre.
4.2Environmental Implications – This project will replace the existing poor quality temporary buildings with permanent buildings sympathetically designed to complement the adjacent Grade 2 listed Town Hall.
4.3Staffing Implications – Major new libraries generate additional demand. New technology will ensure the minimising of additional revenue costs.
4.4Legal/Human Rights Implications – Approval of the preferred procurement route will lead into the tender process for the construction of the new building. The external project management consultants will manage the project, in accordance with legislation and the Council’s Standing Orders.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.